32 Conn. 115 | Conn. | 1864
The parties to this suit submitted to arbitration “ all matters of controversy subsisting between [them,] whether debt, damages, costs, title to lands, or any other matters whatsoever.” The arbitrators by their award established certain lines and boundaries, fixing one line “ as the fences now stand, including a piece of stone wall near the south-west
This suit was brought to recover the money so awarded.
The first objection made by the defendant to a recovery is, that the submission, so far as the title to land was concerned, not being in conformity with the provisions of the statute, (Rev. Stat., tit. 29, § 21,) did not authorize the arbitrators to award on that subject, and inasmuch as they have embraced a small portion of land in their award by directing the line to be drawn so as to leave a portion of Allen’s land on the other side of the division line, this renders the whole award void. There is no doubt that since the passage of the act referred to such an award does not pass the title, and does not preclude the owner from claiming it. Whether it would subject the party to damages if he should claim and recover it, it is unnecessary now to inquire. It is also well settled that if this part of the award materially affects the balance found due, it would render that part of the award void also. But as arbitrations are designed to prevent litigation, although they often as in this case promote it, they are regarded in law with much favor. If several distinct matters are submitted, the award as to some of them may be good while it is void as to the residue. If the parties agree to submit all their disputes, and in fact only submit a part, the award will be binding as to that part. The sum found due by these arbitators is the balance of mutual “ damages, costs, &c.” The arbitrators had full power to award as to damages and costs. What is included in the “ <fec.” does not appear. The defendant insists that it includes
The defendant however strongly insists that if this view is correct, there is a fatal variance between the award and the declaration. The allegation in both counts is that the sum was payable “ on demand.”
The defendant in the first place insists that by .the fair construction of the award the money was not payable till the acts to be done by the plaintiff had been performed. But the expression “ when the other matters herein directed tó be done are performed,” evidently refers to the words immediately preceding them, regarding the settlement of all matters in dispute, and not to the time of paying the sum awarded.
Another objection on the ground of variance is of a more technical character. It is insisted that the allegation in the declaration should have been that the money was payable “ in a reasonable time,” and a remark in Kyd on Awards, (page 204,) is referred to. This authority seems to countenance the objection. But we see no good reason for making a distinction between an award and a note of hand. In Bacon v. Page, 1 Conn., 404, a note of hand without specifying when the money was payable was held to he payable on demand. The same doctrine was held in Whitlock v. Underwood, 2 Barn. & Cress., 157. In Thompson v. Ketchum, 8 Johns., 189, such a note was held to be payable immediately, and Kent, C. J., says, page 192, that if in any contract no time for payment is mentioned the law adjudges the money to be payable immediately. This is perhaps the most correct view, and in such cases the form of declaring is to allege that the money was to be paid on demand, or in a reasonable time, indiscriminately. Indeed there is no substantial difference between them. Where .money is due it is reasonable to make an immediate demand, and thus the reasonable time a,nd the
A new trial is not advised.
In this opinion the other judges concurred.