delivered the opinion of the court:
On September 10, 1909, the Parker-Washington Company, plaintiff in error, entered into a contract by which it agreed to construct for the city of Chicago, defendant in error, the foundations of a boiler room, auxiliary buildings and chimney of a pumping station at One Hundred and Fourth street and Stewart avenue, in the city of Chicago, and to complete the same, by December 22, 1909. The work was not" completed until March 5, 1910, seventy-three days after, the date fixed for its completion. The contract contained the following provision: “It is distinctly understood and .'agreed by the parties hereto that the work to be performed hereunder shall be completed within the time hereinabove fixed for its completion. Inasmuch as failure to complete the same within the time herein fixed will work an injury to the city of Chicago, and as damages "arising -from such failure cannot be calculated with any degree of certainty, it is hereby agreed that if such wprk js_ not.fully completed within the time fixed herein there shall be deducted from the contract price and retained by said city, as its ascertained and liquidated damages, the sum of fifty dollars ($50) for each and every day passing after the date fixed for the completion, until said work is fully completed as specified.” When the work was completed the defendant in error retained the stipulated sum of $50 a day for the seventy-three days as liquidated damages and the remainder of the contract price was paid. The plaintiff in error brought suit in the municipal court of Chicago for the sum so retained and also for a balance due on another contract. The court tried the case without a jury and found in favor of the plaintiff for a balance due on the other contract, but found against the plaintiff on this contract on the ground that the defendant was justified in retaining $3650 as liquidated damages. Judgment was entered accordingly, and the plaintiff appealed to the Appellate Court. for the First District and assigned as error the holdings of the municipal court on propositions of law and the refusal to allow the full sum claimed on both contracts. The Appellate Court affirmed the judgment, and a writ of certiorari was awarded to bring the record to this court for review.
The law permits parties competent to contract and free to do so, in the exercise of their judgment, to make their own contracts, and the proper function of courts is to enforce such contracts as made, where they do not conflict with any rule of law or good morals or the declared public policy of the State. When the intention of the parties to a contract is ascertained it is ordinarily the duty of the courts to carry it out, (United States v. Bethlehem Steel Co.
We do not see how there can be any. doubt as to the meaning of the parties as expressed in this contract, inasmuch as they specified that the failure to complete the work would work an injury to the city and the damages arising from the failure could not be calculated with any degree of certainty, which brings the case exactly within the rule of law on the subject. Not only did they express the fact that the damages could not be calculated with any degree of certainty, but that was the truth. The construction contracted for was a part of a pumping station for pumping water from Lake Michigan, to be distributed to the south and southwest parts of the city for the use of the inhabitants and for protection against fire. The city, in its corporate capacity, would suffer no damages by the failure to complete the work, but the citizens in whose behalf the contract was made would suffer damages which it would be practically impossible to prove. The contract was made by the city for the purpose of preserving the health and promoting the convenience and welfare of its citizens and protecting them and their property. (Brooks v. Wichita, 114 Fed. Rep. 297.) It is beyond question that there could be no estimate of damages or compensation for the inconvenience to the public or damage resulting from a failure to complete the contract as agreed, (Harlev v. Sanitary District,
Counsel insist that the defendant could retain nothing as liquidated damages because contractors for other work did not complete their contracts, and the pumping station, therefore, could not be used before the plaintiff completed its work. The pumping station was designed to bring water through a tunnel from Lake Michigan, and the tunnel was divided into three sections and different contracts were let for the construction of the sections. By these contracts all the work- was to be completed more than nine months before the time fixed for the completion of this contract, but the tunnel was not completed until after the work of the plaintiff had been finished. Neither the intention of the parties nor the construction of the contract can depend upon what happened afterward, which was not reasonably in contemplation when the- contract was made. Cases where the actual damages suffered have been capable of ascertainment and could be considered by the parties do not apply to the situation here. It was intended that each contract should be performed within the time agreed upon, and if there was a similar stipulation in every contract, the argument would lead to the conclusion that each one could say that nothing could be deducted from his contract price because someone else had not performed.
The contract was construed by the municipal court in accordance with the views we have expressed and the propositions of law held were in harmony with such views.
The judgment of the Appellate Court is affirmed.
Judgment affirmed.
