113 Wash. App. 592 | Wash. Ct. App. | 2002
— At issue is whether either the statute of repose applicable to claims arising from construction, alteration, or repair of improvements to realty
The material facts are largely undisputed. Ledcor, a general contractor, sued Freeman, one of its subcontractors, after being sued by Parkridge Associates, Ltd. Ledcor was the general contractor for a construction project at the Parkridge Apartments. Freeman subcontracted with Led-cor to provide roofing, waterproofing, deck coating, and metal work for the Parkridge project in February 1993. An addendum to the subcontract provided that Freeman would defend, indemnify, and hold Ledcor harmless from any claims resulting from services performed by Freeman.
The date of substantial completion of the project was December 30, 1993. The parties dispute whether Freeman continued to perform work at the project until December 5, 1994. They also dispute the nature of the work, if any, that Freeman performed after the date of substantial completion.
On November 29, 1999, Parkridge sued Ledcor for product and workmanship failures and defects at the apartment complex. On May 19, 2000, Ledcor tendered defense of the suit to Freeman. Freeman did not accept that tender. On August 29, 2000, Ledcor commenced this third party action against Freeman and others. Ledcor stated nine causes of action in its third party complaint. Among them were: failure to defend, contractual indemnification, breach of express contractual warranties, and a cause of action described as “breach of contract (other).” This latter claim alleges an agreement to “perform work in accordance with the terms and conditions” of the subcontract. In this third party complaint, Ledcor again sought indemnification and defense by Freeman.
On December 22, 2000, Ledcor and Parkridge mediated a settlement. The terms of the settlement are confidential, but Ledcor represents that it and others paid Parkridge a sum “well into seven figures.” Neither Freeman nor another
Freeman moved for summary judgment on Ledcor’s claims, arguing that they were barred by the six-year written contract statute of limitations and the construction statute of repose. The trial court concluded that the statute of repose barred all claims asserted in the third-party complaint, and dismissed the action.
Ledcor appeals.
STATUTE OF REPOSE
Ledcor argues that the record shows that Freeman provided services at the Parkridge apartments until December 5,1994, and that the beginning of the six-year period of the statute of repose should be calculated from that date. Considering all facts and reasonable inferences in the light most favorable to Ledcor, we agree that the relevant date for summary judgment purposes is December 5, 1994, the date of “termination of [enumerated] services” under the statute of repose.
We may affirm an order granting summary judgment if there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law.
Our Supreme Court, in Del Guzzi Construction Co. v. Global Northwest Ltd.,
As Del Guzzi directs, our analysis begins with the statute of repose, RCW 4.16.310:
[a]ll claims or causes of action as set forth in RCW 4.16.300 shall accrue, and the applicable statute of limitation shall begin to run only during the period within six years after substantial completion of construction, or during the period within six years after the termination of the services enumerated in RCW 4.16.300, whichever is later.[11 ]
all claims or causes of action of any kind against any person, arising from such person having constructed, altered or repaired any improvement upon real property, or having performed or furnished any design, planning, surveying, architectural or construction or engineering services, or supervision or observation of construction, or administration of construction contracts for any construction, alteration or repair of any improvement upon real property.[12 ]
Ledcor argues and provides evidence that the work Freeman performed at Parkridge until December 5, 1994 qualifies as “services” for purposes of RCW 4.16.300. In response, Freeman argues that there must be a nexus between the services performed and the cause of action.
We agree with both contentions. The plain language of RCW 4.16.300, describing actions or claims “arising from” various services, shows that the services considered in this assessment must be those that gave rise to the cause of action. More importantly, considering the evidence in this record in the light most favorable to Ledcor, Freeman provided services of the type required by the statute until December 5, 1994.
This court’s opinion in 1519-1525 Lakeview Boulevard Condominium Ass’n v. Apartment Sales Corp.
Freeman claims that the work performed after the date of substantial completion was “warranty repairs” or “punch list” work that had no nexus to the contract and initial construction work on which the lawsuit is based. Nothing in the record supports this bare assertion. But even if Freeman had provided evidence to support this argument, there would be, at most, a genuine issue of material fact on the question. Summary judgment would not have been proper. Accordingly, the date of termination of services, December 5, 1994, controls, not the December 30, 1993 date of substantial completion of the project.
Del Guzzi requires that we determine the dates within which each asserted claim must accrue. Because we hold that for summary judgment purposes the controlling date for the beginning of the relevant period is December 5, 1994, the end of the relevant period for the statute of repose was December 5, 2000, six years later. Therefore, each of Ledcor’s claims must have accrued within that term to satisfy the statute of repose.
EQUITABLE INDEMNITY
Ledcor argues that RCW 4.16.310 does not apply to its equitable indemnification claim because the claim did not arise from construction problems but from Ledcor’s payment of a debt rightfully Freeman’s. Ledcor also argues that this claim accrued when Parkridge commenced the underlying action. We disagree with both contentions.
