5 P.2d 888 | Cal. | 1931
THE COURT.
This is an appeal from a judgment for the plaintiff in an action on a contractor's surety bond.
On November 25, 1925, the plaintiff entered into a contract with one Worswick whereby the latter agreed to furnish all the material and labor, etc., for the erection and *386 field painting of the structural steel for the Sacramento memorial auditorium, which the plaintiff was under obligation as the general contractor to complete. On the same date the defendant wrote its bond to the plaintiff for the faithful performance of the contract on the part of its principal, Worswick. The contract between the plaintiff and Worswick provided that seventy-five per cent of the valuation of all work installed shall be paid monthly by the plaintiff upon presentation of certificates issued by Worswick. On January 14, 1926, and about ten days after commencement of the work, Worswick, being in need of funds wherewith to proceed with his contract, arranged to and did receive from the plaintiff, concededly without the defendant's knowledge or consent, the sum of $1,000 for which he gave to the plaintiff his demand note in that sum. In January and February, 1926, Worswick furnished steel and labor of the value of $1775.50, on which he had been paid other cash sums aggregating $650. Further payments had been refused by the plaintiff, although seventy-five per cent of the value of the work and material furnished had been demanded, on the ground that the advance of $1,000 had been applied to the payments due. On February 17, 1926, Worswick abandoned the contract. The plaintiff through its president then carried on negotiations with Worswick and his surety, the defendant, in a futile attempt to procure either one of them to complete Worswick's contract. On March 1, 1926, the following letter signed "Pacific Coast Engineering Company, by J.J. Coney, President", was sent to Worswick: "Inasmuch as you are in default in your performance of the agreement entered into between yourself and the undersigned, Pacific Coast Engineering Company, on the 25th day of November, 1925, for the erection of the steel work on the Sacramento memorial auditorium at Sacramento, and this default has continued for a period of more than ten days to our great damage, this will serve to notify you that your contract above mentioned is now terminated and cancelled." At the same time the plaintiff sent a letter to the defendant in which the following pertinent portions appear: "Pursuant to said agreement work was commenced by Worswick and continued by him until the 17th day of February, 1926, since which date he has ceased and failed to carry out the terms and provisions of said *387 contract, and is now in default thereunder. By reason of the terms above stated and in consequence of the position we occupy obligating us to carry out and complete the erection of the steel on this job we are compelled to notify you that we are this day advising Mr. Worswick that his contract is cancelled for his failure and delinquency in the performance of same and we shall proceed with the performance of the obligation undertaken by him thereunder. This notice is given to you to advise you of your status under your bond and we shall hold you responsible for your liability thereunder."
The plaintiff completed Worswick's contract, expending a sum greatly in excess of the original contract price, and sued the defendant in this action on its bond. The trial court found among other things that prior to the abandonment by Worswick of his contract the plaintiff had paid to Worswick at least seventy-five per cent of the value of the work completed under the contract up to that time and the plaintiff had complied in all respects with its obligations under said contract; that the plaintiff, in accordance with the contentions, and evidence produced in support thereof, had advanced to Worswick the sum of $1,000 without a certificate of work done, for the purpose of enabling said Worswick to carry on his work under the contract, and that it was not true that said contract had been canceled or rescinded. Judgment for the plaintiff in the sum of $5,000 and interest was entered.
[1] The trial court made no special finding as to whether the president of the plaintiff corporation had authority to sign the letter of March 1, 1926, so as to bind the plaintiff, and in the absence of any evidence in the record to overcome the primafacie showing of authority in the president (Grummet v.Fresno Glazed Cement Pipe Co.,
The defendant makes two contentions on this appeal: (1) That the letter of March 1, 1926, to Worswick operated to cancel Worswick's contract and the plaintiff could not thereafter maintain an action for its breach against Worswick or against the defendant as his surety; and (2) that the $1,000 *388 note transaction between Worswick and the plaintiff, without the knowledge or consent of the defendant, exonerated the defendant from any liability under its bond.
