Ordered that the order is affirmed insofar as appealed from, with costs.
The defendant, Talisman Contracting Co., Inc. (hereinafter Talisman), was the general contractor for a New York City Housing Authority project. The plaintiff, P&T Iron Works (hereinafter P&T) was a subcontractor on the project. P&T commenced this action against Talisman alleging that Talisman failed to make full payment to P&T for the work it performed and the materials it supplied. In its answer Talisman asserted an affirmative defense alleging that P&T was not entitled to any further payment because P&T failed to pay its employees in accordance with the prevailing wage provision of Labor Law § 220 (3). Thereafter, the Supreme Court granted that branch of P&T’s motion which was to strike the affirmative defense.
It is settled that “no private right of action for the underpayment of wages exists under Labor Law § 220 until an administrative determination in the employee’s favor has been made and has gone unreviewed or has been affirmed” (Marren v Ludlam, 14 AD3d 667, 669 [2005]; see Pesantez v Boyle Envtl. Servs., 251 AD2d 11 [1998]; Matter of Pyramid Co. of Onondaga v Hudacs, 193 AD2d 924 [1993]). Moreover, such private right of action belongs only to those employees who have been underpaid (see Matter of International Assn. of Bridge, Structural & Ornamental Iron Workers, Local Union No. 6, AFL-CIO v State of New York, 280 AD2d 713 [2001]; Matter of Yerry v Goodsell, 4 AD2d 395 [1957]).
Talisman has no standing to assert a cause of action under Labor Law § 220. In any event, it is undisputed that there has been no administrative determination that P&T violated the statute’s prevailing wage provision. Furthermore, contrary to Talisman’s contention, it does not matter that the alleged viola
Accordingly, the court properly granted that branch of the plaintiffs motion which was to strike the defendant’s affirmative defense. Schmidt, J.P., Santucci, Rivera and Spolzino, JJ., concur.