14 Ark. 502 | Ark. | 1854
delivered the opinion of the. Court.
This is an action of trespass on the case, against the appellant’s intestate, for damages to the cotton and corn crops of the appellee, whilst in his employ, as his overseer.
Amongother evidence the plaintiffbelow, having proved the signature of Dick & Hill to be genuine, introduced theff letter, stai ting, “ There were 178 bales of cotton, shipped us per So. Western, in bad order, a good deal of it was delivered in bulk and had to be rebaled, 28 bales were picked, the expense of which was $64 87, 23 bales were remade, the charge for ■ which was-$112. Three bales were lost in this operation, and there was-loss in weight on the picked bales, &c.” To which evidence the defendant below objected, but the court overruled the objection and permitted it to go to the jury. The jury brought in a verdict for'the plaintiff for $797 43.
Now if the other evidence, exclusive of this, were sufficient, upon which this verdict might well be sustained, although the court below manifestly erred in permitting this letter to be read as evidence to the jury, yet for this alone the verdict ought not to be disturbed. But aside from this letter, there is no evidence upon which so large an amount of damages, as contained in this-verdict, could be based or sustained: The jury, therefore, must have depended in a great measure upon this evidence in rendering this verdict. Dick & Hill were competent witnesses. Their evidence, if desired by the plaintiff below, ought to have been obtained legally, affording the defendant an opportunity to cross examine them.
As to the other error assigned in the record, we think the plaintiff having fixed the commencement of the term of service of the overseer by his declaration to the 1st day of January, A. D. 1843, and alleged “that he entered on the duties of hi.s said employment as overseer” on that day, is bound by that period, and cannot prove any injury he sustained anterior to that time. For the reason, that this action would be no bar to an action for injury sustained during a term of service anterior to this; because it could not judicially appear that any damages had been recovered for any such anterior term of service; and the declaration itself specifying the commencement of the term of service, would repel any presumption to the contrary.
It is by no means true that the specification of time is, in all cases, immaterial to be proved as laid in the declaration. Where-ever time i's material, not only in matters of contract, but in matters of tort, the plaintiff is strictly bound by that time. Now in trespass, with an allegation of a continuando or diversis diebus, if the plaintiff insists upon proving repeated acts of trespass, he will not be allowed to give evidence thereof, unless committed within the time specified.” 1 Ch. Pl. 3 Ed. 258. Eastman vs. Bodfish, 1 Story’s R. 528.
The court therefore erred in permitting the plaintiff to give evidence of injury sustained prior to the first day of January, A. D. 1843, and for these errors the case must be reversed.