Paul D. Reardon and John E. Reardon v. United States of America and the United States Environmental Protection AgencyPaul D. Reardon and John E. Reardon v. United States of America and the United States Environmental Protection Agency
Lead Opinion
OPINION EN BANC
After removing hazardous substances from property belonging to the Reardons, EPA filed a notice of lien on the property for the amount spent. See
I. BACKGROUND
A. Facts. In 1979, Paul and John Rear-don purchased a 16-acre parcel in Nor-wood, Massachusetts, adjacent to an electric equipment manufacturing plant site
In 1984, the Reardons subdivided Kerry Place into a number of parcels; they sold five of those parcels and retained ownership of the others. In October 1985, EPA notified the Reardons that, as current owners of Kerry Place, they might be liable under §§ 106 and 107 of the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”),
In August 1987, EPA again investigated the properties to assess the feasibility of a long-term remedy for any remaining contamination. New testing showed that soil in several areas on Kerry Place was still contaminated with PCBs. In April 1988, EPA informed the Reardons of these results. The Reardons told EPA that they intended to clean up their property themselves. EPA advised the Reardons to coordinate any offsite disposal plans with EPA and to obtain EPA’s approval of a treatment or disposal facility. In January 1989, the Reardons informed EPA that they had completed their own clean-up of Kerry Place, without having attempted coordination with or sought the approval of EPA.
On March 23, 1989, EPA filed a notice of lien with the Norfolk County Registry of Deeds pursuant to § 107(i) of CERCLA,
B. Procedural History. The Reardons filed a complaint and a motion for preliminary injunction in the United States District Court for the District of Massachusetts. They argued that they were entitled to have the notice of lien removed for three reasons. First, the Reardons maintained that they qualified as “innocent landowners” under § 107(b) of CERCLA,
The district court held that § 113(h) of CERCLA,
The Reardons appealed, and a panel of this court found in their favor. The panel opinion construed
II. JURISDICTION
We turn first to the question of jurisdiction. The district court, as we have noted, held that
No federal court shall have jurisdiction under Federal law ... to review any challenges to removal or remedial action selected under section 9604 of this title, or to review any order issued undersection 9606(a) of this title, in any action except one of the following: [listing 5 enumerated types of actions]
The district court framed the question of jurisdiction as whether the filing of a lien constituted a “removal or remedial action selected under section 9604 of this title.” As the district court noted, the terms “removal” and “remedial action” are defined terms under the CERCLA statute.
A. Jurisdiction over the “innocent landowner” and “overbroad lien" claims. We agree with the district court that filing a lien notice is a type of “enforcement activity” related to a removal or remedial action. And we agree that
First, we think that the language of the statute, read for its ordinary meaning, supports such an interpretation. Central to the entire CERCLA scheme is a provision that makes certain parties liable for the cost of removal and remedial actions. See
Second, we believe that allowing challenges to the merits of particular liens would defeat some of the purposes of barring pre-enforcement review under
would be a significant obstacle to the implementation of response actions and the use of administrative orders. Pre-enforcement review would lead to considerable delay in providing cleanups, would increase response costs, and would discourage settlement and voluntary cleanups.
S.Rep. No. 11, 99th Cong., 1st Sess. 58 (1985).
As long as the. remedy upon review of a lien was limited to the invalidation or modification of the lien, of course, such review would not directly delay clean-up of hazardous substances. However, we do not believe that avoiding delay was the only purpose of postponing review. As the Fifth Circuit stated in a similar case:
Although review in the case at hand would not delay actual cleanup of hazardous wastes, it would force the EPA— against the wishes of Congress — to engage in “piecemeal” litigation and use its resources to protect its rights to recover from any [potentially responsible party] filing such a[n] action.
Moreover, the crazy-quilt litigation that could result from allowing [potentially responsible parties] to file declaratory judgment actions prior to the initiation of government cost recovery actions could force the EPA to confront inconsistent results.
