This dispute arises out of an unsuccessful attempt to lay a 66-inch diameter concrete sewer pipe along a route almost two miles long in Mayaguez, Puerto Rico. The plaintiff, Paul N. Howard Company (“How *882 ard”), was hired by the defendant, the Puerto Rico Aqueduct and Sewer Authority (“PRASA”), to construct the pipeline. Howard claims that due to an unexpected site condition it was impossible to build the sеwer in compliance with contract specifications. Howard brought this suit seeking partial rescission of the contract and compensation for extra costs incurred as a result of design changes ordered by PRASA after construction began.
The district court for the District of Puerto Rico entered a judgment in favor of Howard in the amount of about $4 million. The district court also awarded Howаrd attorney’s fees “in view of the temerity and obstinacy displayed by [the] defendant”.
PRASA appeals, arguing that the district court erred in holding that the terrain at the foot of the embankment of P.R. Highway No. 2 constituted a differing site condition and in holding that it was impossible to lay the sewer along the straight line specified in the contract. PRASA also challenges the district court’s award of costs incurred by Howard as а result of PRASA’s decision to increase the required load capacity of the sewer’s supporting piles and argues that the district court abused its authority in awarding attorney’s fees. Finally, PRASA argues that as an instrumentality of the government of Puerto Rico it is immune from a suit for damages in federal court under the Eleventh Amendment. We reject each of these claims and affirm the judgment of the district court.
Differing Site Condition
The оriginal contract called for Howard to lay the sewer line parallel to P.R. Highway No. 2 for a distance of over 500 meters. Howard was expected to dig a ditch about forty feet deep at the toe of the highway embankment,’ drive piles to support the pipeline, place the pipeline on top of the piles at the bottom of the ditch, and then backfill the ditch with earth, burying thе pipeline. It was Howard’s obligation under the contract to design and use a sheet piling system which would support the wall of the excavation during construction. Howard did design and use such a system, but shortly after Howard began excavation at the toe of the highway embankment it settled, pushing the sheet piling system into the excavation and causing the highway itself to settle. Howard then backfilled the trench to prevent further damage to the highway, and notified PRASA that it had encountered a “differing site condition” 1 , requiring modification of the contract terms. PRASA ordered Howard to further backfill the excavation to an elevation higher than the surrounding ground level, but disputed Howard’s claim that the tendency of the highway embankment to slide constituted a differing site condition.
Both parties retained soil experts to invеstigate the cause of the settlement of the highway embankment. In their discussions PRASA insisted that the settlement was caused by Howard’s use of an inadequate sheet piling system, while Howard argued that given the structure of the highway embankment and the nature of the soil conditions at the site, it would be impossible to lay the pipeline as planned without causing some settlement of the highway and displacement of thе pipeline.
After an impasse of more than four months, PRASA and Howard agreed that Howard would make another attempt to lay the pipeline along the highway. This time Howard limited its excavation, removing only enough earth to allow it to install one section of pipe at a time. Howard’s soil consultant was at the site and directed a significant portion of this second excavation. Bеtween February 18, 1980 and March 3, 1980, Howard installed nine sections of pipe without experiencing any lateral displacement. Highway settlement *883 was limited to a maximum of ih" during that period. But after the sheet piling was removed, as required by the contract, the highway settled 15" and the pipeline was displaced laterally. At the time the parties believed that the pipeline was 14" off center. More recent measuremеnts indicate that the lateral displacement did not exceed 7".
PRASA did not consider this deviation from the design specifications acceptable and refused to approve or pay for Howard’s work in this area of the project. Howard abandoned the construction site in December, 1980 after having spent more than five months in an unsuccessful attempt to obtain a change order from PRASA. This lawsuit followed.
The district court held in Howard’s favor, concluding that it was not possible for Howard to construct the pipeline along the route designated by PRASA in the manner specified in the contract without causing settlement of the highway embankment and displacement of the pipeline. The district court found that the instability of the highway embankment constituted a differing site condition justifying rescission оf that part of the contract that required Howard to lay the pipeline along the highway embankment and rejected PRASA’s contention that it was the design of Howard’s sheet piling system that was responsible for Howard’s difficulties. In coming to this conclusion, the district court relied on expert testimony that the tendency of the highway embankment to slide was unusual and unpredictable, and that only by changing the course of the pipeline or leaving the sheet piling in place could lateral displacement of the pipeline be prevented. The court also relied on testimony describing the difficulties another construction company encountered when it attempted to lay this section of the pipeline several years after Howard had abandoned its attempt.
On appеal PRASA attacks the district court’s conclusion that the conditions encountered by Howard were unusual and unpredictable and that construction of the pipeline according to the design plans was impossible. After reviewing the record, we reject PRASA’s contentions. It is not our task to reweigh the evidence presented to the district court. We may alter that court’s judgment only if it applied аn erroneous legal standard or committed a clear error in its findings of fact. We have not been referred to, nor have we found, any evidence indicating that the district court made either of these errors.
