PARAGON JEWEL COAL CO., INC. v. COMMISSIONER OF INTERNAL REVENUE
No. 134
Supreme Court of the United States
Argued March 8, 1965.—Decided April 28, 1965.
380 U.S. 624
*Together with No. 237, Commissioner of Internal Revenue v. Merritt et al., also on certiorari to the same court.
Philip B. Heymann argued the cause for respondent in No. 134 and petitioner in No. 237. With him on the brief were Solicitor General Cox, Assistant Attorney General Oberdorfer and Melva M. Graney.
John Y. Merrell argued the cause for respondents in No. 237. With him on the brief was Paul P. Senio.
Seymour S. Mintz and Robert K. Eifler filed a brief for Jewell Ridge Coal Corp., as amicus curiae, urging reversal in No. 134.
John Y. Merrell and Paul P. Senio filed a brief for Raymond E. Cooper et al., as amici curiae, urging affirmance in No. 237.
MR. JUSTICE CLARK delivered the opinion of the Court.
The issue in these consolidated tax cases is whether the lessee1 of coal lands is entitled to percentage depletion on all the gross income derived from the sale of the coal
The mining contractors, respondents in No. 237, claimed an allocable portion of the allowance for the years 1954 through 1956, while the lessee, petitioner in No. 134, claimed the right to the entire depletion deduction for 1955 through 1957. In each case the deduction was denied the taxpayer. However, the Commissioner now takes the position that the lessee is entitled to the entire allowance;2 the Tax Court so held, 39 T. C. 257, but the Court of Appeals agreed with the contractors. 330 F. 2d 161. We granted certiorari in No. 134, 379 U. S. 812, and in No. 237, 379 U. S. 886, and consolidated them for argument. We have concluded that the Tax Court was correct and reverse the judgment of the Court of Appeals.
The parties agree that the principles of our opinion in Parsons v. Smith, 359 U. S. 215 (1959), are controlling here. There we held that the deduction is allowed in recognition of the fact that mineral deposits are wasting assets and that the deduction is intended as compensation to the owner for the part used in production; that there may be more than one depletable interest in the same coal deposit, but that the right to an allocable portion of the allowance depends on the ownership of an economic interest in the coal in place since the statute makes the deduction available only to the owner of a capital interest in such deposit; and, finally, that the legal form of such capital interest is unimportant so long as it constitutes a right with regard to the coal in place.
Paragon, on the other hand, says that Congress never intended for contractors mining coal to have a depletable interest as evidenced by statutory enactments adopted subsequent to the tax years involved in Parsons v. Smith, supra; that in the case of a lease the lessor of coal lands is no longer granted a deduction for depletion but is relegated to capital gains treatment only.4 And, finally, that the expenditures made by the contractors were only for equipment which they depreciated and could not constitute an investment in the coal in place as required under Parsons v. Smith, supra.
The Commissioner of Internal Revenue takes the position that only a taxpayer with a legally enforceable right to share in the value of a mineral deposit has a depletable capital or economic interest in that deposit and the contract miners in this case had no such interest in the unmined coal.
THE FACTS.
Paragon took an assignment of written leases on the coal in and under certain lands which obligated it to pay annual minimum cash royalties, tonnage royalties, land taxes, and to mine all or 85% of the minable coal in the
Paragon made oral agreements with various individuals and firms to mine the coal in allocated areas under its leases. They were to mine the coal at their own expense and deliver it to Paragon‘s tipple at a fixed fee per ton for mining, less 2½% for rejects. It was understood that this fee might vary from time to time—and it did so—depending somewhat on the general trend of the market price for the coal over extended periods and to some extent on labor costs. However, any changes in the fixed fee were always prospective, the contractors being notified several days in advance of any change so that they always knew the amount they would get for the mining of the coal upon delivery. After delivery to Paragon‘s tipple the contractor had no further control over the coal, and no responsibility for its sale or in fixing its price. The fixed fee was earned and payable upon delivery and the contractors did not even know the price at which Paragon sold.
The contractors agreed to buy power at a fixed rate per ton from Paragon‘s line or put in their own diesel engine generator and compressors. A certain amount per ton was also paid by the contractors for engineering services inside the mine. An engineer provided by Paragon was used to map out or show each of the contractors the particular direction his mine was to take, the locations of adjacent mines, etc. The single engineer was utilized for all of the mines to ensure that they would not run into each other and also so that no minable coal would be
Because of the nature of the coal deposits, it was necessary to use the drift-mining method5 which requires the opening of two parallel tunnels, one for ventilation and the other for working space and removal of coal. In this type operation the roof is supported by leaving pillars of coal in place and erecting wooden supports about every 18 inches.6 However, as the miners withdraw from a mine where the coal seam has been exhausted, they take out the wooden supports and also remove the coal pillars, thus recovering the last bit of minable coal. Because of the method used it often takes six to eight weeks to develop a mine to the point where it can be operated profitably.
