PARKWEST HOMES LLC, an Idaho limited liability company v. Julie G. BARNSON, an unmarried woman; Mortgage Electronic Registration Systems, Inc., a Delaware corporation, as nominee for Homecomings Financial, LLC (f/k/a Homecomings Financial Network, Inc.,) a Delaware limited liability company; and Does 1-10
No. 36246-2009
Supreme Court of Idaho
June 25, 2010
238 P.3d 203 | 149 Idaho 603
EISMANN, Chief Justice.
Boise, June 2010 Term.
Hawley Troxell Ennis & Hawley LLP, Boise, for respondent Mortgage Electronic Registration Systems, Inc. Ryan T. McFarland argued.
EISMANN, Chief Justice.
This is an appeal from a judgment dismissing an action to foreclose a mechanic‘s lien because: (a) the notice of lien did not substantially comply with the requirements of
I. FACTS AND PROCEDURAL HISTORY
On March 27, 2006, ParkWest Homes LLC and Juli Barnson both signed a written contract dated March 15, 2006, under which ParkWest agreed to construct a home on certain real property for $422,000. At the time that the parties negotiated and executed that contract, ParkWest was not registered under the Idaho Contractor Registration Act,
ParkWest registered under the Contractor Act on May 2, 2006; it commenced construction of the home on May 22, 2006; and it claims to have substantially completed construction on November 1, 2006. ParkWest and Barnson later had a dispute as to wheth
On November 14, 2006, two deeds of trust were recorded against the property. Mortgage Electronic Registration Services, Inc., (MERS) is the beneficiary under both deeds of trust.
On August 7, 2007, ParkWest filed this action to foreclose its lien. On October 2, 2008, MERS filed a motion for summary judgment contending that ParkWest‘s asserted lien was void because: (a) the claim of lien did not substantially comply with
The district court held that ParkWest did not have a mechanic‘s lien because its claim of lien was defective and the construction contract was void. It entered judgment in favor of MERS holding that its deeds of trust were superior to ParkWest‘s mechanic‘s lien. ParkWest then timely appealed.
II. ISSUES ON APPEAL
(1) Did the district court err in holding that ParkWest‘s claim of lien did not substantially comply with
(2) Did the district court err in holding that ParkWest‘s claimed lien was unenforceable because the construction contract was void for failure to comply with the Contractor‘s Act?
(3) Did the district court err in holding that ParkWest did not plead a claim for unjust enrichment?
(4) Is MERS entitled to an award of attorney fees on appeal?
III. ANALYSIS
During oral argument, ParkWest contended that MERS does not have standing in this case based upon a decision in an unrelated bankruptcy case holding that MERS did not have standing to assign a promissory note merely because it was the “nominal beneficiary” under the deed of trust securing that note. That decision has nothing to do with this case. ParkWest has alleged that MERS is the beneficiary under two deeds of trust and that ParkWest‘s mechanic‘s lien has priority over those deeds of trust. There is no contention that MERS attempted to assign any promissory note or to foreclose the deeds of trust.
A. Did the District Court Err in Holding that ParkWest‘s Claim of Lien Did Not Substantially Comply with Idaho Code § 45-507 ?
1. Failure to allege that the amount claimed was determined after deducting all just credits and offsets.
A lien is not invalidated simply because the claimant is not entitled to the amount claimed due in the claim of lien, Barber v. Honorof, 116 Idaho 767, 769, 780 P.2d 89, 91 (1989); Guyman v. Anderson, 75 Idaho 294, 296, 271 P.2d 1020, 1021 (1954), even when the discrepancy is substantial, Electrical Wholesale Supply Co. v. Nielson, 136 Idaho 814, 824-25, 41 P.3d 242, 252-53 (2001) (lien held valid where claim of lien demanded $51,571.00, and only $1,069.2 was found to be due). If an error in the amount of the claim does not invalidate the lien, it would be incongruous to read into
2. Failing to state that the amount claimed was just.
The purpose of this verification requirement is “a desire to frustrate the filing of frivolous claims.” Layrite Products Co. v. Lux, 86 Idaho 477, 484-85, 388 P.2d 105, 109 (1964). The word “just” is defined as “[v]alid within the law; lawful: just claims,” and the word “true” is defined as “exact; precise; accurate; correct: a true balance.” Dictionary.com. The American Heritage Dictionary of the English Language, Fourth Edition. Houghton Mifflin Company, 2004 (accessed June 14, 2010); and Dictionary.com. Dictionary.com Unabridged. Random House, Inc. (accessed June 14, 2010) (italics in originals). The district court did not seek to explain how, in this context, the word “true” differed materially from the word “just.” ParkWest‘s statement that the claim of lien was “true” substantially complied with
3. The failure to have a certificate of verification in the form set forth in Idaho Code § 51-109(4) .
| ParkWest Homes | David Zawadzki |
| Company Name | Authorized Representative of Said Company |
VERIFICATION:
I, the undersigned, say: I am the Authorized Representative of the claimant of the foregoing mechanic‘s lien; I have read said mechanic‘s lien and know the contents thereof; the same is true of my knowledge.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 28th day of November, 2006, at Nampa, Idaho.
/s/ David M. Zawadzki
Signature
WITNESS the hands and seal of said Grantors this 28th day of November, 2006.
I [notary‘s name], a Notary Public in and for said County and State, hereby certify that David M. Zawadzki personally known to me (or proved to me on the basis on satisfactory evidence) to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same voluntarily on the day the same bears date.
[NOTARY SEAL]
WITNESS my hand and official seal.
