OPINION
Overall Roofing & Construction Inc., appeals the judgment of the United States Claims Court dismissing its complaint without prejudice for lack of jurisdiction.
Background
Overall was awarded a roof repair contract at the Naval Air Station, Key West, Florida, in September of 1987, but as work proceeded the government became dissatisfied with the structural integrity of several roofs and demanded their removal and reconstruction. Overall refused and the contracting officer terminated the contract for default by a final decision on October 25, 1988. The final decision did not make any demand for money, but it reserved all rights and remedies provided by law or under the contract, including the right to assess any increased costs associated with securing completion of the work covered by the defaulted contract.
Overall filed a complaint in the Claims Court seeking review of the termination for default. The court dismissed the complaint without prejudice because it had no jurisdiction to consider the propriety of the default termination until one of the parties made a specific claim for monetary relief.
Discussion
The issue is whether the Claims Court has jurisdiction over a case contesting only the propriety of a termination for default and presenting no claim for money; in other words, one asking only for a declaratory judgment that the termination
*688
was wrongful.
1
The Claims Court, of course, has jurisdiction only where and to the extent that the government has waived its sovereign immunity, and any waiver of sovereign immunity “cannot be implied but must be unequivocally expressed.”
United States v. King,
King
held that the Declaratory Judgment Act, 28 U.S.C. § 2201,
2
did not permit the old Court of Claims to enter declaratory judgments because it did not contain an express grant of such power to that court.
Overall argues that legislative changes since
King
have so altered the jurisdictional landscape that the Declaratory Judgment Act now applies to the Claims Court. The court may therefore consider suits challenging terminations for default without any associated claim for money damages. It suggests that the Contract Disputes Act of 1978, Pub.L. No. 95-563, 92 Stat. 2383, and the Federal Courts Improvement Act of 1982, Pub.L. No. 97-164, § 133(a), 96 Stat. 25, 39, together with our opinion in
Malone v. United States,
Taking the most obvious first, the Declaratory Judgment Act by its own terms gives only “courts of the United States” declaratory judgment power. 28 U.S.C. § 2201 (1988). A “court of the United States” is a court whose judges “are entitled to hold office during good behavior,” id. § 451; judges of the Claims Court are appointed for terms of fifteen years, id. § 172(a). We think it would take a pointed and specific legislative enactment to fit the Claims Court into sections 451 and 2201.
See Essex Electro Eng’rs v. United States,
Overall contends, though, that two provisions of the Contract Disputes Act expressly grant jurisdiction to the Claims Court. One added a sentence to the Claims Court’s
*689
primary jurisdictional statute, the Tucker Act, which gave the Claims Court “jurisdiction to render judgment upon any
claim
by or against, or dispute with, a contractor arising under section 10(a)(1) of the Contract Disputes Act of 1978.” 28 U.S.C. § 1491(a)(2) (1988) (as amended by Federal Courts Improvement Act § 133(a),
To construe “claim” as contemplating a naked appeal from a termination for default would also render section 1491(a)(3) superfluous. This proviso added by section 133(a) of the Federal Courts Improvement Act,
3
Overall also relies on section 609(a)(1) of the Contract Disputes Act as proof Congress has waived sovereign immunity for cases like the one here. That section states that “a contractor may bring an action directly on the
claim
in the United States Claims Court, notwithstanding any contract provision, regulation, or rule of law to the contrary.” 41 U.S.C. § 609(a)(1) (1988) (emphasis added). Because
Malone
stated that “[cjaselaw supports the proposition that a government decision to terminate a contractor for default is a government claim,”
As we explained in
Dewey Elecs. Corp. v. United States,
The policies underlying the outcome in
Malone
also weigh against Overall’s position. Whereas the boards historically addressed challenges to default terminations, the Claims Court was prohibited from issuing declaratory judgments. Indeed, after
King
the Court of Claims refused to hear Wunderlich Act appeals of board decisions that did not include money damages.
E.g., Palmetto Enters., Inc. v. United States,
Congress considered giving the Claims Court broad declaratory judgment authority in 1978,
see, e.g.,
124 Cong.Rec. 36267 (1978) (statement of Sen. Byrd that Section 14(k) of S. 3178, which would have given the Court of Claims Declaratory Judgment Act jurisdiction, was deleted prior to passage of the Contract Disputes Act), and again in 1981,
see, e.g.,
H.R.Rep. No. 312, 97th Cong., 1st Sess. 43 (1981) (whether the Federal Courts Improvement Act’s grant of equitable power to the Claims Court in pre-award contract controversies should be even broader “will have to wait for a later date”), but decided not to because it would hamper the government’s administration of contracts and the efficiency of the process for redressing claims against the government in the Claims Court.
See Grimberg,
Conclusion
Accordingly, the judgment of the Claims Court is affirmed.
AFFIRMED.
Notes
. Overall framed the issue as follows: “This appeal involves purely a question of law, i.e., does the United States Claims Court have jurisdiction to rule on the propriety of a government termination for default prior to either: 1) the contractor filing with the contracting officer a claim for specific monetary damages and the issuance of a contracting officer’s final decision on that claim or, 2) the contracting officer issuing a claim on behalf of the government for a specific, liquidated amount.”
. Section 2201(a), the current version of the Act, states in relevant part: “In a case of actual controversy within its jurisdiction, ... any court of the United States, upon the filing of an appropriate pleading, may declare the rights and other legal relations of any interested party seeking such declaration, whether or not further relief is or could be sought. Any such declaration shall have the force and effect of a final judgment or decree and shall be reviewable as such.” 28 U.S.C. § 2201(a) (1988).
. 28 U.S.C. § 1491(a)(3) (1988) states: “To afford complete relief on any contract claim brought before the contract is awarded, the court shall have exclusive jurisdiction to grant declaratory judgments and such equitable and extraordinary relief as it deems proper, including but not limited to injunctive relief. In exercising this jurisdiction, the court shall give due regard to the interests of national defense and national security.”
