Patricia Hayes Associates, Inc. v. Cammell Laird Holdings U.K.Patricia Hayes Associates, Inc. v. Cammell Laird Holdings U.K.
Shaun F. Carroll, Nourse & Bowles (Katharine F. Newman, on the brief) New York, NY, for Defendants-Appellees.
Before: FEINBERG, F.I. PARKER, and SOTOMAYOR, Circuit Judges.
F.I. PARKER, Circuit Judge.
Intervenors-plaintiffs-appellants Greenwich Insurance Co. and NAC Insurance Co. (“Sureties“) appeal the order of the United States District Court for the Southern District of New York (George B. Daniels, Judge), entered on June 3, 2002, denying Sureties’ motion to intervene in an action — filed by other plaintiffs, none of whom are a party to this appeal — against the Big Red Boat II (“BRBII“). The complaint accompanying Sureties’ motion to intervene alleged that Sureties had maritime liens against BRBII, and that Sureties were entitled to enforce those liens in rem against BRBII. The district court denied Sureties’ motion to intervene, and Sureties now appeal. For the reasons set forth herein, we conclude that there was no abuse of discretion in the district court‘s decision to deny Sureties’ motion to intervene. Therefore we affirm.
I. BACKGROUND
A. The Arrest of the Big Red Boat II
On September 14, 2000, Patricia Hayes & Associates, Inc. (“Hayes“) and Smithall Electronics, Inc. (“Smithall“) filed complaints against the BRBII, International Shipping Partners (“ISP“), Premier Cruises, Inc. (“Premier“) and the Master of the BRBII (collectively “the defendants“). Hayes and Smithall alleged that they possessed maritime liens against BRBII and therefore were entitled to a warrant of arrest pursuant to
On September 15, 2000, the district court signed the warrants of arrest requested by Hayes, Smithall, Southern Marine and Alpha Marine, and ordered the clerk of the court to issue a warrant of arrest and a writ of maritime attachment against BRBII. Although BRBII was out of the jurisdiction at the time of the warrant was signed, the vessel arrived in the district on Saturday, September 16, 2000. When BRBII entered the district, the United States Marshals seized it.
On September 28, 2000, the district court signed an order consolidating all claims filed against defendants and granting motions to intervene as to those claims uncontested by defendants. After the bulk of the claims against BRBII were settled, and BRBII‘s owners arranged for security to satisfy the remaining contested claims against the vessel, the district court signed an order releasing BRBII from arrest on November 10, 2000.
B. Sureties’ Claims Against the Big Red Boat II
Sureties’ claims against BRBII were based on and related to a bond Sureties issued to Premier. Premier did not own BRBII; it had chartered BRBII from the boat‘s owners (Big Red Boat(Two) Ltd.) and operated BRBII as part of its own fleet of vessels. In order to carry passengers for hire from U.S. ports, Premier was legally obligated to provide evidence of financial responsibility to establish that it could refund any unearned passenger deposits. See
In the fall of 2000, Premier ceased operations. At the time, Premier had collected passenger ticket deposits of $2,310,028.44 for future trips of BRBII which were canceled when Premier ceased operations. In addition, several BRBII voyages which had been scheduled for the Summer of 2000 were never performed due to operational or mechanical difficulties. Sureties claimed, in their complaint, that they were exposed to potential liability of up to $5 million — the coverage limit for any single boat under the FMC Bond. However, at no point prior to the district court‘s denial of Sureties’ motion to intervene in June 2002 did Sureties actually pay any claims under the FMC Bond.1
In their intervening complaint, Sureties contend that they had claims against BRBII because: 1) they were subrogated to the maritime lien rights of any passengers who made claims against the FMC Bond; and 2) they were entitled to a maritime lien because the FMC Bond was a maritime contract and/or a necessary provided to BRBII. The district court denied Sureties’ motion to intervene after concluding that “the bond between Sureties and Premier is not a maritime contract and, thus, Sureties cannot assert a maritime lien against the vessel.” Hayes v. M/V Big Red Boat II, No. 00 Civ. 6925(GBD), 2002 WL 1163555, at *4 (S.D.N.Y. May 31, 2002). The court also concluded that:
[e]ven if this Court were to find that the bond is a maritime contract, Sureties could not prevail. Sureties have not demonstrated that they have actually paid out any claims, nor that the claims against the BRB[II] exceed the $3.7 million collateral provided by Premier.
