This was an action by the appellants to. enjoin the collection of an assessment for benefits under the acts for the construction of turnpike roads, 1etc. The complaint contains an allegation, that all the lands within one mile and a half of the road were not examined, viewed, or assessed by the assessors ; that there was omitted from their list one thousand acres lying within that distance from the road.
The answer as filed was in five paragraphs, but the first, second, and third paragraphs were withdrawn, leaving only the fourth and fifth. The fourth is pleaded as an estoppel, alleging that the appellants were stockholders; that they had paid a part of the assessments; and that they had stood by and seen the work of constructing the road proceed without objections, etc.
We do not deem it necessary to discuss the questions in the answer, as they have been fully considered in the cases of Hopkins v. The Greensburgh, Kingston, and Clarksburg Turnpike Company, 40 Ind. 44, and The Greensburgh, Milford, and Hope Turnpike Company v. Sidener, 40 Ind. 424.
In the fifth paragraph of the answer, it is alleged that one
What we have said about the fourth is applicable to the fifth paragraph. The allegations about the board of equalization cannot affect the case. That board had no power to assess any lands omitted by the assessors. They could only equalize those assessed.
The complaint was good, and the demurrer to it was correctly overruled.
The judgment of the Decatur Common Pleas Court is reversed, with costs. Cause remanded, with instructions to> the court below to sustain the demurrers to the fourth and; fifth paragraphs of the answer, and for further proceedings, etc.