Cesar Ortega et al., Appellants, v City of New York et al., Respondents.
Supreme Court, Appellate Division, First Department, New York
March 29, 2012
940 N.Y.S.2d 636 | 95 A.D.3d 125
Borchert, Genovesi, LaSpina & Landicino, P.C., Whitestone (Gregory M. LaSpina and Gary E. Rosenberg of counsel), for appellants.
Lester Schwab Katz & Dwyer, LLP, New York City (Harry Steinberg of counsel), for respondents.
OPINION OF THE COURT
Acosta, J.
At issue in this case is whether a plaintiff seeking summary judgment on his
Background
Plaintiff Cesar Ortega, an employee of a subcontractor on the Second Avenue Subway Tunnel Construction Project, was injured while connecting pipes that were to be used to pour concrete underground using the “Tremie Concrete” method. In order to perform this work, plaintiff stood on a work platform located eight feet above the ground and contained within a metal cage known as a tremie rack. This was a rectangular structure, approximately 12 feet high. In addition to housing a work platform, the tremie rack contained vertical slots in which heavy tremie pipes were held. These pipes had a collar at one end and
Ronald Knott, site safety director employed by defendant Skanska, testified at his deposition that upon his investigation of the accident, he concluded that the accident occurred for several reasons, including the stability of the underside of the tremie rack, the weight distribution of the pipes and the fact that the rack was taller than it was wide. Plaintiffs relied on this testimony in arguing that the tremie rack, which we view as a scaffold, albeit one designed specifically for the task at hand, was not secured to the ground. Specifically, citing Ross v Curtis-Palmer Hydro-Elec. Co. (81 NY2d 494, 501 [1993] [”
In denying plaintiffs’ motion for partial summary judgment, Supreme Court found that issues of fact remained, including whether the accident was foreseeable and whether defendant failed to assure proper placement of the tremie rack (2011 NY Slip Op 30740[U] [2011]). The court noted that “foreseeability may be inherent in the work in which a plaintiff may be engaged,” and that the failure of the furnished protective device to prevent a foreseeable external force from causing plaintiff to fall from an elevated work station entitled plaintiff to judgment as a matter of law (id. at *7). The court, however, found that issues of fact existed due to plaintiffs’ failure “to provide the testimony of an expert which would elucidate, among other issues, what standards govern the interplay of drilling rigs and tremie racks, and what measures were foreseeably necessary to ensure the safety of workers performing in the circumstances” (id.).
On appeal, plaintiffs argue that they established a violation of
Analysis
In reversing, we hold that there is no requirement that plaintiff offer expert testimony on the foreseeability of the accident to prevail on a
A defendant‘s failure to provide workers with adequate protection from reasonably preventable, gravity-related accidents will result in liability (Wilinski v 334 E. 92nd Hous. Dev. Fund Corp., 18 NY3d 1, 7 [2011]; Runner v New York Stock Exch., Inc., 13 NY3d 599, 603 [2009] [“the single decisive question is whether plaintiffs injuries were the direct consequence of a failure to provide adequate protection against a risk arising from a physically significant elevation differential“]). Indeed, the question of circumstantial reasonableness is irrelevant when safety devices are required pursuant to
Thus, contrary to the IAS court, expert testimony on foreseeability was unnecessary for plaintiffs to prevail on the section 240 (1) claim. To be sure, this Court has created a limited exception with respect to foreseeability where the accident involves the collapse of a permanent structure (see Jones v 414 Equities LLC, 57 AD3d 65 [2008] [demolition worker fell when a permanent second story floor collapsed]; Espinosa v Azure Holdings II, LP, 58 AD3d 287 [2008] [plaintiff fell when the sidewalk on which he was standing collapsed due to the failure of the cellar vault below it]; Vasquez v Urbahn Assoc. Inc., 79 AD3d 493 [2010] [plaintiff fell when permanent staircase collapsed during demolition of a building]). But, that is not the case here.
Notwithstanding the clear holdings in cases such as Wilinski, Gordon and Runner, defendants in the present case are seeking to expand the limited foreseeability requirement beyond the confines of permanent structures such as those Jones, Espinosa and Vasquez dealt with (see Vasquez, 79 AD3d at 498 [where I noted in dissent that by reading a foreseeability requirement into the statute, contractors would be encouraged “to take a head-in-the-sand approach to their statutory obligations,” which is exactly what defendants are doing in the present case]).1 We thus decline to extend the foreseeability requirement to anything other than permanent structures that are not safety
Rather, in the present case, a device precisely of the sort enumerated by the statute was not “placed and operated” as to provide adequate protection to plaintiff (Runner, 13 NY3d at 603). The tremie rack, which was taller than it was wide, was not in a fixed position, but rather, rested upon wooden planks atop an uneven, gravel surface. Plaintiffs made out a prima facie case in that they established with evidence in admissible form that plaintiff Cesar Ortega was working at a construction site and was injured as the result of the gravity-related hazard created by the elevation differential of the tremie rack in which plaintiff was working, and that the rack, which should have been secured to the ground, but was not, failed to protect him. Indeed, here, unlike Wilinski, where the plaintiff failed to demonstrate that protective devices could have prevented the accident, plaintiffs submitted testimony indicating that the accident could have been prevented had the tremie rack been secured to the ground (see also Howell v Bethune W. Assoc., LLC, 33 Misc 3d 1215[A], 2011 NY Slip Op 51939[U] [Sup Ct, NY County 2011]). Accordingly, they were entitled to summary judgment on the
In any event, if foreseeability were a required element, plaintiffs have nevertheless demonstrated their entitlement to partial summary judgment as to liability on the
Accordingly, the order of the Supreme Court, New York County (Michael D. Stallman, J.), entered March 30, 2011, which denied plaintiffs’ motion for partial summary judgment under
Sweeny, J. (concurring). Plaintiff Cesar Ortega, an employee of a subcontractor on the Second Avenue Subway Tunnel Construction Project, was injured while he was connecting pipes which were to be used in order to pour concrete underground using the “Tremie Concrete” method. In order to perform this work, plaintiff stood on a work platform located eight feet above the ground and contained within a metal cage, also referred to as a tremie rack.
The tremie rack was a considerable, rectangular structure, with its height greater than its width and was estimated to stand as tall as 12 feet high. In addition to housing a work platform, the tremie rack contained vertical slots in which heavy tremie pipes were held, which pipes had a collar at one end and were kept in place by square shaped holders, also referred to as “keepers.” The rack was resting on unsecured wooden planking which was meant to level the gravel surface below, and the tremie pipes, which were estimated to be 10 feet high and weigh 300 pounds each, were all located on one side of the rack.
Plaintiff‘s accident occurred when, as he was standing on the platform, the collar of a tremie pipe which was being hoisted by a multi-ton rig got caught on a keeper, causing the tremie rack to tip over onto its side and eject plaintiff.
Since the work platform, which functioned as a safety device, failed to protect plaintiff from the foreseeable risk of falling from an elevation, judgment as a matter of law under
Accordingly, I concur in the result reached by the majority. In so doing, there is no need to address the foreseeability issue as the majority does. This is an issue which, in any event, has been the subject of extensive analysis in this Court (see Vasquez v Urbahn Assoc. Inc., 79 AD3d 493 [2010]) and does not need further elucidation here.
Freedman and Manzanet-Daniels, JJ., concur with Acosta, J.; Andrias, J.P., and Sweeny, J., concur in a separate opinion by Sweeny J.
Order, Supreme Court, New York County, entered March 30, 2011, reversed, on the law, without costs, and the motion for partial summary judgment under
