OPINION
Appellant, P. McGregor Enterprises, Inc. (McGregor), appeals the granting of a summary judgment in favor of appellees, David Nance and Denman Building Products, Ltd. (Nance and Denman), that ordered that McGregor take nothing against Nance and Denman. We will affirm.
Factual and Procedural Background
On April 5, 2001, McGregor entered into a “Standard Form of Agreement Between Owner and Construction Manager” with Hicks Construction Group, LLC (Hicks).
The above referenced quotation is offered with the understanding and commitment that Denman Building Products will be the subcontractor for the abovereferenced scope of work on the Amarillo project.
The second bid reflects that the sum of $12,800 was added to the bid for per diem expenses for the employees of Denman. Denman’s bid was accepted by Hicks, and a standard contract between the contractor, Hicks, and subcontractor, Denman, was signed on June 25, 2001. Denman commenced its work on the project and, during the construction, submitted change orders to Hicks. Issues arose between Hicks and McGregor that resulted in McGregor terminating Hicks on April 1, 2002. Denman completed its work on the Lubbock project and, on April 18, 2002, submitted a request for final payment to McGregor directly. McGregor paid the final invoice on or about May 14, 2002, as evidenced by a deposit slip showing the check to be deposited in Denman’s bank on that day.
McGregor filed the lawsuit concerning the addition to the Lubbock Ashmore Inn on December 2, 2003, by which it alleges causes of action against Denman in the nature of negligent construction, breach of contract, and civil conspiracy. The original petition also contained allegations against Denman regarding the Amarillo construction project. The Amarillo project was subject to an arbitration agreement and was subsequently arbitrated. The trial court confirmed the arbitrator’s award by an order filed on August 27, 2004. The Amarillo project lawsuit was severed from the matter before the Court. This Court subsequently upheld the arbitration award. P. McGregor Enters., Inc. v. Denman Bldg. Prods., Ltd.,
After severance of the Amarillo portion of the lawsuit, Denman filed a no-evidence motion for summary judgment,
McGregor’s brief basically contends that the trial court erred in granting a motion for summary judgment upon any of the grounds alleged in the motions. Accordingly, we will review all of the theories put forth by Denman. See W. Invs., Inc. v. Urena,
Standard of Review
We review the granting of a summary judgment, either traditional or no evidence, de novo. See D.R. Horton-Texas, Ltd. v. Market Int’l Ins. Co.,
The party moving for a traditional summary judgment has the burden of conclusively establishing the absence of any genuine issue of material fact and that it is entitled to judgment as a matter of law. Tex.R. Civ. P. 166a(c);
In order to prevail on a no-evidence motion for summary judgment, the movant must establish that there is no evidence of one or more essential elements of the claim or claims that the non-movant has the burden to prove at trial. Rule 166a(i). A no-evidence motion for summary judgment will be sustained when 1) there is complete absence of evidence of a vital fact, 2) the court is barred by rules of law or evidence from giving weight to the only evidence offered to prove an essential element of the claim, 3) the evidence offered to prove a vital fact is no more than a mere scintilla, or 4) the evidence conclusively establishes the opposite of the vital fact. King Ranch, Inc. v. Chapman,
Breach of Contract and Implied Warranties
Amid the numerous claims of McGregor against Denman are claims that Denman breached its contract with McGregor. Denman argues that it had no contract with McGregor, and the only contract it had on the Lubbock project was •with Hicks. McGregor responded that it is a third party beneficiary of the contract between Hicks and Denman and, further, the contract between Hicks and Denman contains language that provides that Den-man is directly obligated to McGregor. The contractual language at issue is found in the contract between Hicks and Den-man and is set out below.
SUBCONTRACT WORK To the extent terms of the agreement between Owner and Contractor (prime agreement) apply to the work of Subcontractor, Contractor assumes toward Subcontractor all obligations, rights, duties and redress that Owner assumes toward Contractor. In an identical way, Subcontractor assumes toward Contractor all obligations, rights, duties and redress that Contractor assumes toward Owner and others under the prime agreement.
