Lead Opinion
[¶1] Appellant P & N Investments, LLC (P & N) obtained a franchise for a Dickey’s Barbeque Pit restaurant to be operated in Frontier Mall in Cheyenne, Wyoming, P & N entered into a lease with Frontier Mall Associates, LP (the Mall), which required the Mall to pay P & N a finish allowance when
ISSUE
[¶2] We rephrase the issue: Do the unambiguous terms of the lease require evidence that subcontractors and the general contractor have been paid in full before the Mall is obligated to pay the finish allowance?
FACTS
[¶3] P & N entered into a ten-year Shopping Center Lease (Lease) with the Mall for approximately 2500 square feet in Frontier Mall in which to operate a Dickey’s Barbeque Pit franchise. The Lease allowed P & N to renovate the space to suit its use as a restaurant. P & N retained East Rochester, New York contractor, CCI Builders and Developers, Inc. (CCI), to act as the general contractor on the project. CCI, in turn, hired a number of local subcontractors to provide materials and perform work on the project.
[¶4] The Lease provided that upon satisfaction of ten express conditions, the Mall would pay P & N a tenant finish allowance of $150,180. The condition that lies at the heart of this dispute requires P & N to provide the Mall satisfactory evidence from P & N’s general contractor and subcontractors that any liens have been satisfied or waived.and an affidavit that “all work has been paid for” before the finish allowance becomes due.
[¶5] Work was completed on the'project in September 2014 and the restaurant opened on schedule. For the purposes of this appeal, it is undisputed that the total cost of construction was $308,929.55 and that P & N paid CCI $308,929.55. P & N submitted an affidavit to the Mall stating:
6. The total cost of construction was three hundred eight thousand nine hundred twenty nine and 55/100 dollars ($308,-929.55). The cost was paid in full by me [Nathaniel Schott, owner of P & N] to CCI.
7. The construction was completed in September 2014,
7. [sic] No liens have been filed on the property or may be filed as a result of construction on the leased premises.
It is also undisputed that CCI did not pay numerous subcontractors a total of approximately $90,000 for work they performed on or materials they provided to the project.
[¶6] Under Wyoming law, contractors have one hundred fifty days from the date of the completion of their work to assert a lien.
STANDARD OF REVIEW
[¶8] We review a grant of summary judgment deciding a question of law de novo. Anadarko Land Corp. v. Family Tree Corp.,
[¶9] When summary judgment is based on interpretation of a contract:
The initial question of whether the contract is capable of being understood in only one way is a question of law for the court. If the court determines that the contract is capable of being understood in only one way, then the language used in the contract expresses and controls the intent of the parties. In such case, the next question, what is that understanding or meaning, is also a question of law. When we review the district court’s summary judgment decisions that a contract is capable of being understood in only one way and what that understanding is, we accord no deference to those decisions.
Claman v. Popp,2012 WY 92 , ¶ 23,279 P.3d 1003 , 1012 (Wyo.2012) (quoting Union Pacific Railroad Co. v. Caballo Coal Co.,2011 WY 24 , ¶ 13,246 P.3d 867 , 871 (Wyo.2011)).
Leeks Canyon Ranch, LLC,
DISCUSSION
[¶10] Our “ultimate goal when interpreting a contract ‘is to discern the intention of the parties to the document.’” Comet Energy Servs., LLC v. Powder River Oil & Gas Ventures, LLC,
[¶11] Section 1.5(b) of exhibit B to the Lease provides:
Tenant shall have furnished evidence satisfactory to Landlord from its general contractor and any subcontractors that any and all liens that have been, or may be, filed have been satisfied of record or waived and an affidavit that all work has been paid for[J
Both parties contend that these terms are unambiguous, but they disagree as to the meaning. A disagreement between the parties as to the meaning of the terms of a contract does not give rise to an ambiguity. Omohundro v. Sullivan,
[¶13] Section 1.5, read in its entirety, indicates that the parties’ overarching intent was to ensure that all those who worked on the P & N job were paid in full, and evidence of that was to be obtained from several sources, including directly from the contractor and subcontractors, and by affidavit from P & N. “Our rules of interpretation require that we interpret a contract as a whole, reading each provision in light of all the others to find their plain meaning.” Pope v. Rosenberg,
[¶14] The first portion of section 1.5(b) requires that P & N furnish “evidence satisfactory to [the Mall] from its general contractor and any subcontractors that any and all liens that have been, or may be, filed have been satisfied of record or waived” before it is entitled to payment of the finish allowance. P & N argues that since the statutory time limit for filing a lien has passed, liens can no longer be filed and thus the terms of this provision have, in essence, been met.