Voluntary Purchasing Groups, Inc. v. Reilly,
. The same practical considerations weigh against allowing pre-enforcement review in this case. And we add to these reasons one more: information needed to decide legal challenges to liens may not be available at the time such challenges are made. To decide, for example, the Reardons’ claim that they are innocent landowners, a court must determine whether the contamination pre-dated their ownership; whether they had any knowledge or reason to know of the contamination; whether they had exercised due care with respect to the hazardous substances; and whether they took precautions to prevent releases by foreseeable acts of third parties. See
Third, legislative history supports the view that
Citizens, including potentially responsible parties, cannot seek review of the response action or their potential liability for a response action — other than in a suit for contribution — unless the suit falls within one of the categories in this section....
132 Cong.Rec. S14929 (daily ed. Oct. 3, 1986) (emphasis added). Senator Stafford,
It is certainly possible that Congress inadvertently rather than purposefully included lien challenges in the judicial review bar. Congress amended the scope of “removal” and “remedial” actions to include “enforcement activities related thereto” primarily to ensure that EPA could “recover costs for enforcement actions taken against responsible parties.” H.R.Rep. No. 253(1), 99th Cong., 2d Sess. 66-67, reprinted in 1986 U.S.Code Cong. & Admin.News 2835, 2848-49; see H.R.Conf.Rep. No. 962, 99th Cong., 2d Sess. 185, reprinted in 1986 U.S.Code Cong. & Admin.News 3276, 3278 (“This amendment clarifies and confirms that [enforcement activity] costs are recoverable from responsible parties.”). Perhaps Congress did not realize that other provisions referring to removal and remedial actions — such as the judicial review bar — would also be affected. But even if this were so, we do not see how our conclusion is altered. First, as outlined above, reading the statute to bar review of pre-enforcement challenges to liens is consistent with the language and the purpose of the judicial bar. Second, and more importantly, Congress amended a definitional section, thus changing the meaning of “removal” and “remedial” wherever they appear in CERCLA. We cannot give the definition inconsistent readings within the statute. As the above-quoted legislative history makes clear, the 1986 amendment was certainly intended to allow the government to collect attorney’s fees in cost recovery actions. See United States v. Ottati & Goss,
B. Jurisdiction over the due process claim. Unlike the district court, however, we do not believe that
Second, we read
Third, extending jurisdiction to the Rear-dons’ due process claim does not necessarily run counter to the purposes underlying
Fourth, although the two courts that have considered this issue have reached a different conclusion, see Barmet Aluminum Comp. v. Reilly,
Our disagreement commences with the phrasing of the issue to be decided. Both courts frame the question as whether
Once we recognize this distinction, the reasoning of these two courts becomes less convincing. First, says the South Macomb court,
Reading the language of§ 9613(h) for its everyday meaning supports the notion that this subsection prohibits constitutional as well as statutory challenges until the time prescribed by the statute. The provision explicitly states that federal courts shall not have jurisdiction to review “any challenge” except for those enumerated.
South Macomb,
Both the Barmet and South Macomb courts contend that legislative history— House and Senate Reports, and House Judiciary Committee Hearings — suggests that Congress intended
As several courts have noted, the scheme and purposes of CERCLA would be disrupted by affording review of orders or response actions prior to commencement of a government enforcement or cost recovery action. See, e.g., Lone Pine Steering Committee v. EPA, [600 F.Supp. 1487 (D.N.J.1985) ]. These cases correctly interpret CERCLA with regard to the unavailability of pre-en-forcement review. This amendment [§ 9613(h) ] is to expressly recognize that pre-enforcement review would be a significant obstacle to the implementation of response actions and the use of administrative orders. Pre-enforcement review would lead to considerable delay in providing cleanups, would increase response costs, and would discourage settlements and voluntary cleanups.
S.Rep. No. 11, 99th Cong., 1st Sess. 58 (1985). We see nothing in this discussion which would indicate an intent to divest federal courts of jurisdiction to consider a claim that the provisions of CERCLA itself authorize deprivations of property without due process of law. On the contrary, the reference to “review of orders or response actions” suggests that the writers of the Senate Report focused their concern on the problems that would arise if courts reviewed the merits of particular EPA actions.