As noted by the trial judge in his findings of fact, there was expert testimony to the effect that the instability of the highway embankment was unusual and unexpected:
“It is my opinion that the designers of this projeсt did not anticipate the events which we have observed. And I do not mean that to be critical because I do not think they should be severely faulted for that. The condition which we find is not common. I do not think that the contractor anticipated the occurrences which we observed. I do not think that the soil consultant anticipated the conditions which we observed. In short, I don’t [think] anybody anticiрated what we have observed.
“[I]n October of 1979, we all suddenly learned a lesson.” Testimony of Sydney M. Johnson, VI Joint Appendix 1736-37.
Given this and other testimony describing the uncommon instability of the highway embankment, we believe that the requisite elements of a differing site claim were established.
See William A. Smith Contracting Company v. United States,
We must also reject PRASA’s claim that it was Howard’s sheet piling system, rather than the nature of the embankment, that caused the construction difficulties. Although there was testimony indicating that different sheet piling systems might have prevented the highway from settling and the pipeline from shifting, other experts indicated that these othеr systems would have been impractical or ineffective *884 and that only changing the route of the pipeline or leaving the sheet piling in place could ensure the success of the project. Under these circumstances we have no hesitation in affirming the district court’s conclusion that Howard’s sheet piling system was not the cause of the settling and shifting.
Finally, we reject PRASA’s contention that the district court improperly based its finding of impossibility on an “insignificant defect” — the 7" lateral deviation in the pipeline. Inasmuch as PRASA refused to accept the pipeline with that deviation, and inasmuch as PRASA ordered Howard not to proceed unless it could prevent the embankment from sliding, we think the district court was justified in concluding that it was impossible to lay the pipeline within the tolerances dеemed acceptable by PRASA.
Accordingly, we find no error in the district court’s award of costs incurred by Howard as a result of the differing site condition encountered.
Change in Pile Capacity
The second group of claims raised in this appeal challenge the district court’s award to Howard of the extra costs it incurred as a result of PRASA’s instruction that some of the piles used to support the pipeline be a highеr “ultimate capacity” 2 than was required by the original contract. PRASA argues that Howard should not have been allowed to recover its increased costs because there was a patent ambiguity in the contract documents that should have put Howard on notice that an ultimate capacity of more than 100 tons might be required. PRASA also contends that the district court erred in allowing Howard to recover extra costs incurred due to its inability to use a “follower” 3 to drive the higher capacity piles, and in calculating the amount Howard is entitled to recover.
15] We have carefully reviewed PRASA’s claims, but we decline to disturb the district court’s award. There is a wealth of evidence in the record to support the court’s finding that PRASA raised the required ultimate capacity of some of the piles from 100 tons to 135 tons after the contract was signed. PRASA’s argument that the contract documents were ambiguous appears to have been raised for the first time on appeal and is therefore barred.
Johnston v. Holiday Inns, Inc.,
The evidence also supports the court’s conclusion that the change to piles of 135 ton ultimate capacity significantly increased Howard’s construction costs. Under these circumstances Howard was entitled to an equitable adjustment. The district court did not err in making that calculation. PRASA’s delay in notifying Howard of the change in the required pile capacity and its failure to produce design calculations at trial justify the court’s conclusion that PRASA breached its contractual obligations to Howard.
PRASA claims that Howard should not be able to recover any extra costs incurred as a result of its inability to use a follower because the contract provided that use of a follower should be avoided. PRASA argues that if Howаrd submitted its bid in reliance on its use of a follower, it did so at its own risk and thus should be barred from any recovery on this ground. We disagree.
The district court properly found that the use of a follower is a customary *885 technique, which Howard could reasonably have expected to use with success on this project in driving piles with a 100-ton ultimate capacity. The contract did not absolutely bar use of the fоllower; it merely required that Howard obtain PRASA’s permission before using the technique. Since Howard knew that permission could not be unreasonably withheld, it was entitled to bid in reliance on use of the technique. Indeed, PRASA did agree to use of the follower and substantial evidence at trial indicated that such use would have been successful if PRASA had not subsequently increased the ultimate capacity requirеment for some of the piles. On this record we think Howard was entitled to recover the extra costs it incurred due to its inability to use a follower.
Finally, we reject PRASA’s claim that the district court improperly calculated the costs recoverable by Howard due to the pile capacity change. PRASA argues that Howard failed to establish the essential prerequisites to a claim for total costs. As the district court noted, in order for Howard to recover all the extra costs it incurred in driving the 135-ton ultimate capacity piles, it had to prove that:
“(1) the nature of the particular losses make it impossible or highly impracticable to determine them with a reasonable degree of accuracy; (2) the plaintiff’s bid or estimate was realistic; (3) its actual costs were reasonable; and (4) it was not responsible for the added expenses.” Moorhead Construction Company, Inc. v. City of Grand Forks,508 F.2d 1008 , 1016 (8th Cir.1975) (citations omitted).
We agree with the district court that Howard satisfied this standard.