[¶15] We begin by looking at the plain language of the provision. It requires that (1) P & N provide to the Mall evidence from the general and subcontractors that any liens filed by the general and subcontractors have been satisfied and that all other liens that may be filed have been either satisfied or waived, and (2) the Mall must be satisfied with the evidence provided. P & N claims the intent of this provision was to make sure there were no liens on the property, and that the Mall engaged in bad faith when it refused to accept P & N’s statement that no liens have been filed and any other liens have been waived, and instead insisted P & N satisfy it with written lien waivers from CCI and the subcontractors. Every contract imposes on the parties a duty of good faith and fair dealing in its performance and enforcement. Scherer Constr., LLC v. Hedquist Constr., Inc.,
[¶16] While we cannot conclude that the Mall acted in bad faith, we would be hard pressed to conclude that, as a practical matter, the release or waiver requirement has not been satisfied by the passage of time. However, the second part of section 1.5(b) requires that “all work” be paid for before P & N is entitled to the finish allowance. The Mall argues that this provision is unambiguous and that “all work” includes work performed by not just the general contractor, but the subcontractors as well. Because it is undisputed that numerous subcontractors have not been paid, the Mall claims that this provision has not been satisfied. P & N also contends that the Lease provision is unambiguous, but claims it requires only that P & N pay the full cost of construction to CCI and provide an affidavit to that effect to the Mall.
[¶17] We afford words in a contract the plain meaning that a reasonable person would give to them. Hunter,
[¶18] The affidavit P & N submitted to the Mall stated:
The total cost of the construction was three hundred eight thousand nine hundred twenty nine and 55/100 dollars ($308,-929.55). The cost was paid in full by me to CCI.
P & N claims that the affidavit complies with the terms of section 1.5(b), but it does not say that “all work has been paid for,” as required by the Lease. Had the parties intended that only the general contractor needed to be paid in order for the finish allowance to come due, they could have used language to that effect, such as, “the general contractor has been paid in full.” Instead, they used the term “all work.” We will not “rewrite contracts under the guise of interpretation. ...” Comet I,
[¶19] P & N asks us to examine the terms of its agreement with CCI to determine the intent of the disputed language in its contract with the Mall. “While unambiguous contract language is generally interpreted without resort to extrinsic evidence, it need not be interpreted in a vacuum.” 11 Samuel Williston, Treatise on the Law of Contracts § 30:6, at 108 (Richard A. Lord ed., 4th ed. 2012); see also Pokorny v. Salas,
The ambiguity which justifies examining extrinsic evidence must exist ... in the language of the document itself. It cannot be found in the subsequent events or conduct of the parties, matters which are extrinsic evidence. The suggestion that one should examine extrinsic evidence to determine whether extrinsic evidence may be examined is circuitous.
Wolter v. Equitable Res. Energy Co., Western Region,
[¶20] P & N emphasizes the terms of its agreement with CCI prohibiting P & N from communicating with subcontractors. It argues that this prohibition is further evi
[¶21] P & N also points to the standard and custom in the construction industry that the general contractor is responsible for paying the subcontractors in support of its argument that the intent was only to require P & N to pay CCI, citing Black’s Law Dictionary’s definition of general contractor;
One who contracts for the construction of an entire building or project, rather than for a portion of the work. The general contractor hires subcontractors, coordinates all work, and is responsible for payment to the subcontractors.