Both Barmet and South Macomb attach great weight to the Senate Report’s citation “with approval” of Lone Pine, a case decided before
We do not find the House Report any more convincing. The pertinent passage in that Report, according to Barmet and South Macomb, is a statement that “there is no right of judicial review of the Administrator’s selection and implementation of response actions until after the response action[s] have been completed....” H.R.Rep. No. 253(1), 99th Cong., 2d Sess. 81, reprinted in 1986 U.S.Code Cong. & Admin.News 2835, 2863. See Barmet,
South Macomb also cites testimony of EPA and Justice Department officials during hearings on the bill that contained
Mr. Chairman, briefly, this issue has been litigated under the 1980 statute*1517 quite extensively, and there have been a number of decisions over the last several months that address the fundamental questions of the constitutionality of the procedures set forth in that law. Virtually across the board now the courts are finding that the scheme is constitutional as currently constituted.
Superfund Reauthorization: Judicial and Legal Issues, Hearings before the Sub-comm. on Admin. Law and Governmental Relations, H. of Rep. Judiciary Comm., 99th Cong., 1st Sess. at 226 (July 17, 1985); see South Macomb,
Finally, the Supreme Court recently examined a statute with a judicial review provision not unlike the CERCLA section analyzed here. At issue in McNary v. Haitian Refugee Center, Inc., — U.S. —,
The statute in McNary resembles the CERCLA provision at issue here in two respects. First, as here, judicial review of an administrative event is withheld until the agency instigates a second, independent proceeding. More significantly, the immigration statute is phrased so as to bar review of the agency’s determination of SAW status in an individual action — an event comparable to EPA’s selection of a removal or remedial action, which is the focus of the CERCLA bar. Neither statute mentions the availability of review of a constitutional challenge to the statute itself (as here) or to the agency’s execution of the statute (as in McNary). Insofar as the Immigration and Nationality Act compares to CERCLA, we think that the holding in McNary supports our conclusion here. See also Johnson v. Robinson,
Thus, we conclude that we have jurisdiction to consider the Reardons’ due process claim: that the CERCLA statutory scheme under which liens may be imposed on property without opportunity for a hearing violates the fifth amendment due process clause.
III. THE DUE PROCESS CLAIM
The Supreme Court has established a two-part analysis of due process challenges to statutes which, like this one, involve property rather than liberty interests. One must first ask whether the statute authorizes the taking of a “significant property interest” protected by the fifth amendment. E.g., Fuentes v. Shevin,
A. The Deprivation. The district court, relying primarily on Spielman-Fond, Inc. v. Hanson's, Inc.,
In Connecticut v. Doehr, — U.S.-,
For a property owner like Doehr, attachment ordinarily clouds title; impairs the ability to sell or otherwise alienate the property; taints any credit rating; reduces the chance of obtaining a home equity loan or additional mortgage; and can even place an existing mortgage in technical default where there is an insecurity clause.
Doehr, — U.S. at-,
In light of these comments, we cannot but conclude that the lien on real property created in
B. What Process is Due. The Doehr Court reaffirmed the “now familiar threefold inquiry,” id. at-,
“the private interest that will be affected by the official action”; “the risk of an erroneous deprivation of such interest through the procedures used, and the probable value, if any, of additional or substitute safeguards”; and lastly “the Government’s interest, including the function involved and the fiscal and administrative burdens that the additional or substitute procedural requirement would entail.”
