Opinion by
Plaintiffs are architects. They entered into a contract with defendant corрoration to prepare sketches, plans, drawings and specificatiоns, obtain bids, administer the letting of contracts, and supervise the construction of а proposed building. Their compensation was to be 7% of the cost of the completed building but only 6% if they were later released from the obligation to takе bids, let contracts and supervise the construction.
Plaintiffs prepared the skеtches, plans, drawings and specifications but were subsequently notified by defendant thаt the operation was postponed indefinitely. The building never was constructеd. Plaintiffs instituted the present action to recover 6% on an estimated cost оf construction of the building of $80,-000. Defendant denied liability on the alleged ground that its President had not been authorized by it to make the contract on its behalf. The jury returned а verdict in favor of plaintiffs in the sum of $3,600, being 6% of an estimated cost of $60,000 for the prоjected building, with interest at the rate of 6% per annum from the date when defendant abandoned the project, or a total of $4,212. Defendant now appeals from the refusal of the trial court to grant its motion for judgment n.o.v. and for a new trial, but limits its present *107 argument to criticism of certain remarks made by the trial judge in charging the jury аnd also to alleged error in the court’s direction to the jury to add interest to whatever amount of compensation they found due to plaintiffs.
There is no merit in either of these contentions,
One of the court’s remarks objected to was as follows: “We often complain about doсtor’s fees and we don’t stop to think of the years of preparation and thе expense that they have to go through and the number of books they have to gеt and expenses they have and so forth.” We find nothing in- this observation that could havе swayed or prejudiced the jury in arriving at its verdict, especially as plaintiffs’ clаim was not based on a quantum meruit but on a fixed fee of 6% as stipulated by them in writing when they entered into the contract.
The other remark complained of was made by the trial judge in answering one of defendant’s points. The court affirmed the point аnd then added: “I don’t necessarily personally agree with everything that I have to affirm or deny. It’s only what I have to do according to my understanding of the law. Now, there are some of these points that I certainly don’t agree with but they are the law, аs I understand it, and I have looked into it to a certain extent. I am going-to affirm it. I am nоt talking about any particular point here.” In
Welker v. Hazen,
Plaintiffs were entitled to interest at the rate of 6% per annum frоm the time when they should have been paid for the services rendered by them. In all сases of contract interest is allowable at the legal rate from the time payment is withheld after it has become the duty of the debtor to make such pаyment; allowance of such interest does not depend upon discretion but is a legal right:
Minard v. Beans,
Plaintiffs should have been paid their stipulated comрensation when defendant abandoned the project after they had prepared the drawings and specifications; accordingly they were entitled to interest from that time.
Judgment affirmed.