Black’s Law Dictionary 683 (6th ed. 1990). P & N argues that because it paid CCI, the general contractor, it paid for all work and it was CCI’s responsibility to pay the subcontractors. P & N claims that because it has clean hands, it should not be punished by not receiving the finish allowance or by having to pay the subcontractors directly (when it has already paid CCI) in order to receive the finish allowance.
[¶22] We cannot rewrite the terms of the Lease. Brashear v. Richardson Constr., Inc.,
[¶23] P & N was in a better position than the Mall to ensure subcontractors were paid. Accordingly, the Lease put the burden on P & N to ensure that all work'was paid for, and it specifically required P & N to provide an affidavit to that effect. Read together, the terms of section 1.5(b) indicate that the intent of the parties was for the general and the subcontractors to be paid, and the affidavit stating that CCI had been paid did not satisfy that requirement.
CONCLUSION
[¶24] The Lease provision requiring P & N to furnish “evidence satisfactory to [the Mall] from its general contractor and any subcontractors that any and all liens that have been, or may be, filed have been satisfied of record or waived” and an “affidavit that all work has been paid for” before the finish allowance becomes due is unambiguous. Even if we were to conclude that the passage of time has fulfilled the lien satisfaction and waiver requirement, all work completed by the subcontractors has not been paid for. Accordingly, P & N is not entitled to the finish allowance from the Mall. The district court’s summary judgment in favor of the Mall is affirmed.
Notes
. CCI is not a party to this action, perhaps because of the arbitration clause in its contract with P & N requiring that “[a]ny controversy or claim arising out of or relating to this contract, or the breach thereof, shall be settled by arbitration administered by the American Arbitration Association....”
. Wyo. Stat. Ann. § 29-2-106(a) (LexisNexis 2015) provides:
(a) Except as provided in subsection (c) of this section, any contractor asserting a lien under this chapter shall file his lien statement within one hundred fifty (150) days and every other person asserting a lien under this chapter shall file within one hundred twenty (120) days:
(i) Of the earlier of:
(A) After the last day when work was performed or materials furnished under contract;
(B) From the date of substantial completion of the project on which work was performed or materials were furnished under contract; or
(ii) With respect to a subcontractor, after the last day he performed work at the direction of the contractor or other person authorized to provide direction.
. The identity of the party drafting the contract is one of those surrounding circumstances that we may consider. See Williston, supra, § 30:5, at 84 ("Extrinsic evidence properly considered in deciding whether the contract is ambiguous may include ... whether one of the parties prepared the instrument, so that the language should be construed most strongly against it.”); see Nuhome Invs., LLC v. Weller,
. In their briefs, the'parties dispute whether the Mall could or could not be sued by unpaid subcontractors under a variety of legal theories. That question is not before the Court and is not relevant to the unambiguous terms of the Lease.
Dissenting Opinion
dissenting, with whom DAVIS, Justice, joins.
[¶25] I agree that the lease between the Mall and P & N is unambiguous, but because I interpret the lease differently from the majority opinion, I respectfully dissent.
The disputed lease provision reads:
Section 1.5 Landlord’s Contribution to Construction of Leased Premises. Of the costs incurred by Tenant in constructing or*1108 improving qualified long-term real property for use in Tenant’s trade or business at the Leased Premises (the “Leasehold Improvements”), Landlord agrees to pay to Tenant the lesser of (a) the actual cost of said construction of or improvements to said real property made in accordance with this Exhibit, or (b) the sum of One Hundred Fifty Thousand One Hundred Eighty and 00/100 Dollars ($150,180.00), less any sums owed to Landlord by Tenant under this Lease or this Exhibit, and the excess, if any, shall be paid by Tenant. Landlord’s obligations under the preceding sentence shall not bind any Mortgagee Party of the Shopping Center nor any party acquiring title through or under any such Mortgage Party. The sum to be paid by Landlord hereunder shall be paid by check to Tenant after all of the following conditions shall have been satisfied:
* * *
(b) Tenant shall have furnished evidence satisfactory to Landlord from its general contractor and any subcontractors that any and all liens that have been, or may be, filed have been satisfied of record or waived and an affidavit that all work has been paid for[.]