Id. (quoting Mathews v. Eldridge,
(1) The Affected Private Interest. The federal lien here, like the attachment lien in Doehr, does not deprive the landowner of possession and use of his property. As Doehr said, the effect of such a lien— clouding title, impairing the ability to alienate the property, tainting credit ratings, and reducing the chance of obtaining any further mortgage—“is less than the perhaps temporary total deprivation of household goods or wages.” Id. However, the interests that the federal lien affects—the same as the interests affected in Doehr—
(2) The Risk of Current Procedures and the Value of Additional Safeguards. This part of the analysis encompasses several considerations. First, we must weigh the nature of the issues which would indicate whether the federal lien in this case has been correctly filed. Are these issues “uncomplicated matters that lend themselves to documentary proof,” Mitchell v. W.T. Grant Co.,
This case falls somewhere between the two extremes. The initial issue of liability under CERCLA is quite straightforward. Section 107(a) of CERCLA,
Second, we must consider what procedural safeguards, if any, CERCLA provides against erroneous filing of a lien.
a. The right to a judicial hearing. CERCLA provides no such safeguards. It provides for no pre-deprivation proceedings at all — not even the ex parte “probable cause” hearing judged insufficient in Doehr. See Doehr at -,
Nor does CERCLA provide for an immediate post-deprivation hearing.
“[M]ere postponement of judicial enquiry is not a denial of due process if the opportunity given for ultimate judicial determination of liability is adequate.” Phillips v.
b. Posting of a Bond. The Court has recognized that requiring the filing party to post a bond may provide the property owner important protection against wrongful filing; in Doehr, four members of the Court suggested that due process always requires a plaintiffs bond in the context of an attachment. See Doehr, — U.S. at —,
c. Action for damages. In Doehr, the State of Connecticut argued that the availability of a double damages remedy for suits that are commenced without probable cause was an important protection against misuse of the attachment provisions; however, four members of the Court did not find the availability of such a suit to be an adequate procedural safeguard. Four members of the court explained in detail why an action for damages would never prove adequate:
The necessity for at least a prompt pos-tattachment hearing is self-evident because the right to be compensated at the end of the case, if the plaintiff loses, for all provable injuries caused by the attachment is inadequate to redress the harm inflicted, harm that could have been avoided had an early hearing been held. An individual with an immediate need or opportunity to sell a property can neither do so, nor otherwise satisfy that need or recreate the opportunity. The same applies to a parent in need of a home equity loan for a child’s education, an entrepreneur seeking to start a business on the strength of an otherwise strong credit rating, or simply a homeowner who might face the disruption of having a mortgage placed in technical default.
Doehr, — U.S. at —,
In this case, EPA asserts that the Rear-dons might recover damages for the wrongful filing of a lien by filing a suit under the Tucker Act,
(3) The Government’s Interest. The third consideration is “ ‘the Government’s interest, including the function involved and the fiscal and administrative burdens that the additional or substitute procedural requirement would entail.’ ” Dolehr, — U.S. at —,
a. Recognized Interest in the Property. First, the Court has considered whether the party seeking to impose a lien on property has a recognized interest in the particular property which it is seeking to protect. See Doehr, — U.S. at-n. 4, —,
In this case, the government does not have any prior recognized interest in the Reardons’ property. Under
We believe this conclusion is consistent with the Court's remarks in Doehr about the Spielman-Fond case. The Court, explaining why its summary affirmance in Spielman-Fond, Inc. v. Hanson’s Inc.,
The facts of Spielman-Fond presented an alternative basis for affirmance in any event. Unlike the case before us, the mechanic’s lien statute in Spielman-Fond required the creditor to have a pre-exist-ing interest in the property at issue.379 F.Supp., at 997 . As we explain below, a heightened plaintiff interest in certain circumstances can provide a ground for upholding procedures that are otherwise suspect.
Doehr, — U.S. at — n. 4,
But in Spielman-Fond, Inc., supra, there was, as the Court points out in fn. 4 [sic], ante, an alternate basis available to this Court for affirmance of that decision. Arizona recognized a pre-existing lien in favor of unpaid mechanics and material-men who had contributed labor or supplies which were incorporated as improvements to real property. The existence of such a lien upon the very property ultimately posted or noticed distinguishes those cases from the present one, where the plaintiff had no pre-exist-ing interest in the real property which he sought to attach.
Id. at —,
Every person who labors or furnishes materials, machinery, fixtures or tools in the construction, alteration, or repair of any building, or other structure or improvement whatever, shall have a lien thereon for the work or labor done of materials, machinery, fixtures or tools furnished.
