History
  • No items yet
midpage
Page v. Structural Wood Components, Inc.
102 S.W.3d 720
Tex.
2003
Check Treatment

*1 appeals’ court of request explain why appeal dismissed, should not have been

I reluctantly agree that we should remand appeals

this case to the court of for consid-

eration of the merits. PAGE, Petitioner,

Herman C.

v. COMPONENTS,

STRUCTURAL WOOD

INC., Respondent.

No. 01-1122.

Supreme Court of Texas.

Argued Oct. April

Decided

terminated, the was we hold that affidavit Consequently, filed. we reverse judgment and render appeals’ the court of take the subcontractor judgment nothing.

I 1997, Page Mark In Herman C. hired $300,000 Sepolio general contractor on a M. Law M. Young, John Office of John project for Houston, remodeling expansion and Young, for Petitioner. in Se- building Page owned Houston. Keeling, Kenneth Elmore A. James subcontractors, in turn polio hired several III, Hudson, LLC, Keeling Hudson Hous- including Components, Structural Wood ton, Respondent. for (Structural Wood), provide Inc. to labor complet- and materials. Structural Wood Chief Justice PHILLIPS delivered mid-March, portion job ed its Court, opinion of the in which Justice progressed 1998. As work on the HECHT, OWEN, Justice Justice struction, Page periodic payments made O’NEILL, SCHNEIDER, Justice Justice $270,000. Sepolio pro- SMITH, totaling Before and Justice WAINWRIGHT however, finished, Sepo- ject Page was and joined. work, quarreled Sepolio lio over the and Chapter per- the Property 53 of Code funds requested additional to finish mits a construction claim subcontractor to refused, 14, project. Page April and on a hen on funds retained the owner 1998, terminated Sepolio’s he “(1) the subcontractor the notices sends Page then hired six new contractors required by chapter in the time and ad- hiring finish the construction. Without (2) required; manner and files an affidavit subcontractors, ditional new contrac- claiming day a hen not later than the 30th 21, completed project July tors on completed.” after the work is Tex. PROP. 1998, $27,074.43. payment for a total case, In this 53.103. the owner Code Meanwhile, Sepolio pay terminated the and contractor because failed to materials, hired other complete contractors in full for its and labor Structur- when, project. question claiming us is filed an affidavit a lien on before al Wood 15, fulfilling requirement 1998, property May thirty-one the affidavit on statute, completed. “work” days Page The subcon- after terminated the contract thirty-one Sepolio. tractor here filed its affidavit with Structural subse- Wood termi- filed lien. quently contract was suit to foreclose on its trial, nated but before trial subsequent well contrac- After a bench court conclud- project. completed July tors finished the The court of that the ed work was on appeals replacement held that work is when when contrac- completed are requirements project. of the initial contract tors finished the The trial court finished, Sepolio jointly severally either the first Page contractor held and and $11,861 by subsequent for contractors. 57 S.W.3d liable Structural Wood damages pre- must plus post-judg- 524. Because we conclude that work actual defined in to a interest court fur- particular relation ment and costs. The tract, and that the work that con- ordered of the lien ther foreclosure individually Page tract was held Page’s property the contract $4,000 in attorney’s liable for Page fees. file “an affidavit claiming lien not later appealed appeals and the court of re- day than the 30th after the work is com formed judgment to eliminate the fore- pleted.” period during 53.103. The order, closure holding that no evidence which a claimant can and must file a lien *3 supported the trial finding court’s that affidavit under section 53.103 is therefore Page had failed to retain percent ten of the period the same that an owner can and price contract required by as section retainage must hold under section 53.101— Property 53.101 of the Code. S.W.3d at completion after the of work. However, 53.103, based on section consequently It is in the best interest of all the court of appeals upheld personal participants construction to know when the judgment against Page, concluding that period thirty-day terminates —the owner Structural Wood would still be entitled to a funds, that it so can release the remaining hen on retained long funds as as the lien original contractor so that it can bud affidavit was filed. Id. at 531-32. get for final payment, its and the claimant court, Like the trial the court of appeals so that it can file the lien affidavit before interpreted the statutory definition of com- that date. pletion as the when date the additional To determine thirty-day period when the project July contractors finished the ends, statutory we look to the definitions 1998. Id. “completion of “work” and of an original II Property provides contract.” The Code “ that ‘[cjompletion’ original of an contract Property

