120 N.Y. 51 | NY | 1890
The agreement of the 1st of June, 1883, between the parties, by which the plaintiffs agreed to furnish and prepare materials for the construction of and to erect one hundred and twelve buildings along the line of the proposed Panama canal, for $163,000, was so modified by contract of *54
December 18, 1883, as to release the plaintiffs from their undertaking to erect the buildings, and the consideration of performance on their part of the contract so modified was reduced to $113,000. With a view to the observance of the provisions of the contract relating to the quality and character of the materials, and their preparation, to be furnished and performed by the plaintiffs, inspection was to be made by agents appointed for that purpose. They were designated by the defendant, and proceeded to examine the materials subjected to their inspection, and by the use of an instrument the inspectors placed upon the materials marks indicating approval and rejection, as they determined them to be or not to be such as the contract required. The delivery commenced August, 1883, and soon thereafter the inspection so made was partially defeated by the act of the employes of the plaintiffs in procuring a die similar to that of approval, used by such inspectors, and by marking with it materials which had been rejected by the latter, after removal of the marks denoting such rejection. This was carried on by the plaintiffs' employes without discovery by the defendant until January 9, 1884. In the meantime a considerable portion of the prepared materials had gone forward, some of which consisted of those so rejected and fraudulently marked with the false die. At the time of this discovery there was one vessel loaded and another partially loaded with the materials in the harbor near Hunter's Point, the place of the plaintiffs' lumber yard, from which they were taken for transportation to the Isthmus. The defendant thereupon paid to the plaintiffs the amount, by the terms of the contract, then payable, less $20,000 retained by the defendant on account of the delivery and shipment made of the falsely marked lumber. The plaintiffs, however, continued in the performance of the contract, and the defendant received from them the residue in quantity of lumber, and paid them for all delivered subsequently to that time. The moneys, therefore, paid by the defendants to the plaintiffs altogether amounted to $93,000; and this action was brought to recover the $20,000 retained as before mentioned. The plaintiffs were chargeable *55
with a gross violation of their contract, which, unless in some manner waived by the defendants, constituted a defense to the action. The mere direction of the defendant to the plaintiffs to proceed with the performance and completion of their contract would not constitute a waiver, but the evidence given by the plaintiffs tended to prove that something more than that took place on and after the discovery of the fraudulent device before referred to, used by the plaintiffs' employes. When their attention was called to it by defendant, the plaintiffs asserted their ignorance of the false marking and their personal innocence in respect to it, and upon the trial they testified to the truthfulness of such assertion; and further, their evidence tends to prove that at the time the $20,000 was reserved it was understood, and the arrangement between the parties was such that the plaintiffs should allow to the defendant such damages as it had sustained by reason of the delivery of the rejected materials, which the defendant had been induced to take and transport to Panama by means of the use of the false die; that the sum retained was reserved as indemnity for that purpose, and that the plaintiffs should, in view of such arrangement, proceed with the performance of the contract, and that at the request then made by the plaintiffs of the defendant the latter should send back, at the expense of the plaintiffs, lumber not within the requirement of the contract, which had been delivered to the defendant, and that the plaintiffs would supply its place with other lumber. The evidence on the part of the defendant was not in harmony with that of the plaintiffs in some essential respects, but for the purposes of the question on this review it is unnecessary to refer specifically to it. The quantity of material consisting of prepared lumber for the buildings, was upward of two million feet. There seems to have been no question about the delivery of the quantity required by the contract. Nor does it appear that it was not all appropriated and used for the purpose contemplated by it. The delivery and shipments were made, from time to time, from a date in August, 1883, until in February, 1884, and about one-half of it was *56
transported from the place of shipment to the Isthmus after January 9, 1884. The trial court held that there was no question for the jury and directed a verdict for the defendant. And upon the exception taken to such ruling the main question arises for consideration. If the right to submit any question of fact to the jury was dependent upon the complete performance of the contract by the plaintiffs, the action was properly disposed of at the trial, because it cannot be said that the delivery, shipment and use, in the construction of the buildings, of the fraudulent materials produced acceptance of them by the defendant. Although it does not appear to what extent the plaintiffs proceeded with the erection of the building before the modification of the contract, relieving them from performance in that respect, was made, it does appear that they had for some time sixty or eighty men on the Isthmus engaged in the construction or doing work preparatory to the erection of the buildings there. The time of performance provided by the contract was nine months from its date, which would not then expire until the first of March. Whatever of the falsely-marked lumber was put into the construction of the buildings without the prior knowledge of the defendant and approval of its use, would not be deemed accepted by the fact that the defendant or the Panama Canal Company took possession of and used the buildings after they were erected. The defendant could still insist that the plaintiffs had failed to perform their contract, by way of defense to any action brought by them upon it, or otherwise to recover compensation for the lumber. (Smith v. Brady,
The judgment should be reversed and a new trial granted, costs to abide the event.
All concur, except FOLLETT, Ch. J., dissenting, and HAIGHT, J., not voting.
Judgment reversed. *58