Of course, the Reardons cannot claim that the underlying action is entirely unrelated to the attached property, as was the case in Doehr. But, taking the Reardons’ contentions as true, a cleanup undertaken by EPA on portions of the Reardons’ property is too minimal a connection to justify bootstrapping a lien on all the parcels.
b. Exigent Circumstances. The absence of notice and a hearing may be justified by exigent circumstances. As the Court said in Doehr, finding a lack of such circumstances:
[Tjhere was no allegation that Doehr was about to transfer or encumber his real estate or take any other action during the pendency of the action that would render his real estate unavailable to satisfy a judgment, our cases have recognized such a properly supported claim would be an exigent circumstance permitting postponing any notice or hearing until after the attachment is effected. See Mitchell, supra, at 609,94 S.Ct. at 1901 ; Fuentes, supra, at 90-92,92 S.Ct. at 1999-2000 ; Sniadach,395 U.S., 337 at 339,89 S.Ct. 1820 at 1821,23 L.Ed.2d 349 . Absent such allegations, however, the plaintiff’s interest in attaching the property does not justify the burdening of Doehr’s ownership rights without a hearing to determine the likelihood of recovery.
Doehr, — U.S. at —,
As in Doehr, there is nothing in this case suggesting that a transfer or encumbrance of the parcels retained by the Reardons was imminent. And a special feature of CERCLA makes a claim of exigent circumstances even less likely than in the usual lien case. Under the CERCLA liability provisions, any subsequent owner of property who knew at the time of purchase that hazardous wastes were located on the premises would become liable for cleanup costs, and the property could be sold to satisfy a judgment against that subsequent owner. See
c. The Added Burden of Additional Procedural Requirements. The due process calculus also involves consideration of “ ‘the fiscal and administrative burdens that the additional or substitute procedural requirement would entail.’ ” Doehr, — U.S. at —,
Of course, EPA might seek to place a lien on property during the very early stages of a response action, when it did not have sufficient proof that a particular parcel of property was going to be “subject to
EPA argues that the present case can be distinguished from Doehr in five respects: (1) the EPA’s interest in the Reardons’ property before attachment of the lien; (2) the availability of a Tucker Act damages action; (3) the presence of exigent circumstances; (4) the interest of the United States in protecting the federal fisc; and (5) the purportedly minimal risk of erroneous attachment in this case. Our discussion above has already addressed the first three of these arguments. We will now consider the last two.
It does not seem that the fact that the United States, rather than a private party, is seeking the lien, should weigh in favor of the statute’s constitutionality. Indeed, since the due process clause protects against government deprivation, just the opposite would seem to be the case. There is one situation, the federal tax lien, where the government’s financial well-being may justify the draconian deprivation of its citizens’ property. But an EPA lien is not on the level of a federal tax lien. The tax lien is a law unto itself, and arises from administrative necessity (as well as direct constitutional authority, see
As for EPA’s final point, we simply do not see how the risk of erroneous deprivation in this case can be characterized as minimal. Rather, the risk seems greater than it was in Doehr. In that case, a judge considered the merits ex parte before authorizing the attachment, the plaintiff could attain an immediate post-attachment hearing, and a double damage remedy was available to compensate for, and to deter, error. Here, there is no prior neutral proceeding, no double damage remedy, and no post-attachment review for what may be many years. Unless EPA is immune from error — which we doubt — the risk of mistake is not minimal.
IV. CONCLUSION
In sum, we find that CERCLA
For these reasons, the judgment of the district court is affirmed in part, reversed in part, and remanded for further proceedings.