Ledcor relies on Central Washington Refrigeration, Inc. v. Barbee
Our Supreme Court identified the claim at issue as “implied contractual indemnity,” or “implied in fact” indemnity.
First, the Barbee court did not decide the question now before us: whether equitable indemnity claims that arise from construction are subject to the statute of repose. As the Barbee court stated, one issue before it was whether a buyer may maintain an indemnity action against a seller based on breach of warranty.
Second, the proper inquiry is whether the legislature intended to include equitable indemnity claims within the broad sweep of RCW 4.16.310. We determine legislative intent by construing the relevant statutes.
RCW 4.16.300 states that RCW 4.16.300-.320 “shall apply to all claims or causes of action of any kind against any person, arising from such person having constructed, altered or repaired any improvement upon real property.”
Next, Ledcor argues that summary judgment was improper because the equitable indemnity claim accrued when Ledcor was sued by Parkridge, rather than when it settled with Parkridge. Again, we disagree.
As to accrual of the cause of action, Barbee does control. It states “[i]t is settled law that [equitable] indemnity actions accrue when the party seeking indemnity pays or is legally adjudged obligated to pay damages to a third party.”
Here, Ledcor’s equitable indemnification claim accrued, at the earliest, when it reached a settlement agreement
Because the statute of repose bars the claim, we need not address whether suit was timely under the proper statute of limitation for equitable indemnity. Accordingly, summary judgment of dismissal of the equitable indemnity claim was proper.
CONTRACTUAL INDEMNITY
Ledcor next argues that its claims under the subcontract’s written duty to defend, indemnify, and hold harmless provisions accrued when it received notice of Parkridge’s suit on November 30, 1999. Freeman argues that Ledcor’s causes of action for indemnity and defense both accrued when Freeman breached the subcontract by rejecting the tender of defense. We hold that the contractual indemnity claim had not accrued as of December 5, 2000, and is thus barred by the statute of repose.
Ledcor’s claim is based on an indemnification addendum to its subcontract with Freeman. Therein, Freeman agreed to defend, indemnify and hold Ledcor harmless from “any and all claims, demands, losses and liabilities.”
Ledcor does not argue on appeal the duty to defend claim. Thus, we do not further consider that matter. Instead, we focus our discussion on the duty to indemnify claim.
Freeman argues that our Supreme Court’s holding in Schwindt v. Commonwealth Insurance Co.
Freeman argues that there was no breach of the duty to indemnify Ledcor until some point after Ledcor presented Freeman with the claim in May 2000, and it failed to honor its duty of indemnity under the addendum to the subcontract. Schwindt is consistent with the principle that we apply here. As of the bar date of the statute of repose (December 5, 2000) under the summary judgment analysis we apply here, there was no breach of the duty to indemnify for “losses or liabilities.”
Ledcor also argues that the canons of statutory construction require that we hold that the statutory language “all claims or causes of actions” in RCW 4.16.300 and RCW 4.16.310 creates a meaningful distinction between “claims” and “causes of action.” Specifically, Ledcor argues that even if it did not have a cause of action until Freeman refused tender, it did have a claim for indemnification and defense as soon as it was sued by Parkridge. We disagree.
We construe statutes as a whole to give effect to all the language and to harmonize all provisions.
Ledcor’s claim for contractual indemnity, like the claim for equitable indemnity, did not accrue until after the
CONSTRUCTION SUBCONTRACT
Ledcor also argues that its breach of contract claim against Freeman based on construction defects accrued when Parkridge Apartments sued Ledcor on November 29, 1999. Freeman argues that any claim based on construction defects must accrue on the date of substantial completion, December 30,1993. We hold that genuine issues of material fact bar summary judgment on this claim for breach of the subcontract between Ledcor and Freeman.
Following the analysis laid out in Del Guzzi, we begin with the statute of repose. As we have already held in this opinion, the term of the statute of repose for summary judgment purposes was from December 5, 1994 to December 5, 2000.
Next, we must determine whether Ledcor’s suit satisfies the applicable statute of limitation. Although the parties fail to address in their briefing what limitation statute applies, we presume the six-year written contractual statute of limitation applies to this claim.
Ledcor argues that this cause of action did not accrue until Parkridge sued Ledcor on November 29,1999. Relying heavily on North Coast Enterprises, Inc. v. Factoria Partnership.
In North Coast, this court refused to apply the discovery rule to a construction contract, but a more recent
It is unclear from the record before us whether Ledcor, in the exercise of due diligence, should have discovered the alleged breach of contract before it did. For example, if Parkridge’s suit is based, in part, on work Freeman did after the date of substantial completion, we fail to see the relevance of that date as a bar date for this action. Likewise, it is unclear whether the types of alleged defects could have been discovered earlier. In short, these questions present genuine issues of material fact. Accordingly, we reverse the dismissal of this claim for breach of the subcontract.
We affirm summary judgment dismissal to the extent of the equitable indemnity claim and the breach of the duty to indemnify. We reverse the dismissal of the breach of subcontract claim, and remand for further proceedings.