The Texas requires Code work, means the actual owners to retain either “10 percent of the any including change extras or orders rea price contract of the work to the owner” or sonably required contemplated or under “10 of the value of the work ... Prop.Code original contract....” or, using price the contract if there is no Tex. 53.001(15).1 § The Code defines “work” as price, contract using the reasonable value “any part repair per of construction of completed work” for “30 Prop.Code original formed under an contract.” Tex. completed.” the work is PROp.Code 53.001(14). § parties’ § 53.101. These stat retained funds “secure the utory interpretations payment focus on different of artisans and mechanics who service,” perform words within these definitions. labor or including sub contractors such as Structural Wood. Id.

§ 53.102. A Page phrase subcontractor or other claim focuses on the “under ant who to make a wants claim on contract”2 and contends that properly must give notice and work under an individual contract should arose, written, dispute originally At the time this definition contract as however. 53.106(e). Rather, was Property "original found in The statute was Code defines amended agreement in 1997 to move the definition of "an contract” as to which an own- ‘completion’ of an contract” to party directly by implication er is a either or 53.001(15). Property clarity, 53.001(6). Code For we of law.” An 53.001(15). refer to the current section "origi- amended contract can therefore be an statute, nal contract” under the own- may "original er into a premised enter number of 2. The dissent is on the notion that the "Sepolio’s tracts” with different contractors. In this contract case, Page had at least seven and that all the work done was work contem- plated Sepolio under that contract....” 102 S.W.3d tracts: one with and at least six with "Original replacement at 730. contract” does mean contractors. See, First Bank v. e.g., Nat’l be deemed claimants. argues (Tex.1983).3 He terminated abandoned. Sledge, 653 S.W.2d will just as a contract’s amount arguments are strong there Although price change when the contract is later interpretations, we con- both supporting modified, peri- too the retainage so should authority greater weight clude change when the work is od modified. supports Page’s contention that contemplated Page argues that the work is terminated. The ends when a contract necessarily completed under a contract is dem- terminated, history the mechanic’s lien statute when a contract is no addi- tional work to make Legislature’s intent onstrates *4 dependent on indi- requirements the previous vidual A version of contracts. focuses on word Structural Wood the phrased lien statute the retain- that mechanic’s “contemplated” and counters because requires completion requirement “actual age the statute of as: ... reasonably required or con- (10%) per price ten cent of the contract contract,” templated under the work, ten to the ... of such owner court should determine based (10%) same, the per cent of value of initially on when all the work proportion the that the by measured contract is In finished. done, work bears to the to be done work case, the original contemplat- this none, using price or, if the contract expansion ed the remodeling and of the value of the work reasonable building, so lien affidavit could filed computing as a basis of value. any at time pro- within of the ject’s completion. accepting In this inter- 1961, 382, 17, Leg., Act of 57th ch. June pretation, appeals the court of noted that 9,§ (repealed 1961 Tex. Gen. Laws 869 “specify the statute did that not 1983) (current at version only be done the contractor who started 53.101). Co., Hayek In v. Western Steel it, opposed ato substitute contractor.” 786, (Tex.1972), 478 792 S.W.2d Court 57 at argues S.W.3d 531. Structural Wood interpreted language this to mean that interpretation urged alternative percent pro owner retain ten must by Page hardship works a on subcontrac- ject’s many of individ regardless cost how tors, must who file their lien in a affidavits ual construction contracts were awarded. may shorter time and who not if an know Therefore, we held that a subcontractor general owner has terminated the contrac- had steel and to the supplied who concrete posits only tor. Structural Wood its bring foundation contractor could a retain- comports requirement approach with the age just percent not for ten claim interpret that courts lien mechanic’s liberally protect in of rather statute order to hen value the foundation but 3. The dissent not First Bank v. Whirl "[w]e observes must materialmen.” Nat’l forget (Tex. 1974). mechanic’s and materialman’s pool S.W.2d 269 Corp., 517 protect lien statutes are meant to the subcon particular claimant Although the lien in this tractor, general contractor.” subcontractor, general case is a contractors (emphasis original). S.W.3d at How may Con provide labor and materials. also ever, designed protect the statute is not ignore sequently, effect of our we cannot