This was an action in equity to obtain the cancellation of a special taxbill for $51.48, issued by the city of Joplin for the construction of a sewer which was laid along an alley back of appellant’s property, the grounds alleged for relief being that said taxbill was void and constituted a cloud on appellant’s title. Defendant, the owner of the taxbill, prevailed before the chancellor, and the case is be
“11. The first party shall not be entitled to any claim for damages for any hindrance or delay, from any cause whatever, in the progress of the work, or any portion thereof, but such hindrance may entitle such first party to an extension of time for completing this contract sufficient to compensate for this detention, the same to be determined by the city engineer, provided he shall have immediate notice in writing of the cause of the detention.
‘ ‘ 12. The work embraced in this contract shall be begun within one week after written notice so to do shall have been given to the contractor by the city engineer, and carried on regularly and uninterruptedly thereafter (unless the said engineer shall otherwise in writing specially direct) with such a force as to secure its full completion by July 25, 1907, thereafter, the time of beginning, rate of progress, and time of completion being essential conditions of this contract. And if the contractor shall fail to complete the work by the time above specified, the sum of five dollars per day for each and every day thereafter until such completion, shall be deducted from the moneys payable under the contract. ’ ’
The record furnished us does not show when the city engineer gave the written notice to the contractor to commence work or when work was actually begun. The work was not completed on July 25, 1907. The evidence shows that on August 20, 1907, a request for an extension of sixty days was filed by the defendant with the city council, reciting that on account of delay caused by failure of pipe to arrive in time and scarcity of men, it had been impossible to complete the’
Ajjpellant contends that time is of the essence of the contract in question, and that the city council could not extend the time for completing the work after the original time mentioned in the contract had expired.
This case stands on the border-ground of a number of decisions in this state concerning the branch of taxbill law which has to do with the timely completion of public improvements according to the provisions of the several ordinances and contracts. The general principles have been iterated and reiterated in the following cases: Heman v. Gilliam, 171 Mo. 258, 71 S. W. 163, and cases cited; Allen v. Labsap, 188 Mo. l. c. 695, 87 S. W. 926; Gilsonite Construction Co. v. Coal Co., 206 Mo. l. c. 75, 103 S. W. 98; Brigham v. Hickman, 136 Mo. App. 216, 116 S. W. 449.
In this case, as in that of Allen v. Labsap, supra, no special or general ordinance of the city authorizing the improvement was put in evidence making time of the essence of the transaction or requiring the work to be commenced by a day certain or completed by a
The question whether the council could, after the time specified in the contract had expired, in the absence of an ordinance provision fixing a time for completion, lawfully extend the time, was considered by the Supreme Court in the case of Gilsonite Construction Co. v. Coal Co., supra, where the following appears : “ . . .the common council did, on the 8th of June, 1897, pass an ordinance extending the time for the completion of the work until June 20', 1897, but this ordinance was passed after the expiration of the time limited by the express provisions of the com tract, and after all the extensions granted by the city engineer had expired, and this court has ruled in Neill v. Gates, 152 Mo. l. c. 592, and Hund v. Rackliffe, 192 Mo. l. c. 324, 325, that it is not within the power of the municipal corporation to extend the time by ordinance for the completion of work after the time for completing it has expired ; but if it should be said that the last-two cases should be limited to cases in which the time was specified by ordinance, and that when the common council granted this last extension on June 8, it was a legitimate determination of what constituted a rea-sonable time, the plaintiff is still confronted with the fact that the contractor did not complete the work within the time fixed by the ordinance of June 8,
So it may be considered as settled in this state that when time is not of the essence of the contract, an extension, to be legal, must be made before the expiration of the period named in the contract.
But it does not necessarily follow that the taxbill in question should be declared void. There being no time for completion fixed by an ordinance provision, the delay, in order to invalidate the taxbill, must have been an unreasonable one, according to the authorities herein cited. The evidence in this record nowhere shows when, according to the contract, the city engineer gave the written notice to the contractor to begin work. The contract provision is that the contractor shall begin work within one week after written notice so to do shall have been given by the city engineer. Are we expected to speculate as to when the city engineer gave the notice? Certainly the contractor could not lawfully begin the work until such notice was given. If, perchance, the notice was not given until
