Affirmed by published opinion. Judge WILKINSON wrote the opinion, in which Chief Judge WILLIAMS and Judge ALARCÓN joined.
OPINION
This case involves a dispute between a rail carrier and a mine owner over payment for the relocation of the rail line that serves the mine. We affirm the district court’s judgment that the rail carrier is liable for the payment pursuant to a covenant in the original deeds of easement granting the carrier’s predecessor-in-interest a right-of-way across the mine’s property. We hold that enforcement of the covenant is not preempted by the Interstate Commerce Commission Termination Act, 49 U.S.C. § 10101 est seq., because it is not the sort of rail “regulation” contemplated by the statute and, as a voluntary agreement, does not “unreasonably interfere” with rail transportation. At the *215 same time, to honor the parties’ original bargain, we reject plaintiffs attempt to change the terms of the agreement by seeking treble damages for breach of the agreement under the North Carolina Unfair and Deceptive Trade Practices Act, N.C. Gen.Stat. § 75-1.1.
I.
A.
The plaintiff in this case, PCS Phosphate Company, Inc. (“PCS”) owns and operates the world’s largest phosphate mine. The mine was projected to produce over 3 million tons of phosphate annually. PCS is the successor-in-interest to the pri- or owners of the mine: Texas Gulf Sulphur Company and North Carolina Phosphate Corporation. As its predecessors did, PCS relies on rail transportation to ship raw materials and products to and from the mine.
The defendants are Norfolk Southern Railway Company and its parent corporation Norfolk Southern Railway Corporation (collectively referred to as “Norfolk Southern”). Norfolk Southern currently operates the rail line that serves PCS and received over $65 million in payments from PCS for shipments over the line between 2001 and 2006. Norfolk Southern is the successor-in-interest to Norfolk Southern Railway Company (“Old NS”) — the rail carrier that originally built and operated the line.
Old NS began constructing the 31.5 mile Lee Creek Rail Line to serve the mine in 1965 after receiving approval from the Interstate Commerce Commission. The last five miles of the line needed to cross land jointly owned by the mining corporations and others, so the land owners granted Old NS five deeds of easement to build the line across the land.
The first two deeds were executed on June 29, 1965 and used identical language. Another three deeds were subsequently executed using slightly different language. The deeds were all recorded in the Beaufort County Register of Deeds. They explicitly granted the easements to Old NS and “its successors and assigns” for as long as the easements “shall be used for railroad purposes and shall not be abandoned.”
The deeds also contained multiple covenants. Of relevance here, each of the deeds contained a covenant whereby Old NS agreed to relocate the rail line when the mine owners deemed it necessary to mine operations. The first two deeds stated:
If, after ten (10) years from the date of this instrument, either Grantor determines that all or any part of said right of way and easement interferes with its anticipated mining or processing operations in the Beaufort County, North Carolina area, then said Grantor shall notify Grantee in writing of its desire that the right of way and track be moved ... and Grantors shall provide Grantee with a right of way and easement over said new location and Grantee at its expense shall relocate the said track on the said new right of way ...
(emphasis added). The last three deeds contained a similar provision which stated, “[Old NS], at its expense, shall ... relocate the said track on the said new right of way.” With respect to the new location for the track, the deeds required that engineers from the mining company and Old NS would jointly determine the new location so that it would avoid “excessive curvature, grade and distances.” The three later deeds also required that the new location “not necessitate excessive or unreasonable filling or bridge building” and that the “relocation will not affect the abili *216 ty of [Old NS] to comply with its legal obligation to serve any existing customer then on its line.”
Old NS completed the line and provided rail service as the sole carrier on the line until 1977. At that point another carrier began operating after it was granted access to the line as a condition of Norfolk Southern’s acquisition of Old NS. In 1985, the mining corporations merged, and, in 1995, the new corporation was acquired and changed its name to PCS.
Years later, PCS conducted studies that confirmed it would need to mine under the rail line. It thus consulted engineers and drafted a proposal to relocate the line. After presenting the proposal to Norfolk Southern, PCS formally requested by letter on November 20, 2003, that Norfolk Southern pay to relocate the necessary portion of the line by mid-2007 so that the line would not interfere with mining operations.