Notes
. Of course,
. The Connecticut statute at issue in Doehr provided "expeditious” post-attachment review, see-U.S. at-,
. See, e.g., United States v. Snyder,
The power of taxation has always been regarded as a necessary and indispensable incident of sovereignty. A government that cannot, by self-administered methods, collect from its subjects the means necessary to support and maintain itself in the execution of its functions is a government merely in name. If the United States, proceeding in one of their own courts, in the collection of a tax admitted to be legitimate, can be thwarted by the plea of a state statute prescribing that such a tax must be assessed and recorded under state regulation, and limiting the time within which such tax shall be a lien, it would follow that the potential existence of the government of the United States is at the mercy of state legislation.
Snyder,
Dissenting Opinion
(dissenting).
Although the majority makes a respectable case that
We are required to start with the well-settled theme that a court “will construe [a] statute to avoid [constitutional] problems unless such construction is plainly contrary to the intent of Congress.” Edward J. De Bartolo Corp. v. Florida Gulf Coast Building & Constr. Trades Council,
We are required to respect a second settled tenet in determining whether there is an alternative interpretation more consonant with the Constitution. “[T]he ‘starting point in every case involving construction of a statute is the language itself,’ Blue Chip Stamps v. Manor Drug Stores,
Although
Section 9613(h) provides in relevant part: No Federal court shall have jurisdiction ... to review any challenges to removal or remedial action selected under section 9604 of this title, or to review any order issued undersection 9606(a) of this title, in any action except one of the following:4
First, the panel adopts what it considers the “ordinary meaning” of the term “enforcement activity,” as including a CERC-LA lien. Whatever other arguments there may be for such an interpretation, I must confess that I cannot think that “ordinary meaning” is among them. Under any ordinary understanding, CERCLA liens created by statute, see
The panel conclusion that “a lien on property to secure payment of [the costs of removal and remedial actions] ... can reasonably be described as seeking to enforce the liability provision,” at 1512 (emphasis added), while true, is predicated on a misapprehension of the
Second, the panel opinion correctly notes that the primary purpose of
The panel relies in particular on Voluntary Purchasing Groups, Inc. v. Reilly,
A further legislative purpose supposedly served by barring preenforcement review is avoidance of the difficulty of litigating the innocent owner issue, see
Nor would preenforcement review impair the specific legislative purpose that prompted the amendment to
Third, the panel relies on legislative history for its conclusion that
As the panel indicates, Congress did make clear its general purposes in enacting
Congress’ reasoning regarding PRP’s in general simply does not have meaning for those whose property is encumbered by a CERCLA lien. Congress perceived no need to permit PRP’s to challenge their liability for costs and damages prior to the completion of the cleanup, because “plaintiffs concerned with the monetary consequences of a response can be made whole after the cleanup is completed by reducing the amount of the Government’s recovery.... Delay in the timing of suits seeking monetary damages does not diminish the court’s ability to grant later and adequate relief.” 132 Cong.Rec. S14898 (daily ed. Oct. 3, 1986) (Sen. Stafford). The statement by Senator Stafford, a floor leader, demonstrates that Congress did not consider the plight of innocent owners indefinitely deprived of their property rights and the right to challenge an invalid CERCLA lien.
Innocent landowners whose property rights remain encumbered for years by a CERCLA lien are not seeking to challenge their potential liability for cleanup costs but to terminate the confiscatory effects of the invalid lien. Nor can an innocent owner be made whole by “reducing the amount of the Government’s recovery,” since the deprivation sustained by the innocent owner does not result from a recent assessment of unwarranted cleanup costs but from the inability to dispose of the encumbered property while awaiting EPA’s discretionary initiation of an in rem action to recover on an invalid CERCLA lien. See
The panel interprets
The constitutionality of the CERCLA lien provision depends on whether the notice of lien and the opportunity for judicial review satisfy the three part analysis articulated in Mathews v. Eldridge,
“the private interest that will be affected by the official action”; “the risk of an erroneous deprivation of such interest through the procedures used, and the probable value, if any, of additional or substitute safeguards”; and lastly, “the Government’s interest, including the function involved and the fiscal and administrative burdens that the additional or substitute procedural requirement would entail.”