II. DISCUSSION
In their briefs and at oral argument, the parties focused primarily on the question of whether the FMC Bond is a maritime contract, and whether a maritime lien may attach as a result of payments made under such a bond. However, in the present case it is not necessary to reach — and therefore we do not decide — those issues, because nowhere in the motion to intervene, or in any of Sureties’ subsequent filings and communications with the district court up until the time the district court denied the motion, did Sureties ever allege that they had paid any claims under the FMC Bond. Therefore, it was within the district court‘s discretion to decide whether or not to exercise jurisdiction over Sureties’ claims, and the district court decided not to exercise jurisdiction. Sureties contend that, to the extent that the district court relied upon the prematurity of Sureties’ claims as the basis for the court‘s denial of the motion to intervene,2 that reliance was error. We disagree and, accordingly, affirm the district court‘s order.
A. Standard of Review
This Court reviews “a District Court‘s denial of a motion to intervene, whether as of right or by permission, for abuse of discretion.” In re Holocaust Victim Assets Litigation, 225 F.3d 191, 197 (2d Cir. 2000). “A district court abuses its discretion when (1) its decision rests on an error of law . . . or a clearly erroneous factual finding, or (2) its decision — though not necessarily the product of a legal error or a clearly erroneous factual finding — cannot be located within the range of permissible decisions.” In re Fitch, Inc., 330 F.3d 104, 108 (2d Cir. 2003) (per curiam) (internal quotation marks omitted).
B. General Principles
In order to intervene in the action against BRBII, Sureties had to establish that they had the right to enforce a maritime lien against the vessel. See Local Admiralty Rule for the Southern District of New York E.2 (“When a vessel . . . has been arrested, attached or garnished, and is in the hands of the marshal . . . anyone having a claim against the vessel . . . is required to present the claim by filing an intervening complaint” that meets the requirements of
As we explained in Itel Containers International Corp. v. Atlanttrafik Express Service Ltd., 982 F.2d 765 (2d Cir. 1992):
A maritime lien is: “a special property right in the vessel, arising in favor of the creditor by operation of law as security for a debt or claim. The lien arises when the debt arises, and grants the creditor the right to appropriate the vessel, have it sold, and be repaid the debt from the proceeds.” Id. at 766 (quoting Equilease Corp. v. M/V Sampson, 793 F.2d 598, 602 (5th Cir. 1986) (en banc)).
C. Analysis
Sureties claim that they had maritime liens against BRBII (and thus had an interest in the pending case against BRBII sufficient to justify intervention) for two reasons. First, Sureties contend that any amounts due under the FMC Bond that were attributable to the BRBII give rise to a maritime lien against BRBII. Second, Sureties claim that any passengers who paid to travel on BRBII but did not complete their trip were entitled to maritime liens against the ship, and Sureties, by paying those passenger claims, became subrogated to these maritime liens. The district court concluded that any potential claims Sureties might have against BRBII were premature because the “Sureties ha[d] not demonstrated that they ha[d] actually paid out any claims, nor that the claims against the BRB[II] exceed the $3.7 million collateral provided by Premier.” Sureties contend that the district court erred by denying their motion to intervene on this basis for two reasons. First, Sureties argue that the district court improperly concluded that Sureties’ claims were unripe. Alternatively, Sureties argue that even if the district court correctly determined that their claims were unripe, the court nonetheless abused its discretion by denying the motion to intervene. We consider and reject each of these arguments in turn.
1. Sureties’ Claims Were Unripe
Sureties argue that the district court erred by concluding that their claims were unripe without first allowing Sureties an opportunity to present evidence in support of their claims. We find this contention unpersuasive because it misstates the record — it is clear from the record both that the district court offered Sureties, and that Sureties accepted, several opportunities to supplement the record between the time the initial motion was filed and the time the motion was denied3 (a period of more than a year and a half) — but, more importantly, because it misperceives the basis of the district court‘s denial of Sureties’ motion.