County of Canyon State of Idaho
[NOTARY SEAL] /s/ [notary‘s signature]
Notary Public
September 30, 2010
My Commission Expires
ParkWest used the shotgun approach in attempting to have its claim of lien verified by oath. In the portion of its lien claim entitled “Verification,” ParkWest first included a signed statement by its agent David Zawadzki stating, “I declare under penalty of perjury that the foregoing is true and correct.” Although some states have a statute making that type of signed statement the equivalent of an oath, see
Next, ParkWest included a certificate of acknowledgement stating that Zawadzki signed the claim of lien as “Grantors.” An acknowledgment is not required in order for a claim of lien to be recorded, In re GVR Ltd. Co., Inc., 107 Idaho 1101, 695 P.2d 1240 (1985), nor is an acknowledgment a verification by oath, Evans v. Twin Falls County, 118 Idaho 210, 219, 796 P.2d 87, 95 n. 9 (1990).
Finally, ParkWest included a statement signed by the notary that the claim of lien had been “[s]igned and sworn to before me [the notary]” on November 28, 2006. This is the form of a written oath set forth in
MERS argued, and the district court held, that section 45-507(4) required a certificate of verification as set forth in
We have not required that a claim of lien comply with
B. Did the District Court Err in Holding that ParkWest‘s Claimed Lien Was Unenforceable Because the Construction Contract Was Void?
At the time ParkWest negotiated and signed the construction contract, it was not registered under the Contractor Act. That Act provides, “On and after January 1, 2006, it shall be unlawful for any person to engage in the business of, or hold himself out as, a contractor within this state without being registered as required in this chapter.”
ParkWest contends that the district court erred in sua sponte raising the issue of the illegality of the construction contract. The district court did not err in sua sponte raising that issue. In Barry we held that “this Court has a duty to raise the issue of illegality,” id., and the district court had the same duty.
ParkWest does not challenge the district court‘s holding that the construction contract was void because ParkWest was not registered at the time it signed the contract. Rather, it argues that after it registered on May 2, 2006, Barnson ratified the construction contract. That issue was not presented to the district court, and so we will not consider it on appeal. Lopez v. Farm Bureau Mut. Ins. Co. of Idaho, 148 Idaho 515, 519, 224 P.3d 1104, 1108 (2010). Had ParkWest wanted the district court to consider that issue before the appeal, ParkWest could have filed a motion for reconsideration.
The district court also implicitly held that ParkWest‘s lien was void because its construction contract was void. Citing
A mechanic‘s lien is granted for “the work or labor done ... or materials furnished.”
No person engaged in the business or acting in the capacity of a contractor, unless otherwise exempt, may bring or maintain any action in any court of this state for the collection of compensation for the performance of any act or contract for which registration is required by this chapter without alleging and proving that he was a duly registered contractor, or that he was otherwise exempt as provided for in this chapter, at all times during the performance of such act or contract.
In order to bring an action to collect compensation for work or labor performed and materials supplied in a construction project, the contractor must allege and prove that he was a duly registered contractor or exempt from registration “at all times during the performance of such act or contract.” Thus, ParkWest is entitled to a lien for work or labor it provided and materials it supplied during the time that it was duly registered. To hold otherwise would mean that a contractor who violated the Act would be forever barred from obtaining a mechanic‘s lien.
C. Did the District Court Err in Holding that ParkWest Did Not Allege a Claim for Unjust Enrichment?
In its decision, the district court wrote, “At the very least, PARKWEST should have been entitled to a recovery based upon unjust enrichment. Nevertheless, that issue is not before the court.” (Citation omitted.) ParkWest contends on appeal that the district court erred in ruling that the factual allegations in ParkWest‘s “Second Amended Complaint to Foreclose Lien” did not include a claim for unjust enrichment.
Because it had ruled the lien invalid, the district court obviously was referring to a claim to recover money damages against Barnson for unjust enrichment. It obviously was not holding that although the lien was invalid, ParkWest could have established the amount of the lien by showing that Barnson had been unjustly enriched.
ParkWest and Barnson entered into a settlement under which ParkWest filed a second amended complaint and Barnson permitted it to obtain a default judgment against her on that complaint. The judgment awarded ParkWest the sum of $141,208.39, plus interest and $33,000.00 for costs and attorney fees “against Barnson to the extent of her interest in the Property, but not personally.” Thus, under the settlement Barnson would not be personally liable to ParkWest on any claim, including unjust enrichment. Therefore, we need not decide whether or not ParkWest‘s second amended complaint could be read to include a claim against Barnson for unjust enrichment. Because the district court did not decide, and ParkWest has not argued on appeal, that the amount of its lien could be measured by unjust enrichment, we do not address that issue.
D. Is MERS Entitled to an Award of Attorney Fees on Appeal?
MERS seeks an award of attorney fees on appeal pursuant to Bowles v. Pro Indiviso, Inc., 132 Idaho 371, 377, 973 P.2d 142, 148 (1999). In that case, this Court awarded attorney fees on appeal pursuant to
IV. CONCLUSION
We vacate the judgment of the district court and remand this case for further proceedings that are consistent with this opinion. We award costs on appeal to appellant.
Justices BURDICK, J. JONES, W. JONES and HORTON concur.
Notes
1. Section 51-109(2) provides:
An oath or affirmation, which is in writing, shall be signed by the person who takes it, and the notary public shall enter thereunder substantially the following:
“State of Idaho )
)ss.
County of )
Subscribed and sworn (or affirmed) before me this ___ day of ______, ___
___________________________
(official signature and seal)”
2. Section 51-109(4) provides:
A certificate of verification of an instrument shall follow the maker‘s signature and shall identify the notary public and certify that the maker personally appeared, was sworn, stated his authority for making the instrument, and averred the truth of the statements therein.