PRASA points out that the district court based its finding that Howard’s original bid was realistic on the fact that it was accepted. While we agree that the mere fact that a bid was accepted does not demonstrate that it was reasonable, we think the record mandates the conclusion that Howard’s bid was not unrealistically low. Specifically, we find persuasive the testimony that Howard’s bid was in line with the three other bids PRASA received. It was slightly higher those that submitted by two of the three unsuccessful bidders and slightly lower that submitted by the third.
Nor do we accept PRASA’s contentions that Howard’s actual costs were unreasonable and that Howard was responsible for the additional expenses. On the basis of all the evidence the district court concluded that Howard’s extra costs were reasonable. As we have noted above, it is not our function to try this case de novo. Based upon our review of the parties’ briefs and the record, we find no reason to doubt the district court’s conclusion.
Award of Attorney’s Fees
Relying on Rule 44.4(d) of the Puerto Rico Rules of Civil Procedure, 32 L.P.R.A. Appendix II, which provides that a court mаy impose attorney’s fees “[wjhere a party has been obstinate”, the district court awarded Howard attorney’s fees on account of PRASA’s “temerity and obstinancy”.
We have previously warned of the dangers of the over-application of this rule and indicated that explicit findings should be made to justify such an award.
Carrillo v. Sameit Westbulk,
Although we do not lightly endorse an award of fees under Rule 44.4(d) in a complex, hard fought case such as the one before us, we believe that the court’s findings, as supplemented by the record, are adequate to suppоrt its award of attorney’s *886 fees. We note particularly that the record supports the court’s findings and that it contains at least three warnings from three different judges regarding the possibility that sanctions would be imposed if the parties did not cooperate in expediting this litigation.
Eleventh Amendment
PRASA’s final argument is that it is immune from suit in federal court under the Eleventh Amendment. This claim is raised for the first time on appeal, but inasmuch аs it challenges the jurisdiction of this court, we must consider it.
E.g., Edelman v. Jordan,
We doubt that PRASA is sufficiently an arm of the state to qualify for the protection of the Eleventh Amendment.
See generally,
13 C. Wright, A. Miller & E. Cooper,
Federal Practice and Procedure
§ 3524 (1975) (discussing the factors considered in determining whether the state is the rеal party in interest in a particular case). An autonomous governmental corporation, such as PRASA, which was established to provide drinking water and sewage facilities for the people of Puerto Rico,
see
22 L.P.R.A. § 141-68 (“Aqueduct & Sewer Act of Puerto Rico”), is not normally immune from suit in federal court. 13 C. Wright, A. Miller & E. Cooper,
Federal Practice and Procedure
§ 3524, at 87 (1978). PRASA receives periodic appropriations from the state treasury, but it is financially independеnt of the Commonwealth. It has no power to pledge the credit or taxing power of the Commonwealth and the bonds it issues are its debts alone. PRASA’s operations generate substantial revenue, and it does not seriously dispute Howard's assertion that the judgment rendered in this case will be paid out of PRASA’s funds, rather than those of the Commonwealth. Taken together these facts might well lead us to conсlude that PRASA is not an alter ego of the state and therefore does not qualify for immunity under the Eleventh Amendment.
See, e.g., Miller-Davis Company v. Illinois State Toll Highway Authority,
We need not take that step today, however, because we conclude that PRASA has waived any protection it may or may not enjoy under the Eleventh Amendment by its conduct during this litigation. There is no question that a state may waive its Eleventh Amеndment immunity,
e.g., Pennhurst State School & Hospital v. Halderman,
— U.S. -, -,
The judgment of the district court is affirmed. Costs shall be borne by appellant.
MEMORANDUM AND ORDER
Having carefully considered the petition of Puerto Rico Aqueduct and Sewer Authority (PRASA) for rehearing, we determine that it should be denied. We perceive no ground for reconsidering our conclusions with respect to the existence of a differing site condition, and we remain equally convinced that PRASA enjoys no Eleventh Amendment immunity.
With respect to the latter issue, we note that- the Supreme Court of Puerto Rico has in two persuasive opinions reasoned that PRASA, by statute is a public corporation, “a personality separate and apart from that of the government”, which statute “depriv[es] it of the protection of
*887
sovereign immunity traditionally enjoyed by the State.”
Canchani v. C.R.U.V.,
Accordingly, PRASA’s petition for rehearing is denied.
Notes
. The contract between Howard and PRASA incorporated the standard definition of differing site conditions defining them, in part, as "unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract”.
. The term "ultimate capacity” refers to the greatest weight a pile will support without failing.
. A “follower" acts as an extension of the top of the pile and permits the pile tо be driven below the surface of the ground. Howard intended to use a follower to drive the pipeline's supporting piles before beginning excavation. That techñique is more efficient and less expensive than driving the piles after the trench has been excavated. But when PRASA increased the required pile capacity to 135 tons, Howard found it impossible to use the follower successfully, because the higher capacity piles were longer and more difficult to drive.