Grosse and Kennedy, JJ., concur.
RCW 4.16.310.
Concrete and Steel Systems, Inc., is a third party defendant, but not a party to this appeal. Ledcor represents that its claims against Concrete await the outcome of this appeal.
CR 56(c).
Mountain Park Homeowners Ass’n v. Tydings, 125 Wn.2d 337, 341, 883 P.2d 1383 (1994).
Mains Farm Homeowners Ass’n v. Worthington, 121 Wn.2d 810, 813, 854 P.2d 1072 (1993).
Greater Harbor 2000 v. City of Seattle, 132 Wn.2d 267, 279, 937 P.2d 1082 (1997) .
Dien Tran v. State Farm Fire & Cas. Co., 136 Wn.2d 214, 223, 961 P.2d 358 (1998) .
105 Wn.2d 878, 719 P.2d 120 (1986).
Del Guzzi, 105 Wn.2d at 883.
Rice v. Dow Chem. Co., 124 Wn.2d 205, 211-12, 875 P.2d 1213 (1994).
(Emphasis added.)
RCW 4.16.300 (emphasis added).
101 Wn. App. 923, 6 P.3d 74 (2000), aff’d, 144 Wn.2d 570, 29 P.3d 1249 (2001).
Lakeview Blvd. Condo. Ass’n, 101 Wn. App. at 930.
133 Wn.2d 509, 946 P.2d 760 (1997).
Barbee, 133 Wn.2d at 511.
Barbee, 133 Wn.2d at 512.
Barbee, 133 Wn.2d at 513.
Barbee, 133 Wn.2d at 513.
Barbee, 133 Wn.2d at 517.
Barbee, 133 Wn.2d at 512.
Barbee, 133 Wn.2d at 512-13.
Rice, 124 Wn.2d at 211-12.
Health Ins. Pool v. Health Care Auth., 129 Wn.2d 504, 508, 919 P.2d 62 (1996).
Allan v. Dep’t of Labor & Indus., 66 Wn. App. 415, 418, 832 P.2d 489 (1992).
Harmon v. Dep’t of Soc. & Health Servs., 134 Wn.2d 523, 530, 951 P.2d 770 (1998).
State v. Akin, 77 Wn. App. 575, 580, 892 P.2d 774 (1995).
(Emphasis added.)
(Emphasis added.)
The American Heritage Dictionary of the English Language 47 (3d ed. 1992).
Beckman v. Connolly, 79 Wn. App. 265, 273, 898 P.2d 357 (1995) (quoting Toll Bridge Auth. v. Aetna Ins. Co., 54 Wn. App. 400, 404, 773 P.2d 906 (1989); Avemco Ins. Co. v. Mock, 44 Wn. App. 327, 329, 721 P.2d 34 (1986)).
Barbee, 133 Wn.2d at 517.
Barbee, 133 Wn.2d at 517-18 (citing Smith v. Jackson, 106 Wn.2d 298, 302, 721 P.2d 508 (1986); Earley v. Rooney, 49 Wn.2d 222, 228, 299 P.2d 209 (1956); Hanscome v. Perry, 75 Md. App. 605, 542 A.2d 421,425 (1988); 42 C.J.S. Indemnity § 44, at 137 (1991)).
(Emphasis added.)
Koch v. City of Seattle, 9 Wn. App. 580, 584, 513 P.2d 573, review denied, 83 Wn.2d 1004 (1973); George Sollitt Corp. v. Howard Chapman Plumbing & Heating, Inc., 67 Wn. App. 468, 475, 836 P.2d 851 (1992).
42 C.J.S. Indemnity § 21.
42 C.J.S. Indemnity § 21.
Barbee, 133 Wn.2d at 517 (citing Smith, 106 Wn.2d at 302; Earley, 49 Wn.2d at 228; Hanseome, 542 A.2d at 425; 42 C.J.S. Indemnity § 44, at 137).
140 Wn.2d 348, 997 P.2d 353 (2000).
Schwindt, 140 Wn.2d at 353.
Schwindt, 140 Wn.2d at 353.
While Freeman argues that the proper bar date for the statute of repose was December 30, 1999, six years after the date of substantial completion, we rejected that contention in our analysis. Nevertheless, the principle that Freeman argues is correct: its duty to indemnify had not arisen as of the proper bar date under the statute of repose.
City of Seattle v. Fontanilla, 128 Wn.2d 492, 498, 909 P.2d 1294 (1996).
94 Wn. App. 855, 859, 974 P.2d 1257 (citing City of Algona v. City of Pacific, 35 Wn. App. 517, 521, 667 P.2d 1124 (1983)), review denied, 138 Wn.2d 1022 (1999).
Architechtonics Constr. Mgmt., Inc. v. Khorram, 111 Wn. App. 725, 737, 45 P.3d 1142 (2002).
Architechtonics, 111 Wn. App. at 728.
Architechtonics, 111 Wn. App. at 737.