Panhandle Fire Protection, Inc. v. Batson-Cook Co.Panhandle Fire Protection, Inc. v. Batson-Cook Co.
Panhandle Fire Protection, Inc. appeals from the order and final judgment entered by the Superior Court of Troup County confirming an arbitration award in favor of Batson Cook Company (“BCC”) and awarding BCC attorney fees under OCGA § 9-15-14. Panhandle asserts that personal jurisdiction and venue were improper in Troup County. Additionally, Panhandle contends that the attorney fees award must be vacated because the superior court failed to make any findings of fact. For the following reasons, we vacate the superior court’s order and final judgment, and we remand with instruction.
The record shows that BCC, a Georgia corporation, was the general contractor for a construction project located in Gulf Shores, Alabama. BCC entered into a subcontractor agreement with Panhandle, a Florida corporation, under which Panhandle agreed to install a fire sprinkler system as part of the construction project (the “Subcontractor Agreement”). BCC andPanhandle dispute over which version of the Subcontractor Agreement was assented to by the parties. According to BCC, the parties agreed to a version of the Subcontractor Agreement containing a choice of law clause which stated that the сontract would “be governed by the law of the state of Georgia,” as well as a Georgia choice of forum and arbitration clause which stated:
AGREEMENT TO ARBITRATE: All claims, disputes and matters in question arising out of, or relating to, this Agreement or the breach therеof... shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then in effect unless the parties mutually agree otherwise. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law.
The location of the arbitration proceedings shall be the city of [BCC’s] headquarters or Atlanta, Georgia.
In contrast, Panhandle contends that the Subcontractor Agreement ultimately agreеd to by the parties did not require arbitration in Georgia. According to Panhandle, the Subcontractor Agreement mutually assented to by the parties incorporated and made controlling an “Attachment X” which stated that “[a]ll or any legal disputes will bе handle [d] in a Florida court.”
In any event, Panhandle commenced work on the project. BCC apparently became dissatisfied with Panhandle’s work and filed a demand for arbitration with the American Arbitration Association (“AAA”). BCC sought to recover exрenses that it had incurred as a result of Panhandle’s alleged breach of contract. Panhandle responded to the demand with several letters to the AAA in which it denied the existence of a Georgia choice of forum and arbitration clause in the Subcontractor Agreement and objected to the arbitration.
The arbitrator subsequently issued an order finding that Panhandle was bound by the arbitration clause and that the Subcontractor Agreement unambiguously provided for the arbitration to be conducted in the city of BCC’s headquarters or Atlanta, Georgia. Consequently, the AAA scheduled an arbitration hearing and notified both BCC and Panhandle. The arbitration hearing was conducted in Atlanta. Panhandle did not participate. The arbitrator found in favor of BCC and awarded it the monetary damages sought in its arbitration demand.
Thereafter, BCC filed a motion to confirm the arbitration award in the Superior Court of Troup County, the location of its principal place of business. Panhandle filed a motiоn to dismiss, arguing that the superior court lacked personal jurisdiction over Panhandle and contesting venue in that court. The superior court confirmed the arbitration award and found that BCC was entitled to recover attorney fees under OCGA § 9-15-14.
1. Panhandlе maintains that personal jurisdiction and venue were improper in the Superior Court of Troup County. As discussed below, we conclude that the superior court’s order and final judgment must be vacated, and the case remanded, because the
(a)
The Subcontractor Agreement.
If BCC’s version of the Subcontractor Agreement is correct, personal jurisdiction and venue are proper in Troup County. Under Georgia law, personal jurisdiction is conferred over a nonresident if the nonresident enters into a contract containing a Georgia choice of forum and arbitration clause.
Galindo v. Lanier Worldwide,
Likewise, venue in the Superior Court of Troup County would be proper pursuant to thе Georgia Arbitration Code, OCGA § 9-9-1 et seq. (“GAC”), under BCC’s version of the Subcontractor Agreement. Although Panhandle contends that the Federal Arbitration Act, 9 USC § 1 et seq., applies since the case involves interstate commerce,
the GAC controls because BCC’s version of the Subcontractor Agreement contains a Georgia choice of law clause and an arbitration clause.
Southwire Co. v. American Arbitration Assn.,
In contrast, if Panhandle proves that the parties never agreed to the Georgia сhoice of forum and arbitration clause, personal jurisdiction and venue in the superior court would be improper. Panhandle is a Florida corporation, the project was located in Alabama, and the only other alleged contact between Panhandle and Georgia was the mailing of letters to the arbitrator by Panhandle’s attorney objecting to the arbitration. “It is well settled under Georgia law that... mailing a response to [an] arbitration notice and... letter [s] to the аrbitrator, standing alone, are not sufficient to confer personal jurisdiction.”
Galindo,
(b)
The Arbitrator’s Decision.
Here, the arbitrator ruled that BCC’s version of the contract controlled and thus that the parties had agreed to arbitrate their dispute. That, however, does not resolve the matter. Under federal and Georgia arbitration law, the threshold question of whether parties to a contract agreed to arbitrate a dispute is normally a matter for a court, rather than an arbitrator, to decide. See
First Options of Chicago v. Kaplan,
Based on the record before us, BCC cannot show by clear and unmistakable evidence that the parties agreed to have the arbitrator resolve whether the version of the Subcontractor Agreement to which the parties mutually assented contained the arbitration clause. The record reflects that Panhandle consistently denied entering into the version of the Subcontractor Agreement containing the arbitration clause and refused to participate in the arbitration proceeding as a result. Moreover, it is clear that Panhandle did not agree to submit the question of arbitrability to the arbitrator merely by sending letters to the arbitrator objecting to the arbitration. Sеe
First Options of Chicago,
(c)
The Superior Court’s Decision.
Having reviewed the hearing conducted before the superior court and the order granting BCC’s motion to confirm thе arbitration award, we cannot discern whether the superior court conducted an independent review of the arbitrability issue or simply deferred to the arbitrator’s decision on the issue. Consequently, we vacate the superior court’s ordеr and remand for the superior court to conduct an independent review of whether the parties agreed to arbitration. See
Galindo,
On remand, if the superior court finds that the parties mutually assented to the version of the Subcontractor Agreement containing the choice of forum and arbitration clause, personаl jurisdiction and venue were proper in Troup County and the arbitrator’s award may be confirmed. See Division 1 (a), supra. In contrast, if the superior court finds that the parties never agreed to the choice of forum and arbitration clause, instеad assenting to the Florida forum selection clause contained in Attachment X, then personal jurisdiction and venue were improper, and BCC’s motion to confirm must be dismissed. See
Galindo,
2. Panhandle next argues, and BCC concedes, that the superior court’s order awarding attorney fees to BCC under OCGA § 9-15-14 failed to include the necessary findings of fact to support the award.
When a trial court exercises its discretion in assessing attorney fees and costs of litigation under OCGA § 9-15-14, it is incumbent upon the court to spеcify the conduct upon which the award is made. A judgment devoid of such findings must be vacated and the case must be remanded for reconsideration.
Judgment vacated and case remanded with instruction.
Notes
Citing to
Tampa Motel Mgmt. Co. v. Stratton of Fla.,
Contrary to Panhandle’s assertion, the fact that the аrbitrator chose to rule on the arbitrability issue does not cause “the entire case for jurisdiction and venue in the Superior Court of Troup County [to] disintegrate[ ].” The arbitrator’s ruling on the arbitrability issue has no effect at all, one way or the other, on the question of personal jurisdiction and venue, since that question is to be independently resolved by the superior court.