Owens Flooring Co. v. Hummel Construction Co.Owens Flooring Co. v. Hummel Construction Co.
In this accelerated calendar case, submitted on the record and the briefs of the parties, appellant, Altercare of Westerville, Inc. (“Altercare”), appeals from the judgment of thе Portage County Court of Common Pleas entered on September 15, 1999. The court denied Altercare’s motion to stay proceedings in which it and Hummel Construction Company (“Hummel”) were named as defendants by аppellee, Owens Flooring Company (“Owens”), while Altercare and Hummel pursued court-ordered arbitration. Altercare also appeals from the court’s judgment entry of October 8, 1999, denying its motion for rеconsideration.
On October 28, 1999, Owens filed a motion to dismiss this appeal for lack of a final appealable order. This motion was denied on March 23, 2000. Altercare’s appeal is based upоn
Owens, howеver, claimed that this statute is in conflict with
“When more than one claim for relief is presented in an action * * * or when multiple parties are involved, the court may enter final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay. In the absence of a determination that there is no just reason for delay, any order or other form of decision, however designated, which adjudicates fewer than all the claims or the rights and
Thus, pursuant to
In denying Owens’s motion, we concluded that
Returning to the merits of the present appeal, Altercare hired Hummel to construct improvements and additions to a nursing home owned by Altеrcare located in Westerville, Ohio. Their contract included a clause that required that any controversy or claim arising out of or related to the contract, or the breach of the сontract, be resolved by arbitration in accordance with the construction industry arbitration rules of the American Arbitration Association. Owens was not a party to this contract. Owens was subcontractеd by Hummel and completed work on the project valued at $13,185.
During the course of this project disputes developed between Hummel and Altercare. On September 30, 1997, Hummel filed suit against Altercare аnd other parties in the Portage County Court of Common Pleas. As the result of a motion by Altercare, venue was transferred to Stark County. The Stark County Court of Common Pleas ordered that all disputes between Altеrcare and Hummel be decided in binding arbitration. Hummel alleges that Altercare owes it $644,186, subject to various claims by Altercare for delays in completing the work and claims that the work was completеd in an unworkmanlike manner. These disputes were still not resolved by arbitration as of October 1999.
On May 17, 1999, Owens filed suit in the Portage County Court of Common Pleas against both Hummel and Altercare for the $13,185 due for the work it
“The trial court erred as a matter of law when it denied apрellant’s motion to stay proceedings pending arbitration pursuant to
In relevant part,
Generally, public policy in Ohio encourages the resolution of disputes through arbitration.
Kelm v. Kelm
(1993),
In McCourt Constr. Co. v. J.T.O., Inc., this court stated:
“As a general proposition, this court would agree that a party to an action cannot be ordered to submit a claim to arbitration if that party has not agreed to arbitration in writing. Specifically, we would note that, even when some of the claims in an action are subjеct to arbitration under a valid arbitration provision in a contract, other claims in the same action cannot be submitted to arbitration if the individual or entity to whom the claims pertain was not a party to that contract. Under these circumstances, only those claims which arose from the contract containing the provision can be submitted to arbitration, while the remaining claims must be tried by the cоurt.” McCourt Constr. Co. v. J.T.O., Inc. (Sept. 20, 1996), Portage App. No. 96-P-0036, unreported, at 5-6.
See, also,
Kline v. Oak Ridge Builders, Inc.
(1995),
Altercare has cited cases in support of its position that arbitration agreements must be enforced even when some of the parties to the disрute are not parties to the agreement. However, in those cases, there is a critical factual distinction. In those cases, the plaintiff in the suit was a party to the contract with the arbitration agreement, but the plaintiffs suit included defendants who were not parties to the contract containing the arbitration clause. The claims against the parties outside the contract arose оut of that contract. In those cases, the plaintiff was held to the terms of its arbitration agreement, and proceedings against parties outside the agreement were stayed pending arbitration. See
Krafcik v. USA Energy Consultants, Inc.
(1995),
Appellant’s assignment of error is without merit. The judgment of the trial court is affirmed.
Judgment affirmed.