The two appeals which we have consolidated raise eminent domain questions which are unsettled in this state. If we are to reach those questions, it is necessary to bypass a procedural jungle which results from the consolidation in the trial court of three apparently representative cases from hundreds of cases filed, or to be filed, in three different counties. The two separate appeals are from two separate interlocutory orders which did not include a Rule 54(b), NDRCivP, determination that there is no just reason for delay nor an express direction for the entry of judgment. The motion to stay proceedings pending the disposition of the appeals made to the trial court was denied. This court granted a motion to stay and to consolidate the two appeals. Otter Tail has moved to dismiss one оf the appeals and, in its argument on the merits, urges us to dismiss both appeals. We heard arguments on all motions in September 1981, and have made tentative disposition thereof. We have now heard the appeals on their merits and we dismiss both appeals and remand for trials on the question of damages.
In the absence of a trial court Rule 54(b) order, the determinations, which are the subjects of the two property-owner appeals, are “subject to revision at any time” by the trial court. As the trials proceed on the issue of damages, the court will likely be confronted with opportunities to consider revision of its interlocutory determinations. It would be in the interest of judicial economy for this court to make some comments that might assist the trial court and, possibly, save the need for another appeal after final judgment is entered.
We would not encourage trial courts to make Rule 54(b) orders when there are reasons to believe that it may be discovered during trial that a revision is advisable. Unless there are extraordinary circumstances, this court should not intervene in the process of amending complaints which, under some circumstances, should be permitted even up to the entry of the final judgment. Orders relating to the amendment of pleadings and orders denying motions to dismiss an action are not appeala-ble.
Strecker v. Railson,
The property owners here argue inconsistently that the certificate from the Public Service Commission granted Otter Tail authority, under § 49-22-07, NDCC, limited to a transmission line capacity of 230 kilovolts. On the other hand, they contend that Otter Tail should be required to seek an easement for a 230/345 kilovolt transmission line because the facility planned tо be constructed will, in many respects, have the capacity to carry 345 kilovolts.
Although the Otter Tail complaints originally sought a general transmission •line easement that would have permitted future “increasе in capacity,” the complaints have now been amended to a restricted easement. Unless the complaints are again amended, increase in voltage will not be permitted by the easemеnt acquired. The judgment should so provide, and rulings on the admission of evidence should be in accordance therewith. The admissibility of opinion testimony as to how the present market value of property is affected by potential future upgrading of the line will depend upon many factors upon which we cannot speculate. The jury, of course, will be instructed that increase of voltage will not be permitted without the acquisition of additional PSC authority and additional easements from the property owners.
Reminder of some of the basic rules that govern condemnation proceedings and appeals therefrоm may be helpful:
The right of eminent domain may be exercised for “power transmission lines.” Section 32-15-02(4), NDCC;
Otter Tail
*301
Power Company v. Malme,
A complaint in eminent domain proceedings must, with accuracy and certainty, describe and include a map of the right-of-way sought аs to (1) location, (2) general route, (3) termini, and (4) legal description of each piece of land sought. Section 32-15-18 (4) and (5), NDCC;
Otter Tail Power Co. v. Von Bank,
An interlocutory order which involves the merits of an action, or some part thereоf, is separately appealable to this court. Section 28-27-02(5), NDCC;
Skoog v. City of Grand Forks,
If, during the consideration by this court of
any
appeal, it becomes apparent that there are issues in the case that have not been tried or have not been detеrmined by the trial court, and this court determines that it is necessary or desirable that such issue be first tried and determined, this court may remand the case to the trial court for disposition of the undetermined matters. Rule 35(b), NDRAppP (source: § 28-27-29, NDCC);
Center State Bank, Inc. v. State Bank. Bd.,
Although interlocutory orders which involve the merits of an action have been separately appealable since territorial days [§ 23(4), Ch. 20, Laws of Dakota Territory, 1887)], in 1927 the Legislative Assembly, in enacting Ch. 214, S.L. 1927, concluded that the appeal of any matter, other than a final judgment, should be subject to remand by this court if it determines that a final judgment is necessary or desirable. Considering the growth in the caseload cоnfronting this court, it should be obvious that a final judgment should be required, except in the most unusual and extraordinary circumstances. The 1927 enactment became a part of § 28-27-29, NDCC, and ultimately, Rule 35, NDRAppP.
In
City of Williston v. Beede,
“The court in Teigen expressed reservations on the ability to appeal the separate judgment on the necessity of taking without first completing the triаl on compensation or damages. We are confident that with the adoption of Rule 54(b) [NDRCivP], the appealability issue has become considerably more doubtful.” City of Williston v. Beede,289 N.W.2d at 237 .
That is not to say that, as a part of the appeal from the “final” judgment, a judicial review of the findings of fact and conclusions of law which support the trial court’s determination upholding the condemnor’s position on use and necessity will not be madе by this court. As in any other fact *302 issue review, we would apply Rule 52(a), NDRCivP, to determine whether or not the findings of fact on questions of use and necessity are clearly erroneous. Because § 28-27-32, NDCC, was repealed, trials de novo on fact questions are not ordinarily available.
When the statute which authorizes a utility company to exercise the power of eminent domain describes only generally the interest which can be taken as a “power transmission line” easement, it is generally construed that no greater interest in the property can be taken, over the objection of the property owner, than the particular use requires.
See e.g.,
26 Am.Jur.2d Eminent Domain § 133. Although no greater interest may be acquired than is necessary within the statutory limits, the condemnor has discretion in determining what is needed. See 29A C.J.S. Eminent Domain § 92, and
Falkner v. Northern States Power Co.,
In the case of
Minnkota Power Coop. v. Lake Shure Prop.,
There is a distinction betweеn mere unenforceable promissory statements by a con-demnor as to the intended use of the property taken and binding stipulations, reservations or limitations. See Annotation,
There are fine lines of distinction between unlawful takings for future needs and lawful takings for present needs, with authority to make reasonable improvements аs necessary in the future and consistent with the present purpose.
See
Annotation in
We conclude that a condemnor of right-of-way for a power-line easement may ordinarily elect to acquire a general easement or, by appropriate words of limitation in the complaint and in the judgment entered, restrict the easement to the transmission of specific voltage. If there is no voltage limitation elected by the condemnor in its complaint, the evidence cannot be restricted by any promissory statements by the condemnor. If there is a binding election by the condemnor to a limitation of the voltage, the evidеnce, if objected to, should be limited accordingly. Property owners’ rights will be protected by an appropriate explicit limitation in the judgment.
The appeals are dismissed. No costs are allowed on the appeals. The matter is remanded for proceedings consistent herewith.