Rather, only subcontractors. we have held general interpretation we contractors: that "the and materialman’s lien mechanic’s applies to all must the statute as it consider liberally statutes of State will be con suppliers of material. laborers and purpose protecting for the of laborers strued percent dissent, for ten of Hayek the entire cost of build- in his focusing on the en- ing the home. Id. project tire instead of the individual con- tracts that a means contractor “who has in Hayek Court’s decision focused performed fully by constructing the foun- on protecting might hen claimants who of building paid dation ... cannot be fund, need to share in the retainage based full until 30 painting after the on the Legislature’s “broad extension finally completed contractor has the last protection and sharing this fund to a work on building. may This be sever- (materialmen).” persons new class of years al after the work of the foundation However, at 793. deter completed.” contractor was Hayek, 478 Hayek placed mined that too great a bur (Walker, J., S.W.2d at 797 dissenting). den on owners and contractors Structural interpretation Under Wood’s creating “an unreasonable retainage re statute, the current an owner who termi- quirement on who origi owners enter into nated a contract before the con- 16, 1973, nal May contracts.” Act of 63rd project struction was completely finished 96, § Leg., ch. 1973 Tex. Gen. Laws 215 would not have to release the ten 1983) (current (repealed version at *5 retainage until thirty days after all the Prop.Code 53.001). § In response, the job. new contractors finished the if Even Legislature amended the statute at its postponed comple- an economic downturn regular next analysis session. The bill years, tion for the general terminated stated that “original legis the intent of the payment tractor could not claim its final lation was for the retainage require 10% project until later completed. was apply contract, ment to to each individual is, an delay payment Such indefinite in we job” not the total cost of the and that the believe, exactly what the Legislature was purpose “carry bill’s was to out the intent trying prevent to it when added refer- original legislation which created the original ences to “an contract” in its defi- retainage requirement 10% by limiting the ” price” nitions of “contract and “work.” to 10% each individual contract.... Prop.Code (14). 53.001(1), § See Tex. Judiciary, Analysis, House Comm. on Bill (1973). H.B. Leg., Tex. 63rd R.S. Hardship possibility caused language The new added references to “an delay just such would not be limited to original contract” in the contractors, definitions of general but would also affect price.” “work” and “contract “Work” was lien A generally. longer claimants retain- “any repair defined as construction ... or age period give potential would lien claim- performed pursuant which is to an original longer ants a time which to file their contract,” price” and “contract was defined affidavits, delay but would also a lien “the any as cost to the owner for construc claimant’s to ability enforce a lien on the repair tion ... performed pur or which is retainage. owner’s A subcontractor who suant to an original May contract.” Act of early example, had finished its work —for 16, 1973, 2(d), § Leg., 63rd ch. 1973 the subcontractor who laid the foundation 1983) (cur (repealed Tex. Gen. Laws for a building take little comfort —would Prop.Code 53.001). rent version at having period extended which to claim a hen on the owner’s retained funds Focusing initially on the work contem- many those funds were retained for plated may give a subcontractor more years. months or lien, perfect time to a it may but also greatly delay payment for contractors in Nor do we agree with Structural Wood’s general. pointed As out contention that subcontractors need to be Justice WalkeR “ ‘completion’ of an phrase defined the rely initially able on the work contem- original contract.” plated under contract in order 53.001(15). Moreover, period thirty-day begins when the know any “includ[es] ex specified that the term interpretation, our run. Under reasonably required or change tras orders true that a not be subcontractor would contemplated” by the contract. rely able on a visual examination Thus, if additional work to parties add worksite in order to determine whether contract, will not contract completed. the work has been A subcon- also completed until that work is com be half-completed pro- tractor viewed a who Likewise, parties if the scale back pleted. ject assumed the lien affidavit will be project, contract com yet due would run the risk pleted complet when the reduced work general had been terminated If ed. the owner or the contractor termi passed. the affidavit deadline had nates the then no additional work may But examination not be mere visual contemplated can be under enough interpretation. either To Hayek analogy borrow the from dis- sent, even under Structural Wood’s inter- recognizes The mechanic’s hen statute

