Paul Sardella Construction Co. v. Braintree Housing AuthorityPaul Sardella Construction Co. v. Braintree Housing Authority
A judge of the Superior Court ruled, as matter of law, that the Braintree Housing Authority (authority)
2
was liable in damages for breach of contract to Paul Sardella Construction Co., Inc. (Sardella), for wrongfully rescinding the award to Sardella of a contract for the construction of a State-aided housing project for the elderly.
3
The matter was reported to the Appeals Court pursuant to
We summarize the facts, as stated in the opinion of the Appeals Court, ‘
Sometime prior to September 15, 1971, the authority invited bids pursuant to the provisions of the fair competition for bidders of public works act (
On September 29, 1971, Mazza wired the authority purporting to withdraw its subbid on the basis of an alleged clerical error, and confirmed that action by a letter sent the following day.
On October 20, 1971, the authority voted to award the contract to Sardella as the lowest responsible and eligible general bidder. See
Mazza failed to execute the subcontracts within five days (
Thereafter, the authority reviewed all the other eligible and responsible plumbing subbids and determined that if any one of those bids was to be substituted in place of Mazza’s, Findlen’s bid would be the lowest general bid. The authority then voted on November 24,1971, to rescind its award of the general contract to Sardella and to award that contract to Findlen. Sardella was not invited to nor was it represented at the meeting at which such votes were taken. A notice of the decision was mailed to Sardella, and it immediately lodged a protest with the Department of Labor and Industries, which conducted an investigation and held a conference on December 7, 1971. See
At a meeting held on December 15, 1971, the authority found that “a bona fide clerical error had been made by Mazza” and voted to return Mazza’s deposit (which it subsequently did). See
On January 20, 1972, the authority and Findlen executed a contract for the project. The contract was approved by the Department of Community Affairs. Findlen has been paid the contract price, with the exception of a small amount held back pending the completion of certain seeding operations.
Both Sardella and Findlen were eligible and responsible bidders at all material times. 4
*239
We conclude that there was no error. In reaching that conclusion we agree with the result, and in general we agree with the reasoning, of the Appeals Court. However, we expand somewhat on the analysis of the Appeals Court in support of our determination that
Preliminarily, we observe that Sardella could not prevail, at least in the circumstances of this case, if it were determined that
The trial judge framed the crucial issue in this case in this way: “[W]here a sub-bidder of the lowest responsible and eligible general bidder refuses to execute his subcontract, should the procedures of
The arguments in support of the application of
From this contention, it is argued that
Nevertheless, we recognize compelling reasons why
Convincing support for this result is found in language added to
The only substantial argument against applying
Since it is established that
We agree with the Appeals Court that in circumstances like those of the instant case the proper remedy is to allow recovery of the cost of preparing the general contractor’s bid. See Paul Sardella Constr. Co. v. Braintree Housing Authority, supra at 833, 834, and cases and authorities cited. We need not elaborate on the reasoning advanced by the Appeals Court beyond noting that this measure of damages is the fairest in all circumstances, is consistent with the public interest, and furthers the legislative objectives underlying the fair competition for bidders of public works act.
The case is remanded to the Superior Court for the entry of judgments declaring that Findlen and Mazza are not liable to Sardella and for a determination of the damages to be awarded to Sardella from the authority in accordance with the principles set forth in this opinion.
So ordered.
Notes
The judge ruled that neither Findlen nor Mazza was liable in damages to Sardella. These rulings were held to be correct by the Appeals Court,
Paul Sardella Constr. Co.
v.
Braintree Housing Authority,
Bids were invited and the contract was awarded pursuant to the provisions of
No facts relating to damages were stipulated. The parties agreed that, if the trial judge found liability, evidence relating to damages could be introduced at a later date. The Appeals Court decided the *239 issue of the proper measure of damages on its own motion. Before us on further appellate review the parties have briefed and argued the question, and we consider it open for us to determine.
The authority’s vote of October 20, 1971, was subject to the approval of the Department of Community Affairs, and thus it is argued that no final award of the contract was made.
Presumably this language of amendment was impelled by a decision of this court which effectively stripped such a general contractor from protection against later invalidation of the contract if it were discovered that the general contract was awarded on the basis of an invalid subbid.
Grande & Son
v.
School Housing Comm. of N. Reading,
In material part the language of