The nature of the coal deposits here involved was such that the miners often encountered “a sandstone roll” which is an outcrop of rock which “squeezes” out the coal. When one of these situations is encountered the miners must move large amounts of rock to reach the coal seam. During this period, of course, they are receiving no money because they are not delivering merchantable coal to Paragon‘s tipple.7 At other times, water might accumulate which would have to be pumped out before work
After the coal was removed it was placed in the contractor‘s bins at the entrance to the mine and was later trucked over a connecting roadway built by the contractor to the adjacent road of Paragon and then taken to the latter‘s tipple. Paragon took all of the merchantable coal mined. If its facilities were full at the moment the contractor would fill his own bins and then shut down his mine. The record shows no deliveries by the contractors to anyone other than Paragon.
Although there was nothing said at the time of the oral contracts regarding who was to receive the depletion, the Tax Court found that Paragon expected to receive that deduction and had fixed its per-ton fee for mining with this in mind. The contracts were also silent regarding termination and were apparently for an indefinite period. However, numerous contractors quit mining, and some sold their equipment, buildings, tracks, etc., to others. Under the agreements, those ceasing to operate could not remove the buildings, but could remove all other equipment. It was anticipated that the contractors would continue mining in their allocated areas as long as it was profitable and so long as proper mining methods were used and the coal met Paragon‘s standards. However, the contractors were under no obligation to mine any specific amount of coal and were not specifically given the right to mine any particular area to exhaustion.
The contractors paid nothing for the privilege of mining the coal; they acquired no title to the coal either in place or after it was mined; they paid none of the royalty or land taxes required by Paragon‘s leases; they claim no sublease, no co-adventure, no partnership. Their sole claim to any interest in the coal in place is based on their investment in equipment, connecting roadways, buildings and the costs of opening the mine, and, in some in-
On the basis of these facts the Tax Court concluded as a matter of law that the contractors did not have a depletable interest under their contracts. The Court of Appeals accepted all of the Tax Court‘s findings but held that the latter erred in its conclusions. It reversed on the basis that the contractors were “performing Paragon‘s obligation under its leases and this constituted ample consideration” together with their “continuing right to produce the coal and to be paid therefor at a price which was closely related to the market price” to give them “an economic interest in the mineral [bringing] them within the rationale of Parsons v. Smith. . . .” At 163. We believe that the Court of Appeals was in error in so doing.
STATUTORY PROVISIONS FOR COAL DEPLETION.
This Court has often said that the purpose of the allowance for depletion is to compensate the owner of wasting mineral assets for the part exhausted in production, so that when the minerals are gone, the owner‘s capital and his capital assets remain unimpaired. United States v. Cannelton Sewer Pipe Co., 364 U. S. 76, 81 (1960). Percentage depletion first came into the tax structure in 1926 and has been consistently regarded as a matter of legislative grace.8 We, therefore, must look to the Code provisions and regulations in effect during the years involved to determine whether these contract coal miners acquired a depletable interest in the coal in place.
“(1) Annual depletion deductions are allowed only to the owner of an economic interest in mineral deposits or standing timber. An economic interest is possessed in every case in which the taxpayer has acquired by investment any interest in mineral in place or standing timber and secures, by any form of legal relationship, income derived from the extraction of the mineral or severance of the timber, to which he must look for a return of his capital. But a person who has no capital investment in the mineral deposit or standing timber does not possess an economic interest merely because through a contractual relation he possess[es] a mere economic or pecuniary advantage derived from production. For example, an agreement between the owner of an economic interest and another entitling the latter to purchase or process the product upon production or entitling the latter to compensation for extraction or cutting does not convey a depletable economic interest. . . .”
Treas. Reg. § 1.611-1 (b)(1) .
However, they claim that they are entitled to a portion of the percentage depletion because they have somehow acquired an economic interest in the coal in place. This test was first enunciated in Palmer v. Bender, 287 U. S. 551, 557 (1933), and has since become the touchstone of decisions determining the eligibility of a party to share in the depletion allowance. The contract miners contend that their investments of time and money in developing these mines bring them within the meaning of our cases. We believe that Parsons v. Smith, supra, completely settles this question against them.