pretation a foundation subcontractor would often change that construction contracts likely way have no to know when an interi- project As one progresses. commenta- or-painting paint- subcontractor finished observed, retainage require- tor has ing, and therefore would not know “upon the ment is calculated adjusted price, may as the same from *6 tract Recognizing was finished. this hard- time to 1 Eldon Youngblood, time.” L. ship, a recent treatise noted “[i]n Youngblood Liens, on Texas Mechanics’ situations, many it is difficult to ascertain ed.1999). (2d § the 803.1[b] at 8-20 While actually when all completed; the work is if adjusted upward addi- may be therefore, prudent claimants will their file contract, tional work is added to hen days no later than 30 after the date may adjusted price also be downward. they have finished their own on the work Further, recognizes that the commentator job site.” STERLINGW. STEVES& BRENDAT. uncommon; are not terminated contracts Complete Cubbage, The Guide to Mechan- eventuality he that usu- “[o]ne writes that ic’s & Lien Materialman’s Laws of Texas and, adjusts ally price contract com- (4th ed.2002). at 3-26 Subcon- 3.8.[1] mensurately, the amount of re- precaution tractors who fohow this and file tainage, is the abandonment thirty within lien affidavit of com- contractor.” Id. will pleting fully their own work remain recognized long Texas courts have protected, even contract including contract termi modifications— terminated or abandoned. change nation —can the amount funds required to retained under the contract. Finally, emphasizes the dissent See, Bldg. & e.g., McKalip v. Smith Ma Legislature’s “definition of ‘com 884, Inc., pletion’ any sonry Supply, not include 599 S.W.2d 885-87 does reference 1980, n.r.e.); refd (Tex.Civ.App.-Waco writ whether a contract is abandoned or termi Co., Dowdy v. 498 simply ‘completion’ Supply nated defines as Hale S.W.2d [but] ” (Tex.Civ.App.-Fort 721-22 Worth completion.’ ‘actual at S.W.3d writ). However, no It is therefore consistent Legislature did not define rather, can itself; say that modifications also “completion” by contract word change contemplated by the work Ill tract, and, by implication, the retainage We conclude that the construction terminated, period. a contract When performed contract and the work thereun modified courts have re- complete der are at the time that quirement to require retainage per- of ten abandoned, is terminated or so cent of prior the value of the work to that the lien affidavit must therefore be termination, further recognizing that no thirty days filed within of the contract’s payments contemplated are under a termi- Thus, termination. we hold that Structur See, e.g., Dowdy, nated contract. al Wood’s affidavit was not filed Likewise, case, at 722. no future work is thirty-one days S.W.2d as it was filed contemplated Sepolio’s under a terminated after Page terminated construc tion accordingly contract. We reverse the “comple- we therefore conclude that appeals’ judgment court of and render tion of work” includes a situation in which judgment that Structural Wood take noth the initial contract is terminated. ing against Page. Finally, we note that the has recently pro mandated contractors Justice filed a dissenting ENOCH vide “disclosure statement” to home opinion, in which Justice JEFFERSON engaging owners in residential construc joined. projects. tion 53.255. Justice filed a dissenting ENOCH The disclosure applicable statement is not opinion, in which Justice JEFFERSON case, in this Page Seoplio hired for a joined. commercial, residential, project. not a Nevertheless, the disclosure statement of ap- I agree Because with the court of guidance provides plain- fers because it peals that Structural Wood was not re- English description of an owner’s retain- quired to file until its lien age duties under the mechanic’s hen stat

ute, and these duties are the same in both Sepolio actually completed, I projects pro respectfully residential and commercial dissent. *7 PROp.Code

