Defendants appeal from a judgment entered pursuant to a stipulation in an action to fqreclose a mechanic’s lien. The stipulation, which was in writing, dated April 20, 1949, and filed in the action, contained recitals that plaintiff, as contractor, and defendants, as owners, had entered into a contract for the building of certain improvements in the city of Palm Springs; that during the course of construction disputes had arisen between the parties as to changes *653 made in the building, extras furnished, charges made, alleged interference by the owners with the work, and alleged failure of plaintiff to complete the construction according to the terms of the contract; that the owners refused to pay plaintiff’s claimed balance due on the contract; that plaintiff had filed a suit to foreclose a mechanic’s lien on the premises; that the contractor and owners had agreed that their various disputes should be settled by arbitration and that the decision of the arbitrators should be final and entered as a judgment in the foreclosure action. It was then stipulated that the moneys due one party by the other under the contract should be determined by three named arbitrators; that upon arriving at a decision the • amount determined to be due should be entered as a judgment in favor of the party found to be “entitled in the within action”; that the findings and award of the arbitrators should be written and signed by each of the arbitrators; that all items of costs and interest allowable in the event the action should have been tried before the court should be awarded to the parties entitled thereto and that all other expenses of the arbitrators should be borne equally by the plaintiff and the defendants.
The arbitrators conducted hearings, received evidence, and on July 12, 1950, submitted an award in writing in which they found in favor of plaintiff in the sum of $3,633.42, with interest, filing fees $20.60, “costs in the sum of $300. Arbitrators. (2).”
The award was submitted to the attorney for the defendants and on July 19, 1950, returned by him to the attorney for the plaintiff. Apparently, no objections were made to the award by the attorney for the defendants and it was filed in the action on July 25, 1950, and on the same day the court entered judgment for the amount found due in accordance with the stipulation of the parties. Thereafter, on August 14th, the defendants filed a notice and motion to vacate the award of the arbitrators and on the same day filed a motion to set aside the entry of the judgment on the ground that no notice of motion for an order confirming the award of the arbitrators had been served on the defendants or their attorney in compliance with section 1287 of the Code of Civil Procedure. These motions were supported by affidavits in which it was claimed, among other things, that the arbitrators had failed to properly conduct the arbitration proceedings and make proper findings therein; that they failed to allow certain credits claimed by the defendants; that a *654 mutual final and definite award upon the subject matter was not made and that the defendant Marie Malley did not sign the stipulation for arbitration. These motions were denied by the court and this appeal, which is from the judgment entered on July 25, 1950, was filed.
No reporter’s transcript was filed and the record consists of the clerk’s transcript and affidavits which were filed by the attorney for the plaintiff in opposition to the motions.
Appellants first contend that the arbitrators, in making the award, failed to comply with the directions of submission as contained in the stipulation and argue that by the stipulation the issues submitted to the arbitrators for settlement were “(a) Extras furnished and their value; (b) Unauthorized departure from plans and specifications and amount of damages of any allowable to owner for such departure; (c) Total amount remaining due on the contract or owners.” The record, however, does not show a failure to consider these three issues and the total amount remaining due on the contract was definitely set forth in the award made. In this connection, it is contended that there should have been written findings on the issues set forth. The affidavits filed by plaintiff and used in the hearings on the motion indicate that findings such as contended for by the defendants were waived by the attorneys in the hearings before the arbitrators. The defendants contend that these affidavits cannot be considered as part of the record on appeal and in that connection cite
Smith
v.
Halstead,
It is next argued that the judgment based on the award is void in that there was a failure to comply with the provisions of the arbitration sections (1280 to 1293, inclusive) of the Code of Civil Procedure. The stipulation contains no reference to the arbitration sections of the code and there is nothing in it indicating that proceedings would be taken
*655
to confirm, vacate, modify or correct the award in accordance with the provisions of said sections. As noted, the stipulation provided that “upon arriving at a decision, the amount determined to be due shall be entered as a judgment in favor of the party found to be entitled in the within action. ’ ’ No objections were made to the award or to the entry of the judgment thereon prior to the filing of the motions referred to. As was said in
Dore
v.
Southern Pac. Co.,
“At common law it is competent for persons to submit any question or matter of difference between them to the decision of third persons, whether it could be the subject of an action or not, and when they have done so, the decision will be binding upon them. ’ ’
Finally, it is argued that the judgment based on the award is void for the reason that the respondent failed, to present evidence to the trial court that he was a duly licensed contractor and in this connection the case of
Franklin
v.
Nat C. Goldstone Agency,
Judgment affirmed.
Barnard, P. J., and Griffin, J., concurred.