Throughout discussions about the relocation, Norfolk Southern refused to pay to relocate the line. In a letter dated December 16, 2004, Norfolk Southern formally refused to relocate the line and explained that it was unsuccessful in securing third party funding for the relocation and therefore could not “economically justify bearing the costs of the relocation project.” Furthermore, due to the decreased profitability of the line, Norfolk Southern stated that if PCS would not fund the relocation itself, it would seek permission from the Surface Transportation Board (“STB”) to abandon the line. Norfolk Southern was aware that if it successfully abandoned the line, PCS would not be able to continue operating the mine because rail access was necessary to ship raw materials and products to and from the mine.
In an effort to mitigate its damages, PCS began constructing the relocated line at its own expense. Throughout the construction, PCS engineers sent details about the relocation to Norfolk Southern which initially stated in a letter that “the route proposed by PCS Phosphate is in general terms acceptable,” and never subsequently objected to the proposal.
B.
On May 6, 2005, PCS filed this suit in the United States District Court for the Eastern District of North Carolina premised on diversity jurisdiction, 28 U.S.C. § 1332. PCS claimed that Norfolk Southern was liable for the cost of the relocation due to breach of contract, breach of easement covenants, and unjust enrichment. In addition, PCS claimed that Norfolk Southern was liable for treble damages and attorneys’ fees under the North Carolina Unfair and Deceptive Trade Practices Act (“UDTPA”), N.C. Gen.Stat. § 75-1.1, id. at § 75-16.1.
While the suit was pending, on November 17, 2005, Norfolk Southern filed an application with the STB to abandon the Lee Creek Line under 49 U.S.C. § 10903. On December 7, 2005, the STB rejected the application as “substantially incomplete and defective” because (1) it was premised on Norfolk Southern’s liability for the relocation cost, but the liability needed to be resolved by a court, (2) it was not joined by the other rail carrier that serves the line, and (3) the necessary environmental report was deficient.
See Norfolk S. Ry. Co.—Abandonment—In
Beauf
ort County, NC,
Meanwhile, in the district court, after discovery was completed, PCS filed a motion for partial summary judgment on the breach of contract and breach of easement covenants claims, and Norfolk Southern filed a motion for summary judgment on all claims on the grounds that they were pre-empted by the Interstate Commerce Commission Termination Act (“ICCTA”), 49 U.S.C. § 10501(b), and lacked merit in any event. On September 28, 2007, the court held that PCS’s breach of contract, breach of covenants, and unjust enrichment claims were not preempted by the ICCTA, but the UDTPA claim was preempted.
See PCS Phosphate Co., Inc. v. Norfolk S. Corp.,
Because the court could not determine the amount of Norfolk Southern’s liability for breach of contract and breach of easement covenants on the summary judgment record, the court held a bench trial to determine damages on January 25, 2007. The court awarded a total of $18,790,893.90 in damages, which included $3,753,366.77 in prejudgment interest under N.C. Gen. Stat. § 24-5(a).
Both parties appeal. Norfolk Southern appeals the district court’s liability finding, damages calculation, and holding that the breach of contract and breach of covenants claims were not preempted by the ICCTA. PCS appeals the district court’s dismissal of its UDTPA claim on the merits and on preemption grounds.
1
We review the district court’s rulings on summary judgment
de novo. See Nourison Rug Corp. v. Parvizian,
II.
A.
Norfolk Southern contends that PCS’s claims for breach of contract and breach of easement covenants are preempted by the ICCTA. The Supreme Court has recognized that federal law can preempt state law expressly or by implication and that “the purpose of Congress is the ultimate touchstone in every pre-emption case.”
Altria Group, Inc. v. Good,
— U.S. —,
We first ask whether the ICCTA expressly preempts PCS’s breach of agreement claims. The “plain wording” of the statute “necessarily contains the best evidence of Congress’ preemptive intent,”
see CSX Tansp., Inc. v. Easterwood,
The ICCTA was passed in 1995 to terminate the Interstate Commerce Commission and replace it with the Surface Transportation Board. The “general jurisdiction” provision of the ICCTA states:
The jurisdiction of the Board over—
(1) transportation by rail carriers, and the remedies provided in this part with respect to rates, classifications, rules (including car service, interchange, and other operating rules), practices, routes, services, and facilities of such carriers; and
(2) the construction, acquisition, operation, abandonment, or discontinuance of spur, industrial, team, switching, or side tracks, or facilities, even if the tracks are located, or intended to be located, entirely in one State,
is exclusive. Except as otherwise provided in this part, the remedies provided under this part with respect to regulation of rail transportation are exclusive and preempt the remedies provided under Federal or State law.
49 U.S.C. § 10501(b) (emphasis added).
The express preemption clause focuses specifically on “regulation.”
Id.
