*130 OPINION
In mid-1980, appellant Pandelis Construction Company (“Pandelis”) agreed to construct a medical building for respondents Jones-Viking Associates, et al. (“Jones-Viking”). Pandelis was to receive, in addition to a fee, half of any savings below a guaranteed maximum cost of 1.2 million dollars. After completion of the project, the parties disagreed as to whether there had been savings. Pandelis sued to recover what it claimed was due. The trial court found that there had been no savings, and entered judgment in favor of Jones-Viking. However, the court refused to award Jones-Viking attorney’s fees. All parties appeal.
Pandelis first asserts that the trial court erred in finding there had been no savings. Findings of fact are reversible only if clearly erroneous, NRCP 52(a); they must be upheld if supported by any substantial evidence, Morris v. Imperial Mortgage Co.,
We also perceive no error by the court in refusing to allow a lay witness to testify as to the types of expenditures that would constitute extras under the contract. See NRS 50.265. 2
*131
As a final assignment of error, Pandelis notes that the court admitted certain summaries of financial documents but said they were admitted not as evidence, but only as statements of the builder’s position. Under NRS 52.275, the contents of “voluminous writings” may be presented “in the form of a chart, summary or calculation” if the writings themselves “cannot conveniently be examined in court.” We are at a loss to explain how something properly admitted under a rule of evidence could not be evidence.
See
United States v. Smyth,
Under its cross-appeal, Jones-Viking contends that the trial court erred in denying its request, pursuant to NRS 18.010,
3
for
*132
attorney’s fees. The court entered its denial without comment. In Lyon v. Walker Boudwin Constr. Co.,
Notes
The excess was paid by Jones-Viking; there is no indication why the witness who gave these figures disregarded that excess.
The trial court made its ruling on the correct basis despite the fact that the parties’ arguments centered on an inapplicable doctrine. Jones-Viking insisted the contract provided unambiguously that there could be no extras, so that the parol evidence rule barred testimony to the contrary. That
*131
argument was utterly meritless, for two reasons. First, the contract provided for “extras” or “changes in the work” in several locations. Second, any changes necessarily would postdate the agreement, and so would fall outside the scope of the parol evidence rule. Silver Dollar Club v. Cosgriff Neon,
The statute was amended between the initiation of this lawsuit and entry of judgment. We note that the version in effect at entry of judgment is controlling. Farmers Home Mutual Ins. v. Fiscus,
Jones-Viking also asserts that the contract created an entitlement to attorney’s fees. That is incorrect. The contract contained the following provision:
In the event that Owner must utilize any legal proceeding or arbitration proceeding to enforce any provision of this Agreement, upon prevailing in such action, Owner shall be entitled, in addition to such other relief as may be available, to a reasonable sum as and for his attorney’s fees and costs therein.
By its terms, this provision applied only if Jones-Viking was forced to sue to enforce the contract. In this case it was Pandelis, the contractor, who sued. Jones-Viking argues, citing no authority, that it would be unfair to apply the terms of this provision literally, and thus unilaterally. However, Jones-Viking undoubtedly is responsible for this clause, and we are not unaccustomed to holding draftsmen to the consequences of their choice of words. Caldwell v. Consolidated Realty,