jects. See 53.101. The disclosure statement informs the owner I “During that: days construction and for 30 Components, Inc. was Structural Wood termination, completion, after final or provided supplies a who subcontractor you abandonment of the contract ... Sepolio. Sepolio Mark a con- should your withhold or cause lender to agreed remodeling tractor to do some who percent withhold 10 pay amount of a Page. Following work for Herman C. performed by ments made for the work payment disagreement, Page terminated your contractor. This is sometimes re 14, 1998, and Sepolio’s April contract on ‘statutory retainage.’” ferred to as hired other contractors to finish the work 53.255(b). PROp.Code Legislature’s originally Sepolio he had contracted with description of the statutory retainage re finally completed to do. The work was on quirement indicates 21, July paid 1998. Sepolio Because never require did not intend to an owner to hold Structural Wood for the materials and la- on to the for statutory retainage more provided, filed a bor Structural Wood thirty than May after the contract’s termi lien on mechanic’s and materialman’s 15, statutory compliance nation. In with original An contract.”6 Page original an Wood sent requirements,1 Structural actu- when the work is 15, 1998, completed and a tract is May claim on notice of its any extras or 18, “including ally completed, May on copy the filed lien affidavit of reasonably required or orders change claims that Structural Wood Page contract, oth- original templated under because timely not file its hen affidavit did replacement or warranty work or er than Sepolio’s terminated contract Page performed repair of the work 14, 1998, was deemed April contract.”7 Page con- completed by that termination. affidavit should have

tends that the hen interpret the Texas upon called When 14, May 1998.2 filed on or before been statutes, hen and materialman’s mechanic’s asserts that the work was Structural Wood exactly “are not they recognizing until actually completed July hberahy construe clarity,”8 we model therefore, timely its hen affidavit was and laborer, artisan, the protect them to filed. here, lan- But and the materialman.9 is clear question of the statutes guage

II no more and we need do unambiguous, Property requires The Texas Code ordinary mean- them their than ascribe to an of the contract owner retain ten support this statute ing.10 The words of during amount the time the work contem that it filed Wood’s claim Structural is in plated affidavit, under an contract it filed its affida- its hen because progress, and for com- actually the work was vit well before of the work.3 The July 21. pleted on that these funds be set requires statute “defi- Page argues Legislature’s that the specifically to ensure that subcon aside clearly mandates that work nition of “work’ tractors, artisans, mechanics, and others perform material and labor are supply who is abandoned when that paid.4 against To have a vahd hen terminated,” authority offers no but he funds, a must meet retained subcontractor Instead, support this “clear” mandate. “(1) only requirements: send[] two statutory language that reads he cites chapter notices in the follows: (2) required; file[ ] time and manner to an contractor Indebtedness claiming a hen not later than an affidavit (1) day the month on the last accrues: day complete after the work is 30th 5 by the declaration which written d.” re- the owner is original contractor or party stating that “any part ceived the other The statute defines “work” as *8 has been terminat- original repair performed of or under construction 53.055, Sledge, v. 653 S.W.2d §§ 8. First Nat’l Bank 53.056. 1. (Tex.1983). 286 § 2. See id. 53.101. Co., Zack Burkett Co. v. 9. See Indus. Indem. 3. Id. curiam): (Tex.1984) (per 495 677 S.W.2d § 53.102. 4. Id. Bank, 653 S.W.2d at 288. First Nat’l § 5. Id. 53.103. Gonzalez, 322, 327 82 S.W.3d 10. See State v. (Tex.2002). 53.001(14). § 6. Id. 53.001(15). § 7. Id. (2)

ed; day required original on the last of the month was work under original tract, therefore, in which the contract has been the work was not settled, completed, finally or aban- completed pocket until that actually door doned.11 was installed.16 way provision any This does not refer Appeals’ The Eleventh Court of reason- completed; it merely when work is estab persuasive. “actual ing Defining is com- point lishes the in time from which the pletion” completion” mean “actual is the original owner’s indebtedness to the con only way every to ensure that subcontrac- provision tractor accrues. The is not defi original tor under an construction contract Furthermore, nitional. the mechanic’s and protected: provide materialman’s lien statute does a completion definition of of work contem If, example, the subcontractor who for plated Legisla under a contract. And the pocket had installed the door were [sic] “completion” ture’s definition of does not work, paid he should not for his any include reference to whether a con security entitled to the of a ten tract is abandoned or terminated. It sim fund the full con measured “completion” complet ply defines as “actual Yet, price tract ion.” filing the time for his lien affidavit had Appeals The Eleventh of consid- Court already run at the time when he com ered is con- this same issue—when work work, pleted his he would have been purposes perfect- sidered for of ... rights through divested of his no TDIndustries, ing retainage a hen—in Inc. escaping fault own. There is no of his v. Texas National Bank.13 In that NCNB “completion” the conclusion that means case, a lien subcontractor filed performance the last item com- of against the bank. The bank claimed that work that con pensable and lienable the hen had not been filed. The templated by contract.17 however, appeals, court of held even requires completion The statute actual though an architect certified at work, “any part of con- being work beginning January, the work was repair performed under an struction or actually completed until the end of original contract.”18 The workers hired February pocket door perform by Page were not hired to work construction remodeling different or unrelated to the finally installed.14 Because the term “completion” legislatively defined was both They complete tract. were hired to appeals the court of lit- unambiguous, “ repair construction or that were parts of comple- erally construed the term ‘actual Sepolio’s original con-

