47 P. 599 | Cal. | 1897
Action to recover by C. T. H. Palmer, as assignee of C. A. Warren, contractor, upon a street assessment, and to enforce a lien therefor for grading Broadway, a public street in the city of Oakland. A demurrer was interposed by the defendants to the amended complaint of the plaintiff, which was sustained by the court, and, plaintiff having failed and declined to amend, final judgment went for the defendants. Plaintiff appeals from the judgment, and the cause comes up on the judgment-roll.
The only questions presented relate to the sufficiency of the amended complaint. The resolution of intention to grade “to the official subgrade for macadamizing,” etc., Broadway, from the northern line of Fourteenth street to the northern boundary line of the city of Oakland, was adopted March 18, 1889, and such proceedings were thereafter had that the work was completed prior to June 24, 1890. The improvement was therefore performed under “An act to provide for work upon streets, lanes,” etc., approved March 18, 1885 (Stats. 1885, p. 147), and the act amendatory thereof, approved March 14, 1889 (Stats. 1889, p. 157). The contract under which the grading was performed was dated August 2,, 1889, and the pleader, after averring that the superintendent of streets entered into the same with C. A. Warren, the contractor, continues and avers that he (the superintendent) “fixed the time for beginning said work to be within fifteen days from the date thereof, and the time for completing said work to be within one hundred and eighty days thereafter.” It is also alleged that the work was commenced August 16, 1889, and “under direction of said council by its resolutions Nos. 14,667, 14,853, and 15,062, said superintendent of streets enlarged and extended the time of completing said work, viz., February 4, A. D. 1890, by ninety days, and April 22, 1890, by forty days, and June 17, 1890, by thirty days.” It is further averred that the work was completed according to the “terms of the contract with its said extensions of time.”
Section 6 of the act of 1885 (Stats. 1885, p. 151) confers power upon the superintendent of streets to enter into written
Appellant’s contention is that the expression in the pleading, that “the time for completing said work to be within one hundred and eighty days thereafter,” must be construed to mean one hundred and eighty days from the date of its commencement, which, as before stated, was August 16, 1889, and from which time one hundred and eighty days would extend beyond the date of the first extension. People v. Los Angeles Electric Ry. Co., 91 Cal. 341, 27 Pac. 673, is relied upon in support of this construction. This construction, however, leaves the contract subject to another grave objection, in that it leaves the time of the completion of the contract indefinite. The statute requires the superintendent of streets to fix the time for the commencement and for the completion of the work. This authority is conferred upon and is to be exercised by him, and, until it is done, the contract, as has been said, is inchoate or remains in abeyance. To fix the running of a precise period of time from the happening of an uncertain event is to leave it indefinite. It is not left to the contractor to fix the time within which his contract-may be completed, yet in the present case, as he had fifteen days after
We concur: Haynes, O.; Belcher, 0.
For the reasons given in the foregoing opinion the judgment is affirmed.