The STB’s interpretation of this provision, on which courts rely,
see Green Mountain R.R. Corp. v. Vermont,
Voluntary agreements between private parties, however, are not presumptively regulatory acts, and we are doubtful that most private contracts constitute the sort of “regulation” expressly preempted by the statute. 2 If contracts were by definition “regulation,” then enforcement of every contract with “rail transportation” as its subject would be preempted as a state law remedy “with respect to regulation of rail transportation.” 49 U.S.C. § 10501(b). Given the statutory definition of “transpor *219 tation,” this would include all voluntary agreements about “equipment of any kind related to the movement of passengers or property, or both, by rail.” See 49 U.S.C. § 10102(9) (defining “transportation”). If enforcement of these agreements were preempted, the contracting parties’ only recourse would be the “exclusive” ICCTA remedies. But the ICCTA does not include a general contract remedy. 3 Such a broad reading of the preemption clause would make it virtually impossible to conduct business, and Congress surely would have spoken more clearly, and not used the word “regulation,” if it intended that result.
The history and purpose of the ICCTA support the view that Congress did not intend to preempt all voluntary agreements concerning rail transportation. The ICCTA was enacted in 1995 to deregulate the rail industry by eliminating direct economic regulation of railroads by the states.
See Fla. E. Coast Ry. Co.,
In examining a statute with a similar deregulatory purpose, the Supreme Court held that the Airline Deregulation Act did not preempt breach of contract claims.
See American Airlines, Inc. v. Wolens,
The STB itself has emphasized that courts, not the STB, are the proper forum for contract disputes, even when those contracts cover subjects that seem to fit within the definition of “rail transportation.”
See, e.g., The N. Y, Susquehanna & W. Ry. Corp.
—Discontinuance
of Service Exemption,
In fact, when the STB reviewed Norfolk Southern’s application to abandon the Lee Creek Line it implied that a court should determine whether Norfolk Southern is contractually liable for the relocation costs. The STB stated that the application was “premature and incomplete” because Norfolk Southern could “not claim relocation costs as a burden on continued operation unless the court determines that it is obligated to pay to relocate the line.”
See Norfolk S. Ry. Co.
—Abandonment—In
Beaufort County, NC,
We thus decline to view private contracts as presumptively regulatory. Whether “regulation” must always be by way of public rule is a question beyond the scope of this suit. In certain circumstances, courts have held that common law regulation through negligence and nuisance actions was preempted by the ICC-TA.
See, e.g., Friberg v. Kansas City S. Ry. Co.,
B.
Having concluded that enforcement of the relocation agreements is not expressly preempted, we move on to whether it is impliedly preempted. An express preemption clause does not bar a finding of implied preemption.
See Sprietsma v. Mercury Marine,
In this case, the factual assessment is simple because the remedy sought is enforcement of a voluntary agreement. The relocation agreements were freely negotiated between sophisticated business parties. The agreements envisioned this exact circumstance — that many years after the agreements were made, the railroad would have to pay to relocate this portion of the line. We can assume, therefore, that the agreements reflect a market calculation that the benefits of operating the rail line for many years would be worth the cost of paying to relocate the line in the future. In the context of the Commerce Clause, whether a particular regulation imposes an “unreasonable burden” on interstate commerce depends on whether the burden on interstate commerce imposed by the regulation outweighs the local benefits it provides.
See Pike v. Bruce Church, Inc.,
As the STB has recognized, “voluntary agreements must be seen as reflecting the carrier’s own determination and admission that the agreements would not unreasonably interfere with interstate commerce.”
Township of Woodbridge v. Consolidated Rail Corp.,
This approach to voluntary agreements is not an arbitrary or categorical distinction. Instead, it reflects the fact that market actors have incentives to enter into efficient arrangements.
See Wolens,
III.
We thus reject Norfolk Southern’s preemption claims and turn to the merits. Norfolk Southern contends that it is not liable for breach of contract or breach of easement covenants because the covenants are not enforceable against it. It argues that the relocation covenants are personal covenants that only apply to the original covenanting parties, and the district court therefore erred when it held that the covenants bind Norfolk Southern as real covenants that run with the land.
See Runyon v. Paley,
We reject this argument because it ignores both the language and purpose of the agreement. The deeds of easement must be considered as a whole,
see Weyer-haeuser Co. v. Carolina Power & Light Co.,
A covenant such as this, that protects the physical value of the land, is typical of a covenant that runs with the land.