tion,’ contemplated under according ... to the rules of common unfinished. usage.”15 pocket Installation of the door tract but left 53.053(b). Prop.Code 11. 16. Id. 53.001(15). Youngblood Youngblood, on Tex- Eldon L. *9 (1996) (em- Liens, § 803.6[a] as Mechanics’ 1992, (Tex.App.-Eastland 13. 837 S.W.2d 270 added). writ). phasis no

14. Id. at 272. 53.001(14). 18.

15.

729 ordinary, unambiguous sabotages hold an Page persuaded has the Court to Court infusing it with counterintuitive really phrase by completion” that “actual doesn’t meaning. that of completion,” “actual shades mean enlarged should meaning of the term be contractor, Sepolio, never The of a include abandonment or termination the work But that we cannot do. We contract. That work had to be original contract. completion differently from cannot define finished others. The other contractors points Legislature.19 Page As himself work, they doing warranty were not out, statutory lan- we are bound repair Sepolio or replace did not courts, possessing legis- no guage: “[T]he merely fin- already performed. They had powers, may enlarge not or alter the lative job contemplated un- originally ished the statutory language. plain meaning The work was not Sepolio’s der given its Wording statutes is actually completed Page when terminated interpretation wording literal April 14. The work Sepolio’s contract on duty here is clearly unambiguous.”20 Our actually completed July on 21. Struc- was The apply the words of the statute. tural filed its lien. Wood today unambiguous, ordi- Court takes Ill

nary phrase, meaning, alters its and turns longer points legislative it into a term of art. The out that his- legal For no Court in- completion” “actually tory Legislature’s does “actual mean “demonstrates completed;” “actually retainage requirements it now means com- de- tent to make In pleted” really pendent contracts.”23 because individual —but Co.,24 actually completed, is not we held that Hayek but is abandoned v. Western Steel terminated, percent retainage requirement it also means that has the ten actually completed.21 project. been This cannot be. meant ten of the entire decided, Legislature provided year has defini- Hayek One clear, unambiguous rejected holding tion of in that case, complains terms. This Court often of the and amended the lien statutes so clarity legislative pronounce- requirement apply lack of would legislative clarity, ments.22 In the face of rather than the each individual incomprehensible today, project as a whole.25 cost Co., Univ., 297, (Tex.1976) Ryan 19. See v. S.W.2d 301 Travelers Ins. 715 S.W.2d 540 172, 1986, C.J., (Greenhill, (Tex.App.-Houston concurring); see Chief 175 also [1st Dist.] n.r.e.) Judiciary (stating Phillips, State writ ref’d that when a statute Justice Thomas 4, 2003), (March rights, http:// substantially modifies common law available at Address entirely rights supreme.courts.state.tx.us/Adviso- statute controls the and obli- www. gations parties brought ry/SOJ.pdf. to an action statute). under that at 23. 102 723. S.W.3d Conn, Supply Sherrod & Co. v. Tri-Elec. Co., 31, (Tex.Civ.App.-Tyler 535 S.W.2d 34 786, (Tex.1972). 24. 478 S.W.2d 793 1976, n.r.e.). d writ ref 25. See House Comm. on Judiciary, Analysis, Bill 21. See 102 S.W.3d at 725. 1059, (1973); Leg., see Tex. H.B. 63rd R.S. Servs., Inc., Bldg. Masonry Sup McKalip v. CDB 44 also v. Smith & See Lawrence 544, Inc., 884, (Tex.2001); (Tex.Civ.App.- ply, S.W.3d 549 Kerrville State 599 S.W.2d 889 Clark, 1980, ("In (Tex. n.r.e.) opinion Hosp. ref’d our v. 923 S.W.2d Waco writ Dist., 1996); Hosp. Legislature’s [the statute] Salcedo v. El Paso Amendment of (Tex.1983); v. Tech was intended to and does have the effect of S.W.2d Lowe Tex. *10 only thing The that is affected termi- Sepolio’s the fact that Besides nation or abandonment is the amount the and that all the was the required to retain: owner is contemplated under done was work work contract, retainage the amount of the may The owner use unearned funds not Further, fund at issue here. to the is not yet paid to an contractor retainage of time the extent the amount complete to construction after the order issue, fund is to be held the owner is ... original contractor’s abandonment that must long the statute tells us how But not relieved of his duties re- he is the work An thirty days garding statutory retainage. from the date is owner be— disregard right cannot a subcontractor’s for completed.26 The statute then defines ... merely that he retain because of considered com- us when work is abandonment or default of the plete actually completed. it is The —when contractor.28 Sepolio’s original work the sub- contract was not until that the It is not difficult understand were done. stitute contractors necessarily adjusted be- amount would agreed-to complet- is never cause The states that “Texas courts Court or abandonment of ed.29 But termination long recognized have that contract modifi- a contract does not relieve an owner of the including termination —can cations— percent ten of the contract duty to retain change required the amount of funds to be price, change it the owner’s obli- nor does It is there- retained under the during that amount gation retain say that contract modifi- fore consistent pendency of the work and for change the work contem- cations can also actually completed.30 the work is contract, and, by implication, plated by the dependent obligations Neither of those period.”27 What the Court retainage upon price; they the contract are strict no grasp implica- fails to is that there is imposed by statute that cannot be duties clear, unambiguous here. There are tion adjusted. altered whether legislative concerning directives