There is no dispute with the principle that if the letter to Worswick operated to discharge the contractor from liability under his contract with the plaintiff, the surety also is discharged. But the question presented on this point involves the construction to be placed upon the language appearing in the letter to Worswick, i.e., whether by said letter the plaintiff intended to discharge Worswick from liability on account of his default. [2] Whether a notice is one of rescission, or of termination of further performance amounting to an election to stand on the contract and sue for damages for its breach, has been held to be a matter of intent. (See Tuso v. Green,
In support of its second contention, the defendant relies upon sections
[4] The defendant contends that it is established by the authorities cited by it that a premature payment is a material alteration of the contractual obligation which will exonerate the surety without any inquiry into the question whether the surety has been prejudiced thereby. It is the position of the plaintiff that there is authority in point in *390 this state which establishes that the premature payment will not exonerate the surety if it has not prejudiced its rights.
The case first relied upon by the defendant is Calvert v.London Dock Co., 2 Keen, 638 (48 Eng. Rep. Full Reprint, 774), where the contractor abandoned the work and the obligee completed it and sued at law to recover from the contractor and his sureties. The sureties, by a bill in equity, sought to be relieved of liability under their bond on the ground "that the company [the obligee] until the entire performance of the contract, would have retained in their hands, so much of the contract price, as by the contract, they were entitled to retain, as a security for the performance of the rest of the contract; and that by advancing to Streather more than they were bound to do, the company deprived the plaintiffs of the benefit of that security, and thereby, in equity, released them from the bond". It was there said: "The argument however, that the advances beyond the stipulations of the contract were calculated to be beneficial to the sureties, can be of no avail. In almost every case where the surety has been released, either in consequence of the time being given to the principal debtor, or of a compromise being made with him, it has been contended, that what was done was beneficial to the surety — and the answer has always been, that the surety himself was the proper judge of that — and that no arrangement, different from that contained in his contract, is to be forced upon him; and bearing in mind that the surety, if he pays the debt, ought to have the benefit of all the securities possessed by the creditor, the question always is, whether what has been done lessens that security. . . . What the company did, was perhaps calculated to make it easier for Streather to complete the work, if he acted with prudence and good faith; but it also took away that particular sort of pressure, which by the contract, was intended to be applied to him. And the company, instead of keeping themselves in the situation of debtors, having in their hands, one-fourth of the value of the work done, became creditors to a large amount, without any security; and under the circumstances, I think that their situation with respect to Streather, was so far altered, that the sureties must be considered to be discharged from their suretyship." *391
In Bragg v. Shain,
The next case cited is Kiessig v. Allspaugh,
We are next referred to Bateman Brothers v. Mapel,
The defendant next refers us to County of Glenn v. Jones,
The next case relied upon as deeming material the question of prejudice in relation to premature payments is Russell v.Ross,
We come now to the case of Dunne Inv. Co. v. Empire StateSurety Co.,
The cases of County of Glenn v. Jones, supra, and Kiessig
v. Allspaugh, supra, were followed in Silberstein v.Kitrick,
In the next case, Union Oil Co. v. Pacific Surety Co.,
We are finally referred to Mazzera v. Ramsey,
The above resume must make it obvious that the authorities reviewed established the following: (1) That if the premature payment made by the obligee without the knowledge or consent of the surety is one upon which the plaintiff is relying and is dependent for a recovery against the surety, then the payment has materially altered the principal's obligation, the injury to the surety is established, and the surety is exonerated by virtue of the provisions of section
[5] In the present case, as we have seen, the plaintiff is relying and basing his right to recovery upon the $1,000 payment to Worswick, which the plaintiff contends was made within the contract, and therefore premature, and the trial court so found. Under these circumstances and the law as so established, it must be held that the premature payment altered the obligation of the principal under the contract, and that the surety was exonerated.
The judgment is reversed.