The language of the contractual provision quoted above sets forth the relationship between the Contractor (Hicks) and
However, McGregor contends that, the contract between Hicks and Denman aside, it had a direct contractual relationship with Denman. This is so, according to McGregor, because it made the final payment for the Lubbock project directly to Denman after Hicks was terminated on that project. The record reflects that, after Hicks was terminated on April 1, 2002, Denman submitted its final bill to McGre-gor directly on April 18, 2002, and McGre-gor paid the bill on or about May 14, 2002. Under the terms of the contract between Hicks and Denman, any termination of the Contractor (Hicks) by McGregor also terminated the subcontract that Denman had with Hicks. Upon termination of Hicks’ contract with McGregor, Denman was contractually bound, after notice of termination of the Contractor, to cease working on the contract. In this case, the work was complete and the only matter remaining, according to the record, was the final payment to Denman. This was the subject matter of the final invoice of April 18, 2002. The record contains nothing regarding any assignment of the contract between Hicks and Denman nor does it contain any information about the terms of any alleged contract between Denman and McGregor that arose as a result of McGre-gor’s termination of Hicks. Rather, McGregor simply asserts that, because the final invoice was sent directly to McGregor and was paid directly to Denman, the two had entered into a contract. Without more, we are asked to imply a contract. Yet, nothing in the record provides the terms of said contract. The payment was nothing more than the final act of the Subcontractor under the previously existing contract. Accordingly, the trial court did not commit error in granting Denman’s no-evidence motion for summary judgment regarding the existence of a contract between McGregor and Denman. Because there is no contract between McGregor and Denman, it follows that Denman could not have breached any expressed warranties that might exist in the contract between McGregor and Hicks.
McGregor contends that Denman breached its common law duty to perform its work in a good and workmanlike manner. Denman replies that it did not owe such a duty to McGregor. A review of the opinions of the intermediate courts of appeal in Texas regarding the question of implied warranties between the owner of a
The record before this Court convinces us that Denman and Nance are entitled to summary judgment as a matter of law on the issues of breach of contract and breach of express and implied warranties. See Rule 166a(c); Browning,
Negligence
McGregor alleges in its petition that Denman negligently performed its work as a subcontractor. Denman replies that, since this was a contractual relationship, McGregor to Hicks and then Hicks to Denman, it only owed duties pursuant to the contract with Hicks and not duties relating to tort law. To support this proposition, Denman cites the Court to Jim Walter Homes, Inc. v. Reed,
The subject matter of the economic loss rule was recently revisited by the Texas Supreme Court in the case of Sharyland Water Supply Corp. v. City of Alton,
McGregor’s cause of action is one for breach of contract. In the original petition, McGregor claimed this cause of action against Hicks, with whom McGregor had privity of contract, and Denman. The cause of action outlined by McGregor in its original petition sets forth a claim for monetary damages due to Hicks’s breach of contract. Therefore, as far as the attempted common law action for negligence against Denman, we hold that the economic loss rule would prevent McGregor from maintaining a cause of action against Den-man. Id. Accordingly, the trial court did not err in granting a summary judgment for Denman and Nance on this issue. See Rule 166a(c); Browning,
Fraud and Civil Conspiracy
The vast majority of McGregor’s brief is consumed with attempting to show the ex
The Texas Supreme Court has spoken about the elements of a civil conspiracy claim on a number of occasions. In Schlumberger Well Surveying Corp. v. Nortex Oil & Gas Corp.,
Initially, McGregor contends that the bid for the Lubbock Ashmore Inn addition was as a result of bid rigging which, McGregor alleges, was just the first step in the conspiracy between Hicks and Den-man. To support this contention, McGre-gor submitted the affidavit of Paul McGre-gor. However, all that the affidavit can be said to aver is that Paul McGregor did not know the total contents of the second bid at the time the contract was awarded. The second bid was not simply $200 less than the bid submitted by the other subcontractor because, on the face of the bid, was 1) the exclusion of tape, bed, and texture, and 2) the requirement that the bid as submitted was based upon the availability of space at the Ashmore Inn for the employees of Denman. There is no evidence that these matters were not submitted to McGregor’s agent, Hicks, or that Denman had any knowledge that the proposals were not submitted to McGregor by Hicks. In fact, the summary judgment evidence established that the bid, as stated above, was submitted to Hicks by Denman.