In Parsons, the Court enumerated seven factors to be considered in determining whether the coal-mining contracts there involved gave the contract miners any capital investment or economic interest in the coal in place. They were:
“(1) that [the contract miners‘] investments were in their equipment, all of which was movable—not in the coal in place; (2) that their investments in equipment were recoverable through depreciation—not depletion; (3) that the contracts were completely terminable without cause on short notice; (4) that the landowners did not agree to surrender and did not actually surrender to [the contract miners] any capital interest in the coal in place; (5) that the coal at all times, even after it was mined, belonged entirely to the landowners, and that [the contract miners] could not sell or keep any of it but were required to deliver all that they mined to the landowners; (6) that [the contract miners] were not to have any part of the proceeds of the sale of the coal, but, on the contrary, they were to be paid a fixed sum for
each ton mined and delivered . . . ; and (7) that [the contract miners], thus, agreed to look only to the landowners for all sums to become due them under their contracts.” At 225.
The Tax Court found all of these factors present in this case and ruled therefore that Parsons controlled.
The Court of Appeals agreed with the contractors’ position and held, contrary to the Tax Court, that the contracts under which they mined the coal were not terminable at the will of Paragon but gave the contractors “a continuing right to produce the coal and to be paid therefor at a price which was closely related to the market price.” It based its decision on the fact that the operators made “large expenditures of time and money in preparing their respective sites for mining” and that “[i]t would be inequitable indeed to hold that Paragon might . . . then take the benefit of the operators’ efforts at will and without cause.” At 163. We regret that we are unable to agree.
In Parsons the contract was expressly terminable on short notice; here no specific right to terminate was mentioned in the agreement between the parties. However, as the Court of Appeals noted, “the contracts did not fix upon the operators an obligation to mine to exhaustion.” In fact, many of them quit at any time they chose. We are unable to say that it is any more inequitable to allow Paragon to terminate the contracts at will than it is to allow the contractors to terminate work and thereby impose upon Paragon the obligation to get other people to work the mine or forfeit its right under the leases.
In any event, the right to mine even to exhaustion, without more, does not constitute an economic interest under Parsons, but is “a mere economic advantage derived from production, through a contractual relation to the owner, by one who has no capital investment in the
The court below also indicated that it disagreed with the conclusion of the Tax Court that Paragon could set the price at any level it chose under the agreements. It stated that the contractors were “to be paid therefor at a price which was closely related to the market price.” The conclusion of the Tax Court was that while the fee varied somewhat with labor costs, “there [was] no evidence that the amount paid by Paragon was directly related either to the price it was getting for the coal or to the sales price of a particular contractor‘s coal, and the amount was apparently changeable at the will of Paragon.” (Emphasis supplied.) 39 T. C., at 282. After an examination of the entire record, we can only conclude that Paragon at all times retained the right to change its fixed fee at will, and after delivery to the tipple, the contractors could only rely on Paragon‘s personal covenant to pay the posted price. This is insufficient. As we said in Palmer v. Bender, 287 U. S. 551, 557 (1933), the deduction is allowed only to one who “has acquired, by investment, any interest in the oil in place, and secures, by any form of legal relationship, income derived from the extraction of the oil, to which he must look for a return of his capital.” (Emphasis supplied.) Here, Paragon was bound to pay the posted fee regardless of the condition of the market at the time of the particular delivery and thus the contract miners did not look to the sale of the coal for a return of their investment, but looked solely to Paragon to abide by its covenant.
This construction of the Act as to coal depletion is buttressed by the language of the Treasury Regulations which, by example, specifically provide that “an agreement between the owner of an economic interest and another entitling the latter to . . . compensation for ex-
Further, we believe that additional support is given to our construction by subsequent statutory enactments. As noted above, an owner who by contract disposes of the coal in place while retaining an economic interest is relegated to capital gains treatment of the royalties received. However, exemptive language in
Nor does the opinion in Commissioner v. Southwest Exploration Co., 350 U. S. 308 (1956), undercut our conclusion. There the State of California required that the
G, relating to corporations used to avoid income tax on shareholders (including the determinations of the amount of the deductions under section 535 (b) (6) or section 545 (b) (5)).” (Emphasis supplied.) It is interesting to note that when
For these reasons the judgment is reversed.
It is so ordered.
I respectfully dissent. I cannot accept the Court‘s formalistic view of the depletion provisions of the
The factual situation presented by this case is far different from that considered by the Court in Parsons v.
