Outback Steakhouse, Inc. v. Contracting Management, Inc.Outback Steakhouse, Inc. v. Contracting Management, Inc.
Ordered that the judgment is reversed, on the law and the facts, without costs or disbursements, the petition to confirm the award, as modified, is denied, the cross petition to vacate the award, as modified, is granted, and the arbitration award, as modified, is vacated.
We agree with Contracting Management, Inc., that the arbitrator exceeded his authority in modifying the original arbitration award by rendering wholly new determinations on matters not addressed in the original award, which went beyond correcting a miscalculation or mistake, correcting an award upon a matter not submitted to him without affecting the merits of the decision, or correcting a matter of form not affecting the merits of the controversy (see
Moreover, to the extent the award, as modified, “reaffirmed” provisions of the original award, those provisions also must be vacated on the ground that the arbitrator so imperfectly executed his power in making that award that a final and definite award on the subject matter submitted was not made (see