Ortiz v. UhlOrtiz v. Uhl
Defendants appeal from a judgment pursuant to a jury verdict in favor of plaintiff in the amount of $129,000.07 and from an order which denied their motion to •set aside the verdict and dismiss the complaint.
Plaintiff was injured while employed by Merritt, Chapman and Scott (Merritt), general contractor of the Lewiston power plant. The defendants are the New York State Power Authority (Authority), the owner of the project, and Uhl, Hall and
The Lewiston power plant work area extended approximately 1,700 feet along the Niagara River and approximately 575 feet from the river to the top of the gorge. All construction materials were lowered into position by means of three cranes which moved on rails installed over the work area. Plaintiff was operating a jack hammer at the time he was struck by a bottle of oxygen which fell from one of the crane’s rigging. It was undisputed that the Authority did not furnish Merritt with any tools, equipment nr employees, and that it would not make any determination as to the methods by which the contractor should perform the required work. The Authority did not reserve to itself any portion of the contract of the power plant. It was also undisputed that operation of the cranes was within the exclusive control of the general contractor.
It was necessary for Merritt to work over the entire surface of the gorge and there was no practical way of providing overhead protection. To do so would have made it impossible to lower materials into place. It appears clear, however, that the procedure which the contractor utilized in rigging bottles of gas was hazardous and not in accordance with recognized safety practice.
Uhl, Hall and Rich made the progress engineering .study and prepared the specifications for materials and equipment. They inspected all materials and equipment as necessary and administered the construction program which included the co-ordination, scheduling, layout, supervision and inspection of various contracts. They inspected everything to make sure it was built according to the plans and specifications and had a staff of .safety personnel on the job site.
The court charged the jury that plaintiff could not recover from either defendant if Merritt’s negligence was the sole cause of injury to plaintiff. The court further charged that neither defendant was responsible for the ‘ ‘ manner, method and means ” used by Merritt in the performance of its work, and that neither defendant had the duty to make safe the equipment used by the contractors. The jury was further instructed that ‘1 there is no evidence in this case that either of the defendants ordered, directed or determined the manner, method or means by which Merritt, Chapman & Scott was moving an oxygen tank in the work area at the time of the accident.” The jury was instructed, however, that liability
It is well established that the owner’s duty is to furnish a safe place to work only insofar as its own plant facilities are concerned (Persichilli v. Triborough Bridge & Tunnel Auth., 16 N Y 2d 136, 145; Zucchelli v. City Constr. Co., 4 N Y 2d 52, 55, 56; Iacono v. Frank & Frank Contr. Co.,
It is equally well established that the retention of the power of general supervision over the work does not alter this rule of nonliability (Grant v. Rochester Gas & Elec. Corp., 20 A D 2d 48, supra; see Zucchelli v. City Constr. Co., 4 N Y 2d 52, supra; 2B Warren’s Negligence, ch. 34, Contractors, § 5.03, subd. [7]).
Caspersen v. La Sala Bros. (
The undisputed facts in the instant case reveal that the accident arose out of the improper use of the contractor’s own facilities. The cranes were constructed, operated and maintained by the contractor as its own plant facilities and the accident occurred during the contractor’s performance under the contract. The Authority did not maintain control of the crane apparatus and the negligence of the contractor’s employees is not attributable to the owner. The “place” the owner must keep safe does not include the contractor’s own equipment or the very work under progress. Section 241 of the Labor Law has no application to the determination of defendants ’ liability. That statute deals ‘ ‘ with the duty of safeguarding .openings in floors and shaftways and the planking over of open spaces, a duty similar to that of protecting common walks and ways which is ordinarily imposed upon the owner and general contractor.” (Conte v. Large Scale Development Corp., 10 N Y 2d 20, 28). Section 3-8 of Industrial 'Code No. 23 (now 12 NYCBB 23.3 [h]) which plaintiff contends should have been charged appears to have been promulgated by the Board of Standards and Appeals of the New York State Department of Labor pursuant to section 200 of the Labor Law and not section 241. In any event its requirements could not be followed in the construction of the
It is clear that it was not feasible to provide overhead protection without rendering performance of the contract impossible. The owner is required to provide a safe place to work only to the extent that such is practicable within the context of the ongoing project under construction (Caspersen v. La Sala Bros.,
The accident occurred because of the improper method used by the contractor’s employees to secure the bottle of gas to the crane and its negligence in that respect may not properly be attributable to the owner or engineers, notwithstanding that the owner’s general supervisory agents may have had actual notice of the improper method (Ehrlich v. C. B. S. Columbia, 9 A D 2d 943, affd. 8 N Y 2d 1113).
Since there is no basis for finding liability on the theory that defendants failed to provide a safe place to work, the judgment and the order denying the motion to set aside the verdict should be reversed and the complaint dismissed.
Goldman, P. J., Gabrielli, Motile and Cardamone, JJ., concur.
Judgment and order unanimously reversed, on the law and facts, without costs and complaint dismissed.