the owner must set aside an amount to IV payment, subcontractor how much ensure mechanic’s and materialman’s Texas aside, long and for how the owner must set who does lien statutes do not focus on keep it set aside. The the owner must work; and when the they focus on whether is no issue of the amount completed. The actually work is Court long of how question more related to the initial “[fjocusing asserts that to retain the ten required an owner is ly contemplated may give a subcontractor question than it is to the lien,” amount perfect doing but that more time to to retain hardship of whether owner for so creates both in the event the lien claimants be percent, the ten even contractor and other long for a might delay payment terminated or abandoned. cause contract is omitted). (citations S.W.3d at 725-26 limiting ... of a 27. 102 fund 10% particular in situations multiple original are contracts supra, where there 803.1[b]. Youngblood, single pro of a executed for the construction ject.”). 29. Id. 26. Tex. 53.101.

731 completed to receive full period time.31 the inal contract was The Court misses original each contrac- point. forget payment, long We must not that the me as as subcontractors, paid chanic’s and materialman’s hen statutes and the sub- tor his subcontractor, protect to are meant the not forced to file retain- contractors were not the The general contractor. subcon age hens. claimant,32 tractor is a derivative and the hand, If, foundation on the other the provisions of deriva governing claims were painting contractor and contractor claimants, including retainage tive hen contractors, general hired con- sub provisions, specifically distinguished are tractor, thirty they then would both have provisions governing rights from the from actual original and remedies of contractors.33 if general to file their hens tract A leading There is a reason for this. them, pay just did not as the contractor expert on Texas mechanic’s and material- retainage contemplates. It is dif- statute points “[p]roperly man’s hens out ficult a scenario where the to envision characterizing original the claimant as an paid in full general contractor would be important contractor or subcontractor is completely he fin- any event before because a subcontractor is not entitled to a do under agreed ishes the work he lien, relatively constitutional and it is diffi original contract. And once that perfect statutory cult for him to hen.”34 actually completed, general work is provisions place pro There are other thirty days only contractor has to wait general origi tect the contractor.35 “[A]n will paid before he is full—and that nal contractor often has a constitutional happen long paid as as he has his sub- automatically, per hen and the manner of contractors, outstanding and there are no simp fecting statutory relatively his hen is retainage Again, hens. le.” protect hen statute was enacted to gives example Court the foun- contractor, unpaid sub paid dation contractor cannot until get who contractor. painting contractor finishes paint- scenario,

