Lead Opinion
This action was brought to recover a balance of $2,011.17, conceded to remain unpaid by defendant to plaintiE upon a con
The decisive question before us now is whether the strike clause of the contract defeated the defendant’s right to recover such damages under his counterclaim. The contract provides: “ If the
said party of the second part shall be delayed in performing said work or furnishing said material by reason of strike or strikes on the part of workmen or employees, or on the part of the workmen or employees of any sub-contractor, then the time for the completion of said work shall be extended for a period equal to the duration of any such strike or strikes.”
Plaintiff was a member of the Albany Builders’ Exchange composed of various local contractors, while its laborers, carpenters and masons and the workmen of its subcontractors belonged to labor unions which constituted a local association known as the Building Trades Council. By agreement between the Albany Builders’ Exchange and the Building Trades Council, in force for the year beginning May 1, 1920, and ending April 30, 1921, to which arrangement the plaintiff was a party as a member of the Exchange, a scale of wages had been established for the year, effective as to the laborers, carpenters and masons of the plaintiff and as to the workmen of its subcontractors. That arrangement was in effect in September, 1920, when the contract between plaintiff and defendant was made. The main portion of the construction was to be completed January 1, 1921, and that was accomplished. The contract provided, however, for a possible suspension of certain work of connecting two buildings, if a specified interference therewith should arise, with the understanding that said work
During the first four days after defendant notified plaintiff to proceed with the work of connecting the two buildings, plaintiff’s men and those of its subcontractors worked in full -force.: After May first the men did not report for work because work at the old scale of wages was refused for the year then beginning. The strike among the labor unions in the building trades was general'thrdughout the city. This condition lasted until the latter part of July, 1921. For several days after May first plaintiff was unable to obtain any kind of help to carry on the contract. Plaintiff requested the labor unions to furnish men, offering to pay the wages then being offered by the other contractors and any amount additional as might be adjusted later when the' strike was settled;- but the unions refused unless plaintiff would sign the agreement continuing the old scale of wages for a year. Commencing May fifth plaintiff proceeded with the work with such workmen as it could obtain. They were very few in number, especially at the outset-,- some experienced and competent and some not. As' labor conditions improved- and as fast as it could,, the plaintiff increased its: for-de' and satisfactorily completed the- work on July 26, 1921. Subsequent to May 1, 1921, plaintiff did not pay the old scale of’ wages. It paid the. same wages that were paid by other con-' tractors in the city of Albany at the time and the same wages that continued tó prevail at the time of the trial. The-subcontractors had similar experiences. ■
No question is'raised as to the fact that this disagreement with its employees caused the plaintiff to fail - to complete the work within the stipulated time and was sufficient in duration to rólieve the plaintiff from liability if it was a strike within the meaning-of the strike clause of the contract. The point raised by the defendant is that it was not a strike; but a lockout which plaintiff-itself inaugurated; that the delay was caused, riot because its
Webster’s New International Dictionary defines a “strike” as: “ Act of quitting work;' * * * such an act done by mutual understanding by a body of workmen as a means of enforcing compliance with demands made on their employer; a stopping of work by workmen in order to obtain or resist a change in conditions of employment.” A “lockout” is there defined as: “Act of locking out; refusal of an employer to furnish work to employees, used as a means of coercion.” The defendant urges that the employees of the plaintiff quit work because their pay was to be reduced, but we think that it is equally just to say that the employees quit work because they could not obtain the continuance of a higher scale of wages than the plaintiff was willing to offer. They stopped work in order to obtain these higher wages or to resist the change in the condition of their employment as to wages which the plaintiff required of them as the condition of their continuance in its employ. It was not a refusal of the plaintiff to furnish work within the meaning of a “lockout.”' The plaintiff urged them to work but under" a changed condition which the men resisted. We cannot see why this was not such a strike as was contemplated by the building contract. The provision of the contract is general in its terms and" not limited to any particular kind of a strike. It does not by its terms purport to make any distinction between a strike provoked by the voluntary act of the employer and one instituted by the workmen without such provocation. In the case of Delaware, Lackawanna & Western R. R. Co. v. Bowns (58 N. Y. 573) the Court of Appeals had under consideration a similar strike clause in a contract. The holding of the court in that case is well expressed in the headnote as follows: “ In consequence of a reduction of wages, a strike of the miners and other employees in plaintiff’s employ occurred, interrupting its business and preventing it from obtaining all the coal called for. In an action to recover for the coal delivered under the contract, held, that the clause was a limitation upon the absolute undertaking to sell and deliver; that- plaintiff was not prohibited thereby from conducting its mining operations upon the same general principles it would have been governed by, had the contract not been made, nor wa!s it required to resort to extraordinary or unusual means to prevent strikes, but, by necessary implication, had the right, irrespective of its effect upon the action of its operatives, so long as it was done in good faith, and solely with a view to its general business, to adopt ’ such rules and regulations and pay such wages as were usual,
The judgment and order should be affirmed, with costs.
H. T. Kellogg, Acting P. J., Van Kirk and Hasbrouck, JJ., concur; Kiley, J., dissents, with an opinion.
Dissenting Opinion
This case was before this court on a former appeal (202 App. Div. 94). The facts and principles involved are very fully stated in the opinion; only brief references and recitals will be attempted here. The plaintiff, a contracting corporation, entered into a written agreement with the defendant to reconstruct, rebuild and change, according to plans and specifications furnished with said contract, a building in the city of Albany, N. Y. Said contract provided for a time limit on the work, and clause 8 thereof provided as follows: “ In case the party of the first part [who was this defendant] shall sustain any loss by way of damages of any kind by reason of the failure of the party of the second part to fulfill any of the agreements herein contained on its part, such loss or damage shall be deducted from the last payment made to the party of the second part as provided for herein.” Before making the contract aforesaid the defendant had rented the building, as it would be after the construction contemplated by the building contract was completed, for a large rental return, said lease and occupancy to commence after the time limit fixed for its completion in said building contract. He also sold said building subject to the
B. That the delay caused by this change in the work, together with defendant’s failure to exercise his right to take over and complete the contract under the provisions thereof, abrogated the time limit therein. Under the provisions of the contract and by reason of the written notice served on the plaintiff on May 9, 1921, I do not accede to that proposition. Even if that view were taken, defendant could still assert and succeed on his counterclaim. (Crocker-Wheeler Co. v. Varick Realty Co., 104 App. Div. 568; Reading Hardware Co. v. City of New York, 129 id. 292.) My conclusion is that defendant has sustained his counterclaim and, it being for the amount unpaid on the contract, it offsets plaintiff’s claim for balance unpaid.
The judgment should be reversed and complaint dismissed, with costs.
Judgment and order affirmed, with costs.