[¶26] I view this term as imposing two separate but related obligations on P & N, as Tenant. First, P & N is obligated to furnish evidence satisfactory to the Mall from its general contractor and any subcontractors that any and all liens that have been filed, or may be filed, have been satisfied of record or waived. Second, P & N is obligated to furnish an affidavit that all work has been paid for.
[¶27] With respect to the first obligation, I view this as an obligation to perform that is subject to a condition precedent. A condition precedent is “an act or event, other than a lapse of time, which must exist or occur before a duty of immediate performance of a promise arises.” Mad River Boat Trips, Inc. v. Jackson Hole Whitewater, Inc.,
[¶28] In my view, P & N’s obligation to furnish evidence satisfactory to the Mall was conditioned on the requirement that at least one of two events occurred: 1) a lien was filed against the Mall’s property; or 2) a lien may be filed against the Mall’s property. It is undisputed that neither event occurred. No lien was filed against the Mali’s property in relation to P & N’s project, and because the time for any lien to be filed has expired, no lien may be filed. The condition precedent to P & N’s obligation to perform did not come to pass, and P & N was therefore under no obligation to provide evidence of any type concerning lien satisfaction or lien waivers.
[¶29] P & N’s second obligation is to furnish “an affidavit that all work has been paid for.” I do not agree that this provision should be read to refer back to both subcontractors and general contractors. The term requires that P & N furnish an affidavit. Because it is P & N that is to provide the affidavit, I believe a reasonable reading of the requirement is one that requires P & N to attest that it has performed its obligation to pay for all work. I do not agree the language may be extended to add a requirement that P & N attest that the general contractor has also performed all of its separate payment obligations.
[¶30] This interpretation is borne out by the requirement this provision imposes with regard to liens against the Mall’s property. With respect to liens that have been or may be filed, the provision requires that P & N furnish evidence that such liens have been either satisfied or waived. A Ken waiver suggests that there are amounts owing to the party that has agreed to waive its lien, which is inconsistent with the meaning the Mall asks this Court to give the phrase “all work has been paid for.” If “all work has been paid for” means, as the Mall contends, that the
[¶31] The record of nonpayment to the subcontractors on this project is troubling. It is undisputed, however, that P & N paid CCI, the general contractor, for all the work done on the project. P & N did not breach its payment obligations under its contract with CCI, and P & N had no contracts with the subcontractors. Any breach resulting in underpayment of subcontractors was a breach of CCI’s separate contracts with the subcontractors, contracts to which P & N was not a party. I am unwilling to read section 1.5(b) of the lease to make P & N a guarantor under the separate contracts between CCI and the subcontractors. I believe the more reasonable interpretation to give section 1.5(b), and the one that avoids inconsistencies between its terms, is to interpret the requirement that P & N furnish an affidavit “that all work has been paid for” to mean P & N must attest that it, the affiant, has paid for all work it was obligated to pay for.
[¶32] My final observation relates to the opening paragraph of section 1.5. In that paragraph, the Mall promises to P & N a payment of $150,180.00, upon satisfaction of the enumerated conditions. That opening paragraph also put P & N on notice, however, that the Mall would decrease that amount by any outstanding sums owed to the Mall by P & N under the terms of the lease. It seems to me that the Mall could have added similar language regarding outstanding amounts owing to subcontractors, if its intent was to ensure not only that P & N met its payment obligations, but that all subcontractors were paid in full. This certainly would have been a more transparent imposition of that payment obligation.