ing. In the worst case if the over The Court’s concern owners’ painting original hardship misplaced, foundation contractor and the contractors’ least, very wrong contractor each had their own con- or at the skewed in the tract, they direction, would considering purpose both be an tractor, would Requiring be entitled to their own statute. a subcontractor rights Additionally, particular original and remedies.37 each know only supplying have to wait he materi- would under which has been orig- terminated or aban- his own als or labor has been (citations Youngblood, supra, 31. 102 S.W.3d at 724. 34. at 671 omit- ted). Youngblood, 32. See Eldon L. Mechanics’ and Texas, Liens in LJ. Materialmen’s Sw. See, (accrual § e.g., 35. 53.053 Prop.Code (1972). 670-71 contractor). of indebtedness to See, (notice e.g., § 53.056 (citations Youngblood, supra, at 671 omit- requirements for derivative claimant ted). owner); contractor 53.057 (derivative claimant’s notice for contractual lien); (limitation accompanying supra 53.024 sub- 37. See notes 29-33 and lien). contractor’s text. *12 direct lien claimants to file inequity against requirements doned works a terrible thirty days of actual very persons the statute is intended their liens within particularly contemplated because the hen stat- un- protect, of the work completion require notify does the owner to ute der the of the termination or the subcontractor justi- it that Finally, is ironic the Court provi- abandonment of the contract. The “completion” implic- position fies its —that completion notification of governing sion itly “non-completion” by point- includes — permissive.38 merely statutory ing express to additional and Moreover, particularly the own- because en- language separate legislative used in a position in to know the status er is the best covering actment residential construction contract, placing of his or her own First, express language contracts.40 burden of risk on the subcontractor appear anywhere in the definition does not know if the contract has been terminated and section of the mechanic’s material- unscrupulous potential creates the for statutes,41 retainage or in the men’s lien owner to terminate the contract without itself,42 a rather obvi- lien statute which is subcontractor, thirty to the let the notice Second, it point ous of distinction. is rath- run, days and then contract the work out Court, nevertheless, er bold for the finish, thereby relieving to someone else express and lan- assert that this additional valid encum- himself the otherwise in guage section 53.255 demonstrates above, pointed pur- brance. we out As non-comple- Legislature intended pose of the mechanic’s and materialman’s tion abandonment and termination be protect and ma- hen statute is to laborers implied completion the definition of within

terialmen, not to increase their burden contrary, To the it is section 58.001. risk. undeniably Legisla- certain that the more that a suggests The Court subcontractor “completion” did not recognized ture protect by filing himself a hen can best contract, non-completion of the cover thirty days comple- affidavit within to, therefore, expressly it had refer- for tion of his own work.39 But it is not termination in addi- ence abandonment or legislate requirements, this Court to new completion tion to actual section 53.255. that would ex- particularly requirements only includ- tellingly, Legislature And having to the risk of an other- pose owners in the residential express language ed this numerous, and good wise title clouded with provisions, anywhere and not construction unnecessary, lien claims. The largely retainage provisions. hen Most else has not subcontrac- Legislature Legislature intended assuredly, had the thirty affidavit within tors to file their lien anywhere be- non-completion to count else work; completion of their own construction sides the residential required owners to nor has the expressly have done provisions, would with notify the contract subcontractors so. contractor is terminated. Ab- Texas mechanic’s and mate- Because the requirements, such subcontractors sent requires rialman’s lien statute comply only with the current re- must claimants to file their lien affidavits of the statute. Those literal lien quirements Prop.Code 41. See 53.106. 38. See 53.001.

39. 102 S.W.3d at 42. See id. § 53.101. 40. 102 S.W.3d at within of actual ap- I would affirm the court of

peals. *13 PAGE, Petitioner,

Herman

v. ROOFING, INC.,

MARTON

Respondent.

No. 02-0845.

Supreme Court of Texas.

April

Case Details

Case Name: Page v. Structural Wood Components, Inc.
Court Name: Texas Supreme Court
Date Published: Apr 3, 2003
Citation: 102 S.W.3d 720
Docket Number: 01-1122
Court Abbreviation: Tex.
AI-generated responses must be verified and are not legal advice.
Log In