On or about July 11, 1901, defendant, Grant, as owner, entered into a contract with one Bushman, as principal contractor, to erect a house for him (Grant) upon certain lots in the city of Mason City for the agreed price of $2,600 and a certain house which then stood upon the lots. By the terms of the writing made between the parties, Bushman was to erect a two-story frame house,
the same to be built as Joe Barlow’s house. The roof to be painted, omitting doors in cupboard or dining room side. Outside wall to be sheeted, papered and sided, inside wall to be plastered. First floor lining to be sheeting hoards. Finish flooring unaple. All other floors to he No. 2 fence flooring. The second story floor to he a single floor. Labor and material to be as good as Barlow’s. All outside and roof to receive two coats of paint. All oak to receive two coats of filler and two. coats of varnish. Pine to have two coats of varnish. All according to the drawings, plans and specifications to their fullest meaning and intent, and the said party of the second part covenants and agrees to pay unto said party of the first part for the same, the sum of twenty-six hundred ($2,600.00) dollars and the old house on lot --— dollars lawful money of the United States in payment as follows: The sum of $500.00 when the stone wall is finished; $300.00 when sheeted to the square; $300.00 when main roof is on; $500.00 when ready for plastering; $500.00 when plastering is finished; $500.00 when building is completed.
Plaintiffs Page & Son furnished certain lumber and building material for the structure, the first item being delivered August 19th and the last on October 28, 1901. The Mason Oity Manufacturing Company also furnished material for the building, the first item being delivered October 24th and the last on November 4, 1903. It filed a statement for a mechanics’ lien and afterwards assigned its claim to the plaintiff. The Knapp Hardware
IV. Some other things applicable to each and all of the claims should be set forth before taking them up separately. The contract price for the building, with the terms and times
In this connection appellee contends that payments were not theretofore made in conformity with the contract. We shall not set out the evidence on 'this subject. Suffice it to say that we think they were. The old house was delivered to the contractor almost at once, as it had to be, for it stood in the way of the new structure. The other payments down to and including the one made October 9th, amounting in all to $2,100, were, so far as this lien claimant is concerned, made in full accord with the terms of the contract. The real contention here is that the cellar and stone wall were not included within the contract, and that defendant, as owner,
The Mason City Manufacturing Company is not entitled as a subcontractor to more than it received on its order on the defendant, Grant; and, as the decree passed by the trial court evidently allowed something on account of this claim, it should be modified to this extent.
As to the hardware company claim: This was filed December 12th, and was for the sum of $119.33. The .first item was under date of August 21st, and the last November 13th. No payments were ever made upon it. About $50 of this bill was furnished after the owner had undertaken to complete the building himself, and under a promise that he, the owner, would hold back enough of the contract price to pay the bill. The owner knew, before paying the order drawn upon him by Bushman to the manufacturing company, that the hardware company was furnishing hardware to complete the job, for which it was not being paid. He was not then paying in accord with the terms of his contract, but to complete the job himself, and to pay the balance of the contract price to the manufacturing company. Tie should have kept enough in his hands to pay for the material thus being furnished by tire subcontracting hardware company, and, as he did not do so, he is liable for the material thereafter furnished, amounting to $46.84, with 6 per cent, interest from December 12, 1901, and a lien should be established for that amount in addition to the claim of Page & Son. Our conclusions do not exactly agree with those of the district court, and the case will be remanded for a decree in harmony with this opinion. Defendant will pay two-thii’ds and the plaintiff one-third of the costs of this appeal.
- On plaintiff’s appeal, affirmed. On defendant’s appeal, modified and remanded: