214 Mich. 346 | Mich. | 1921
In 1887 plaintiff’s predecessor in title was the owner of the west one-third and defendants’ predecessor in title the owner of the east two-thirds of lot 2, block 69, of the city of Muskegon. The lot is located on Western avenue in the business section of the city. On May 19, 1887, the then owners of the lot being desirous “jointly to erect a three-story brick block or building on their said premises” entered into a written contract of some length to which was attached a schedule of specifications also of considerable length.
Plaintiff’s Appeal. Plaintiff appeals from that portion of the decree which denies partition of the lands upon which the stairway rests. The trial judge was of opinion that defendants had acquired prescriptive rights to the use of the stairway by adverse possession and that the case was controlled by First National Bank v. Vanden Brooks, 204 Mich. 164. An examination of the contract and specifications is quite persuasive that the parties contemplated the erection and maintenance so long as the building remained of the stairway for their common use. But if we assume (and this is the most favorable position to plaintiff that may be assumed) that the contract gave defendants no right to the use of the land for stairway purposes, we are then confronted with the undisputed fact that for over 30 years defendants have used this stairway without protest. The case cited is controlling. In the recent case of St. Cecelia Society v. Universal Car & Service Co., 213 Mich. 569, where the
“The elements necessary to give rise to a prescriptive right are the same as those of title by adverse possession, with the exception that it does not have to be exclusive.”
The instant case, so far as this question is involved, is so like the case of First National Bank v. Vanden Brooks, supra, that we do not deem it necessary to discuss it further than to say that defendants may not be deprived of this easement under color of partition proceedings.
Defendants’ Appeal. Defendants appeal from that portion of the decree which restrains them from interfering with plaintiff’s water supply and with the sewers and drains. These were expressly provided for in the contract. But defendants contend that this was but a building contract. We think it was something more than a building contract. If defendants are correct in their contention their predecessor could have cut off the water supply the day after the building was erected although plaintiff’s predecessor in title had paid one-third the cost of installing the pipes. Such a construction is too narrow;we can not follow it. The parties were then providing not only for the erection of the building but also for its future use. For over 30 years they and their successors in title have given this contract a practical construction. We think their construction a proper one; we are not inclined to disturb it.
The decree must be affirmed. In the trial court plaintiff was given but part of the relief she asked and was awarded costs. We see no occasion to disturb this award. In this court, both parties having appealed, no costs will be awarded.