The determination of whether Sureties’ claims were ripe turns on the question of whether there were any amounts due under the contract (the FMC Bond) at the time of the motion to intervene. See Itel Containers, 982 F.2d at 766 (“[t]he lien arises when the debt arises“); see also id. at 768 (a maritime lien “gives the creditor a special property in the ship, which subsists from the moment the debt arises)” (quoting The Poznan, 9 F.2d 838, 842 (2d Cir. 1925), rev‘d on other grounds sub nom. New York Dock Co. v. Steamship Poznan, 274 U.S. 117, 47 S.Ct. 482, 71 L.Ed. 955 (1927)). Sureties’ claims are for amounts that they allege they will be required to pay (without the contractually required indemnification from Premier) under the FMC bond. Therefore, Sureties’ claims could not be ripe (i.e., Sureties could not have a maritime lien) until and unless Sureties paid money under the FMC Bond and Premier failed to indemnify Sureties for that payment.
Thus, Sureties’ claims were unripe not because Sureties failed to provide sufficient evidence to support their allegations, but rather because their allegations, taken as true, were insufficient to support their claim. Because Sureties had not paid any claims under the FMC bond by the time their motion to intervene was denied, there was no amount due under the contract at that time. Without a debt due, Sureties could not have a maritime lien to enforce against BRBII. Thus, we find no error in the district court‘s conclusion that Sureties’ claims were unripe.
2. The District Court Did Not Abuse Its Discretion by Declining To Exercise Jurisdiction over Sureties’ Claims
Next, Sureties contend that, even if their claims were unripe, the district court erred by denying the motion to intervene because a maritime claim may be filed even before there is a breach of a maritime contract, if it is clear that the contract will be breached. In support of this position, Sureties cite Greenwich Marine, Inc. v. S.S. Alexandra, 339 F.2d 901 (2d Cir. 1965), and The Lassell, 193 F. 539 (E.D. Pa. 1912). Sureties argue that the district court should have exercised jurisdiction over their claims because, even though they had not paid any claims at the time the motion to intervene was denied, the district court should have inferred, from the scope of the potential liability as documented in the number and amount of claims Sureties had received (though not paid) that Sureties would have mature claims within a reasonable period of time.
As an initial matter, we note that the cases Sureties cite stand only for the proposition that a district court may in some circumstances disregard the prematurity of a plaintiff‘s claim as a matter of discretion, not that a district court must ignore the prematurity of a claim. For example, in The Lassell, a case involving somewhat exigent circumstances, the district court declined to dismiss a claim that was premature when filed but certain to mature shortly (i.e., within a matter of hours). In support of this decision, the court explained that: “It is settled that a suit may sometimes be brought in admiralty before the cause of action accrues, and the prematureness of the proceeding will only affect the question of costs.” See id. at 543 (emphasis added). In Greenwich Marine, this Court recognized the same principle while upholding the district court‘s decision to dismiss the plaintiff‘s claim as premature. See 339 F.2d at 905 (“the admiralty judge, who is asked to disregard the prematurity of plaintiff‘s claim, must be compared to the Chancellor ‘balancing the equities,’ and we would be entitled to reverse him only if he clearly abused his discretion“).
The question, then, is whether the district court abused its discretion by declining, on prematurity grounds, to exercise jurisdiction over Sureties’ claims. In support of its decision to deny Sureties’ motion to intervene, the district court cited both the fact that Sureties had yet to pay any claims, and the fact that Sureties held $3.7 million in cash collateral as security in the event that any claims were paid in the future.
III. CONCLUSION
For the foregoing reasons, we conclude that there was no abuse of discretion in the district court‘s decision to deny Sureties’ motion to intervene. Accordingly, the order of the district court is AFFIRMED.
Notes
Interestingly, this case also appears to explain, at least to some degree, why it took Sureties so long to pay any claims. Apparently they were using their own slow pace of claims investigation and payment as a way to encourage passengers to pursue effective reimbursement from their credit card companies. See Nova Information Sys., 2003 A.M.C. at 237-38 (recounting how Sureties issued public statements informing potential claimants that they would be “well advised” to seek reimbursement from a credit card company, if possible, in order to “avoid the delays that will inevitably occur in the investigation and claims settling process“).