See Runyon,
Norfolk Southern also argues variously that the covenants are not valid against Norfolk Southern because of the reasonable time restriction on contracts, the doctrine of laches, and the doctrine of changed circumstances. These doctrines do not apply. First, the reasonable time restriction on contracts does not bar enforcement of the covenants against Norfolk Southern because, as discussed, they were intended to be enforceable against subsequent land
*223
owners as real covenants in order to protect the long-term interest in mining.
See Rodin v. Merritt,
We therefore conclude that the district court properly held that the relocation covenants were enforceable against Norfolk Southern as the successor-in-interest to the rail easements.
See Runyon,
IV.
We next turn to Norfolk Southern’s appeal of the district court’s calculation of damages at the bench trial. First, Norfolk Southern argues that the district court incorrectly calculated compensatory damages because it included costs of portions of the line that were not necessary to replicate the old line and therefore gave PCS more than the benefit of its bargain.
See Wise,
Second, Norfolk Southern argues that the district court incorrectly applied North Carolina’s prejudgment interest statute as of the date that Norfolk Southern breached the agreement rather than in stages based on the dates that PCS actually spent money constructing the relocated line. Norfolk Southern ignores the language of the statute which provides: “In an action *224 for breach of contract ... the amount awarded on the contract bears interest from the date of breach.” N.C. Gen.Stat. 24-5(a). The district court followed the statute precisely. The court calculated prejudgment interest as of December 16, 2004, which is when Norfolk Southern informed PCS by letter that it would not relocate the line. We therefore affirm the court’s calculation of damages.
V.
On cross-appeal, PCS argues that the district court erred by rejecting its UDTPA claim on the merits and by holding that its UDTPA claim was preempted by the ICCTA. In its complaint, PCS alleged that Norfolk Southern committed unfair and deceptive trade practices under N.C. Gen.Stat. 75-1.1 when it “willfully breached” its obligations under the relocation agreements and threatened to abandon the Lee Creek Line.
This claim is simply an attempt to multiply the damages for an ordinary breach of an agreement by re-characterizing the breach as a violation of the UDTPA. North Carolina law forbids this.
See Broussard v. Meineke Discount Muffler Shops, Inc.,
PCS attempts to show “substantial aggravating circumstances” by pointing to the fact that Norfolk Southern threatened to abandon the Lee Creek Line if PCS forced it to pay for the relocation. PCS argues that these statements were coercive because if Norfolk Southern had successfully abandoned the line, it would have cut off essential rail access to the mine. But these alleged threats are nothing more than Norfolk Southern stating that it believed it had a separate legal right to abandon its own tracks. The basis for PCS’s claim therefore is nothing more than two companies fighting over the enforceability of an agreement. Although we hold that the agreement is enforceable, we will not re-write the parties’ agreement by awarding treble damages for the breach thereof. 5
*225
Moreover, the relocation covenants are far from the reach of the UDTPA because they are wholly divorced from the context of consumer transactions. The UDTPA “was intended to benefit consumers,”
see Dalton v. Camp,
VI.
At bottom, this case involves straightforward breach of covenant or contract claims. The carefully negotiated bargains that are at the center of these agreements drive our conclusions — Norfolk Southern cannot escape its obligation by disputing the parties’ intent or hiding behind the ICCTA, but, just the same, PCS cannot enlarge the scope of Norfolk Southern’s obligation by transforming a breach of covenant claim into a UDTPA action for treble damages and attorneys’ fees. Instead, the parties must fulfill their contractual commitments — the law knows few more basic principles. For these reasons, we affirm the judgment.
AFFIRMED
Notes
. Because PCS does not appeal the district court's dismissal of its unjust enrichment claim, that claim is not before us.
.
The preemption text at issue here differs from the phrase "all other law" interpreted in
Norfolk and W. Ry. Co. v. American Train Dispatchers Ass’n,
. 49 U.S.C. § 11704 provides a cause of action for a person injured by a rail carrier that "does not obey an order of the Board,” id. at § 11704(a), and for a person that is injured by “an act or omission of [a rail] carrier in violation of this part,” id. at § 11704(b). Neither of these remedies would apply to breach of a private contract.
. PCS styled its claims for breach of the relocation agreements as both a breach of contract claim and a breach of easement covenants claim. Without differentiating between the two, the district court held that Norfolk Southern was liable on both grounds.
. Recognizing that an award of extraordinary damages re-writes a contract and destroys the voluntary nature of the agreement, courts have held that an award of extraordinary damages for a breach of contract can amount to preempted “regulation” within the meaning of § 10501(b).
See Pejepscot Indus. Park, Inc.,
