{¶ 1} Appellant, Orwell Natural Gas Company, Inc. (“Orwell”), challenges the confirmation of an arbitration award in favor of appellee, PCC Airfoils, L.L.C. (“PCC”). The dispute stems from a contract for the transport of natural gas and PCC’s decision to use an alternate means of transport. After a thorough review of the record, we affirm the decision of the lower court.
{¶ 2} On February 8, 2008, the two parties entered into a contract for the transport of natural gas to PCC’s Painesville, Ohio manufacturing facility. The contract took the form of a three-page document signed at the end and followed by an exhibit of ten pages of terms and conditions. In this contract, Orwell agreed to transport natural gas to PCC’s manufacturing facility located on Renaissance Parkway in Painesville (the “Renaissance facility”). Soon after entering into the agreement, PCC began negotiating with another company for an agreement covering all of PCC’s facilities in a certain geographic area. On June 20, 2008, PCC informed Orwell that it would no longer be using Orwell’s gas pipelines for the transport of natural gas.
{¶ 3} In August 2008, Orwell sought a temporary restraining order in the Lucas County Court of Common Pleas barring PCC from using other means of transport. The parties agreed to a restraining order and to submit their dispute to arbitration in Cuyahoga County, Ohio pursuant to an arbitration clause in the contract, and further agreed to continue the restraining order with PCC using Orwell’s supply lines for the transport of natural gas while the arbitration proceedings were pending.
{¶ 4} During the arbitration, PCC argued that the contract was ambiguous and that extrinsic evidence was required to properly interpret the contract. Orwell argued that the contract was an unambiguous “full requirements” integrated agreement that PCC intended to breach by receiving natural gas from another transporter.
{¶ 5} On January 16, 2009, Orwell sought to have the arbitrator’s decision vacated in the Cuyahoga County Common Pleas Court, and PCC petitioned the court to have the arbitrator’s award confirmed. On October 6, 2009, the trial court granted PCC’s motion confirming the arbitrator’s decision, finding that “[t]he arbitrators did not depart from the essence of the contract by conflicting with the express terms of the agreement nor did the decision lack rational support as derived from the terms of the contract.”
{¶ 6} Orwell now appeals the denial of their motion to vacate, modify, or correct the arbitration award, claiming that the “[t]rial court erred when it granted appellee’s motion to confirm [the] arbitration award and denied appellant’s motion to vacate, modify or correct [the] arbitration award.”
Law and Analysis
Review of an Arbitral Determination
{¶ 7} When faced with a motion to vacate an arbitration award, a court is limited in its review. Goodyear Tire & Rubber Co. v. Local Union No. 200 (1975),
{¶ 8} Appellate review of an arbitral proceeding is confined to an evaluation of the order issued by the trial court pursuant to R.C. 2711.10. The substantive merits of the original arbitration award are not reviewable on appeal absent evidence of material mistake or extensive impropriety. Lynch v. Halcomb (1984),
{¶ 10} Under R.C. 2711.10(D), an error of fact or law by an arbitrator does not provide a basis for vacating an arbitration award. Goodyear,
{¶ 11} The fact that a trial court might arrive at a different conclusion from the arbitrator is also immaterial. Motor Wheel Corp. v. Goodyear Tire & Rubber Co. (1994),
Discretion of an Arbitrator
{¶ 12} Orwell takes issue with the decision of the arbitrator to allow extrinsic evidence to interpret the contract, contrary to the parol evidence rule. Normally, “ ‘[w]hen two parties have made a contract and have expressed it in a writing to which they have both assented as the complete and accurate integration of that contract, evidence, whether parol or otherwise, of antecedent understandings and negotiations will not be admitted for the purpose of varying or contradicting the writing.’ ” Ed Schory & Sons, Inc. v. Soc. Natl. Bank (1996),
{¶ 13} Section 1.1 of Exhibit A of the instant contract states, “Customer shall arrange with suppliers of Customer’s selection to have Gas meeting the full requirements for its manufacturing facilities located in Lake County, Ohio served through the Delivery Point * * (Emphasis added.) The first page of the agreement contains a provision that states, “Customer has agreed to trans
{¶ 14} Orwell argues that the first few pages of the 13-page contract are a preamble, a perfunctory statement that simply introduces the parties and subject matter. However, these pages are more than that. They set forth a few material terms, such as location of delivery, and provide the only section that binds PCC to the later terms and conditions set forth in Exhibit A. According to the extrinsic evidence submitted by the parties, ambiguities arose in the contract as a result of changes in the agreement, which initially was to transport natural gas to two of PCC’s facilities in Lake County, Ohio. PCC also requested that the “full requirements” language be removed from the first page of the agreement.
{¶ 15} Contrary to Orwell’s argument, the arbitrator did not refuse to apply the parol evidence rule, but found that an exception to this rule applied. The arbitrator found that the contract was ambiguous, and extrinsic evidence should be allowed to explain the ambiguity. “When a provision in a collective bargaining agreement is subject to more than one reasonable interpretation and the parties to the contract have agreed to submit their contract interpretation disputes to final and binding arbitration, the arbitrator’s interpretation of the contract, and not the interpretation of a reviewing court, governs the rights of the parties.” Hillsboro v. Fraternal Order of Police, Ohio Labor Council, Inc. (1990),
{¶ 16} The extrinsic evidence demonstrated that PCC asked Orwell to remove the exclusivity language from the first three pages of the agreement. The agreement also changed from servicing all of PCC’s facilities in Lake County to supplying natural gas only to the Renaissance facility. The arbitrator’s interpretation of the contract is not so far outside of the bounds of logic or law that this court could determine that it “cannot be rationally derived from the terms of the agreement.” Ohio Office of Collective Bargaining v. Ohio Civ. Serv. Emp. Assn., Local 11, AFSCME, AFL-CIO (1991),
{¶ 17} While this court may reach a different conclusion regarding whether the contract was ambiguous as to the exclusivity of the agreement, that alone is not grounds for vacating the arbitral determination because the decision of the arbitrator is not unreasonable, unconscionable, or arbitrary. Motor Wheel Corp.,
{¶ 18} Orwell cites Middletown v. Internatl. Assn. of Firefighters, Local No. 336 (June 30, 1997), Butler App. No. CA96-12-0259,
{¶ 19} The arbitrator’s decision draws its essence from the agreement of the parties. Unless the arbitrator’s decision flies in the face of an unambiguous contractual provision, as it did in Ohio Office, this court is not free to substitute its determination for that of the arbitrator. See Hillsboro,
Conclusion
{¶ 20} It is conceivable that the provision in question is ambiguous. The arbitrator specifically engaged in an analysis of this issue and ruled that the contract was ambiguous. This court should not conduct its own de novo analysis of the contract. To do so would be to give no deference to the arbitrator’s determination and contravene important policy considerations preserving the utility of arbitration.
Judgment affirmed.
Notes
. A requirements contract is "[a] contract in which a buyer promises to buy and a seller to supply all the goods or services that a buyer needs during a specified period. * * * A requirements contract assures the buyer of a source for the period of the contract.” Black’s Law Dictionary (8th Ed.2004). This is also referred to as the exclusivity of the contract in this opinion.
