229 Ct. Cl. 524 | Ct. Cl. | 1981
This case is before the court on defendant’s motion to dismiss the petition. After considering the parties’ submissions, we allow that motion without oral argument.
Plaintiff contracted with the Veterans Administration (VA) to renovate portions of the VA hospital in Coatesville, Pennsylvania. Although plaintiff is apparently continuing to perform under the contract, suit has been filed here to resolve certain disputes which have arisen. The record is unclear whether the disputes have ever been presented to the contracting officer for decision, but it is clear there has been no determination by the appropriate agency contract appeals board.
It has long been settled that if a Government contract provides relief for a particular dispute, the standard disputes clause requires the contractor to present the claim administratively before suit can be brought. United States v. Utah Construction & Mining Co., 384 U. S. 394, 402 (1966); Morrison-Knudsen Co. v. United States, 170 Ct. Cl. 757, 762, 345 F. 2d 833, 837 (1965). Once so resolved, this court exercises only a limited review of the administrative decision. See generally 41 U.S.C. § 321 (1976). If, however, the contract does not provide relief, it is equally well settled that the controversy is not subject to administrative determination and may be tried de novo in an appropriate court. See Edward R. Marden Corp. v. United States, 194 Ct. Cl. 799, 805, 442 F. 2d 364, 367 (1971); Len Co. & Associates v. United States, 181 Ct. Cl. 29, 36, 385 F. 2d 438, 442 (1967).
Count I of the petition seeks an equitable adjustment of $1,180,000 and a declaration that the Government materially breached, and thus terminated, the contract when the Government allegedly failed to disclose the true site conditions prior to contract. Count II realleges much of Count I, alleges numerous change orders, and concludes that a cardinal change has occurred for which breach damages lie in an amount identical to that sought in Count I. Count III alleges that a constructive termination for the convenience of the Government has occurred, entitling plaintiff to appropriate damages. Count IV repeats the allegations of differing site conditions and numerous change orders, concluding that plaintiff is thereby entitled to an equitable adjustment as in Count I. Reducing the petition to essentials, plaintiff seeks whatever relief this court will provide for increased costs and lost profits allegedly attributable to differing site conditions and change orders.
Complete relief, however, for these claims appears to be provided in the contract. It has long been settled that
[w]hen the contract makes provision for equitable adjustment of particular claims, such claims may be regarded as converted from breach of contract claims to claims for relief under the contract. See Morrison-Knudsen Co. v. United States, 170 Ct. Cl. 757, 345 F. 2d 833 (1965); Shedd, Disputes and Appeals: The Armed Services Board of Contract Appeals, 29 Law & Contemp. Prob. 39, 74 (1964); Kelly, Government Contractors’ Remedies: A Regulatory Reform, 18 Admin. L. Rev. 145, 147 (1965). * * * [United States v. Utah Construction & Mining Co., 384 U. S. at 404 n.6.]
See also Edward R. Marden Corp., 194 Ct. Cl. at 806, 442 F. 2d at 368; Len Co. & Associates, 181 Ct. Cl. at 51, 385 F. 2d at 451. Here, contract article 3 deals with change orders and authorizes at paragraph (d)
Plaintiffs best argument against this result is that taken together the differing site conditions and the change orders constitute a cardinal change of the original contract. As we have consistently recognized, a cardinal change breaches the contract in a manner not covered by the standard disputes clause and thus a de novo proceeding in this court is proper. E.g., Edward R. Marden Corp., 194 Ct. Cl. at 808-810, 442 F. 2d at 369-370, and cases cited thereat. The touchstone of the doctrine is that Government actions subsequent to the contract so alter the contractor’s duties and rights that wholesale reformation of the contract occurs. While the cardinal change doctrine is clearly good law, this plaintiff has done little more than make the conclusory assertion that such a transformation has occurred. While we sympathize with plaintiff that certain changes have occurred in the manner in which the contract will be performed, and significant additional costs thereby incurred, the facts alleged fall far short of transforming the original contract for renovation into something else. Indeed, although the determination of whether a cardinal change has resulted is not susceptible to a precise calculus,
it is therefore ordered that defendant’s motion to dismiss is allowed. The petition is hereby dismissed.
As the parties both have copies of the contract, we have not set out the contract provisions referred to here and infra.