McGregor then continues by stating that, “Clearly, the lower bid by [Denman], was the result of bid shopping or bid peddling by Hicks and Nance.” However, nowhere in the summary judgment evidence do we find any evidence that Denman or its President, Nance, had any knowledge of the previous bid of the other subcontractor. Such knowledge is an element of bid shopping or bid peddling. See Sipco Servs. Marine Inc. v. Wyatt Field Serv. Co.,
Finally, McGregor’s issue of the alleged fraudulent kickback and gratuity boils down to two elements. First, McGregor contends that David Nance affirmatively represented that Denman gave a cruise to Donald Hicks and his family before the contract for the Lubbock addition to the Ashmore Inn was signed. However, the record belies that contention. The summary judgment proof offered by McGregor on this issue was the testimony of Nance during the arbitration hearing. At that time, Nance was asked, “And when was that?” in reference to when Hicks was , given the cruise. To which Nance answered, “I don’t know the specific date of that.” Two questions later, the question was asked, “Would it [the gift of the cruise] be before the Amarillo contract was signed?” To this question, Nance answered, “I do not know.” From this exchange, McGregor contends that the record shows the cruise was part of a kickback scheme, and that this exchange is more than a scintilla of evidence regarding the existence of that scheme. However, the answers provided by Nance simply stated that on the day he was asked about the timing of the gift, Nance did not know the exact dates. Prior to the trial court’s ruling on the motions for summary judgment and as part of Denman’s summary judgment evidence, Denman produced an affidavit of David Nance that categorically denies that the gift of the cruise was given to Donald Hicks during any period covered by the Lubbock or Amarillo contracts. Nance produced receipts showing that the cruise was ordered and paid for on June 9, 2002. The summary judgment evidence also shows that Hicks was terminated by McGregor on April 1, 2002. Nothing, other than the speculation of McGregor, connects the gift of the cruise to any actions taken regarding any bid or contract.
(e) Statements which are not hearsay. A statement is not hearsay if:
(2) Admission by party-opponent. The statement is offered against a party and is:
(E) a statement by a co-conspirator of a party during the course and in furtherance of the conspiracy.
Tex.R. Evid. 801(e)(2)(E).
McGregor’s contention fails because the rule has been interpreted to mean that there must be evidence to establish a prima facie case of conspiracy separate and apart from the otherwise hearsay statements. See Utica Nat’l Ins. Co. of Tex. v. McDonald,
In the final analysis, there is nothing more than mere suspicion on the part of Paul McGregor to support the allegation of a civil conspiracy to commit fraud between Hicks and Denman. When appellant’s evidence consists of nothing more than suspicion, conclusory statements, speculation, and improbable inferences, summary judgment is proper. See Ptomey v. Texas Tech Univ.,
Having overruled each of McGregor’s issues, the trial court’s granting of the summary judgment is affirmed.
Notes
.Hicks Construction is not a party to this appeal as all matters in controversy between McGregor and Hicks were adjudicated by a final judgment entered against Hicks on December 13, 2010.
. The judgment was modified to eliminate an award of post-arbitration attorney's fees. See id. at 726.
. See Tex.R. Civ. P. 166a(i).
. See Tex.R. Civ. P. 166a(c).
. Further reference to the Texas Rules of Civil Procedure will be by reference to "Rule-" or "rule-."
.McGregor actually cites the Court to the Texas Rules of Criminal Evidence, which were later combined with the Texas Rules of Civil Evidence into the Texas Rules of Evidence.
. The Texas Rule of Civil Evidence 801(e)(2)(E) read the same as Texas Rule of Evidence 801(e)(2)(E).
. Texas Rule of Criminal Evidence 801(e)(2)(E) read the same as Texas Rule of Evidence 801(e)(2)(E).
