3 Mass. App. Ct. 275 | Mass. App. Ct. | 1975
The plaintiff brought this suit under G. L. c. 149, § 29, to collect a balance alleged to be due under a subcontract with the defendant Aberthaw Construction Co. (Aberthaw), the general contractor for the construction of a power plant for the Commonwealth of Massachusetts. The subcontract called in part for the plain
Aberthaw filed objections to the ruling on the burden of proof and to the general finding that the plaintiff had completed its performance under the subcontract, and
If the master’s statement concerning the burden of proof is taken as an assertion that no evidence warranted a finding that the plaintiff failed to perform its contractual obligations fully, the statement was inconsistent with his finding that the bitumastic coating (which was intended, according to his findings, to protect the metal surfaces of the tanks from the elements and water) cracked and peeled within five or six weeks of delivery. That finding warranted an inference of unworkmanlike fabrication. If, on the other hand, the master’s statement is taken as an assertion that all the evidence was in equipoise and that he was left in doubt whether the cause of the cracking and peeling was improper fabrication by the plaintiff or improper treatment by Aberthaw after delivery, he allocated the burden incorrectly. The burden was at all times on the plaintiff to prove that the tanks it supplied met the contract specifications. Powers v. Russell, 13 Pick. 69, 76-77 (1833). Perley v. Perley, 144 Mass. 104,107-108 (1887). Sayles v. Quinn, 196 Mass. 492, 496 (1907). Waldo Bros. Co. v. Platt Contr. Co. Inc. 305 Mass. 349, 359 (1940). Even assuming, as the plaintiff argues, that Aberthaw’s “backcharge” constituted a recoupment claim (this may be doubted: see Beverly Hosp. v. Early, 292 Mass. 201, 204 [1935], and Zani v. Garrison Hall Inc. 300 Mass. 128, 129 [1938]), as to which Aberthaw had the burden of proof, nevertheless the plaintiff’s claim for payment under the contract cast upon it the burden of establishing the positive of the same proposition that Aberthaw’s claim depended on negating: namely, the plaintiff’s workmanlike fabrication. The defendant’s claim did not shift the burden on the plaintiff’s claim away from the plaintiff. Perley v. Perley, supra.
As the case was decided upon an erroneous view of the law, the final decree must be reversed and the case re
The interlocutory decree confirming the report
So ordered.
The general finding cannot fairly be taken to import a more specific finding that the cause of the cracking and peeling was Aberthaw’s improper treatment of the tanks after delivery, rather than the plaintiff’s unworkmanlike application of the bitumastic coating to the metal. Gillis v. Cobe, 177 Mass. 584, 591-592 (1901).
See Mackey v. Rootes Motors Inc. 348 Mass. 464, 469 (1965).