On the other hand, the mines here involved were not strip mines but deep underground mines. The mine operators in the instant case had to use a drift, rather than a strip, method of mining. Unlike a strip-mine contractor, who can begin full production immediately upon removal of the overburden with one employee and a mechanical shovel, the drift-mine operators here had to employ a number of miners and spend many months opening the underground mines. The operations of the miners here included cutting shafts, building a railroad spur, opening ventilation tunnels, shoring the roof of the mine, removing rock and unmarketable coal, and developing entries, cross sections, rooms and air courses, etc. Normally six to eight weeks was required before any mar-
Kyva and Standard, the two partnerships of mine operators involved here, state without challenge that as of the end of 1956, they had invested in machinery, $33,263.81 and $26,901.30, respectively. Their expenses during their first year of operation were, respectively, $76,036.64 and $73,214.02. This expense was primarily capital expense representing investment in the mine, making it ready for exploitation of the coal in place. Unlike Parsons where the bulldozers, trucks and shovels were movable and primarily designed for road building and other work, the major part of the mine operators’ capital investment here consisted of labor costs and was usable only in this particular underground mine operation. The mine operators could look for a return of their investment only to sales of the coal which they were to mine. Moreover, the Court of Appeals held that Paragon‘s contracts with the operators were not terminable at will or upon short notice, and that “the operators had a continuing right to produce the coal and to be paid therefor at a price which was closely related to the market price.” 330 F. 2d 161, 163. Under these circumstances I believe it undeniable that the operators invested considerable time, labor, and equipment in the coal in place. In order to extract the mineral, they pooled their resources, funds, and energies with Paragon, which supplied its base interest and made other investment necessary
The Court tries to assimilate this case to Parsons by stating that Paragon could have terminated the interest of the operators in the coal at any time and that the operators had no right to mine their coal veins to exhaustion. The actual facts, however, reveal that Paragon has never taken steps, nor given the slightest intimation that it might take steps, to terminate anyone‘s contract. As a matter of practical fact the operators could count on mining the coal vein so long as coal remained and selling that coal to Paragon at a rate which varied slightly with the market price of coal. Additionally, the Court of Appeals found that the operators had “a right to mine to exhaustion,” and a “continuing right to produce the coal and to be paid therefor at a price which was closely related to the market price.” 330 F. 2d, at 163. Whether or not the actions of the parties would produce these legal results is, of course, a question of state law. And, it is a clear rule of long standing that this Court, in the absence of exceptional circumstances, accepts the determinations of the Court of Appeals, the members of which are closer to the local scene than we, on questions of local law. General Box Co. v. United States, 351 U. S. 159, 165; Allegheny County v. Frank Mashuda Co., 360 U. S. 185, 191; Ragan v. Merchants Transfer Co., 337 U. S. 530, 534. Moreover, in view of the operators’ considerable investment in the mines and their substantial reliance on being
The Court, in reaching its result, relies upon
Further, I find this case virtually indistinguishable from Commissioner v. Southwest Exploration Co., 350 U. S. 308. In Southwest Exploration, owners of uplands next to offshore oil drilling sites allowed drillers to use their land as a base for offshore drilling operations in re-
must look for a return of his capital. But a person who has no capital investment in the mineral deposit or standing timber does not possess an economic interest merely because through a contractual relation he possess[es] a mere economic or pecuniary advantage derived from production. For example, an agreement between the owner of an economic interest and another entitling the latter to purchase or process the product upon production or entitling the latter to compensation for extraction or cutting does not convey a depletable economic interest. Further, depletion deductions with respect to an economic interest of a corporation are allowed to the corporation and not to its shareholders.”
The Court also attempts to draw support from
Finally, it is argued that the operators were able to recover their investments through depreciation and to allow them depletion as well would be to permit a double recovery of their costs. This argument overlooks the fact that Paragon too is able to recover every cent of its invest-
understandable that they do not use the exact language of
I conclude that the depletion allowance should be properly apportioned between the lessee and the coal mine operators. The operators were not employees or independent contractors hired to perform services. Unlike a man hired to mow a lawn, or shovel snow, or strip-mine coal, they made a substantial investment in opening and developing each individual mine and could look only to proceeds of the sale of coal extracted for a return of that investment. Under these circumstances I believe that the operators meet the test of Palmer v. Bender, supra, which undisputedly applies here, for they have “an economic interest in the . . . [coal], in place, which is depleted by production.” 287 U. S., at 557. While, clearly, the “phrase ‘economic interest’ is not to be taken as embracing a mere economic advantage derived from production,” Helvering v. Bankline Oil Co., 303 U. S. 362, 367, the operators here, unlike the strip miners in Parsons, do not merely derive an economic advantage through production; they also have a substantial capital investment in