Doehr,
I agree with the panel that the adverse effects of a CERCLA lien, indefinitely extended without the right to judicial review, would work a “significant” deprivation. I disagree, however, that there is a substantial risk of any unwarranted deprivation in the instant case, due to the very different purposes served by a CERCLA lien and the attachment lien involved in Doehr. Finally, I cannot agree that the government has no significant interest in the Reardons’ property.
First, the Connecticut statute in Doehr permitted prejudgment attachment of the defendant’s home to secure recovery of any future damage award to the plaintiff in an as-yet untried tort action. Doehr,
A CERCLA lien, however, is very different from the attachment lien in Doehr. The CERCLA lien encumbering the Rear-don property has been administratively determined to require priority cleanup. The Reardon property has been determined to be contaminated by large quantities of po-lychlorinated biphenyls (PCBs) and has been placed on the National Priorities List pursuant to
The danger of an unwarranted CERCLA lien is further reduced by the very different standards governing the enforceability of the CERCLA lien and the attachment lien involved in Doehr. The prejudgment attachment lien in Doehr would be unenforceable unless the plaintiff eventually prevailed on the tort claim as to which he bore the ultimate burden of proof. The CERCLA statute, on the other hand, makes the owner, see
The lesser risk of unwarranted attachment similarly affects the evaluation of the sufficiency of the statutory safeguards. Given that a CERCLA lien encumbers only the real property rights of the owner of the contaminated property, see
Finally, and perhaps most importantly, I cannot agree with the analysis of the gov
First, the panel analysis overlooks the fact that property owners are answerable for response costs unless they can prove their innocence under the demanding standards prescribed in the statute. See
The inability of the government to recover its costs from responsible parties would reduce the resources available for response actions at other contaminated sites. Congress enacted CERCLA to deal with “unfortunate human health and environmental consequences [of inactive hazardous waste disposal sites] ... amidst growing public and Congressional concern over the magnitude of the problem” and in recognition that “[e]xisting law [wa]s clearly inadequate to deal with this massive problem.” H.R.Rep. No. 1016, 96th Cong., 2d Sess., pt. 1 at 17 (1980), reprinted in 1980 U.S.Code Cong. & Admin.News 6119, 6120. Since the CERCLA lien provision significantly affects the EPA’s financial ability to cope with a health and environmental problem so massive that it hardly admits of cost quantification, the existence of a substantial governmental interest in recouping CERCLA response costs from the affected property appears manifest.
Due process analysis requires that we consider the effects of the CERCLA lien on the Reardons’ property rights, as applied in this case. In my opinion, considering the important governmental interests involved and the relatively insignificant risk of any unwarranted, uncompensable, short-term deprivation of the Reardons’ property rights, a prompt postdeprivation hearing at the instance of the Reardons would satisfy the due process analysis required by Doehr and Mathews. As I believe the statute is reasonably interpreted as permitting a prompt postdeprivation challenge at the instance of innocent landowners and is therefore constitutional, I respectfully dissent.
. The specific instances listed in
. The panel refrains from attempting to establish more than that the imposition of a CERCLA lien "can reasonably be described as [an enforcement activity].” More is required, however, "in order to save a statute from unconstitutionality." De Bartolo Corp.,
. Serious difficulties confound the effort to lump together attorney fees and CERCLA lien costs as "enforcement activities,” on an “all or nothing” basis. See at 1514. First, since the CERCLA lien arises by operation of law, see
I do not think it realistic to suppose that the congressional intent activating the 1986 amendment to
. Were this the case, of course, the court would lack jurisdiction to consider, sua sponte or otherwise, the constitutional difficulties posed by Connecticut v. Doehr,
.
. The statute in fact was unclear as to the showing required. The Supreme Court determined, however, that even a “probable cause” showing would not prevent a substantial danger of erroneous deprivation. Doehr,
. The risk of unwarranted cleanup is even more fanciful in the instant case, as the Rear-dons admit ownership and do not contest the presence of contaminants on their property.
. An action for damages under the Tucker Act,
The United States Claims Court shall have jurisdiction to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department ... or for liquidated or unliquidated damages in cases not sounding in tort.