125 N.Y.S. 664 | N.Y. App. Div. | 1910
This action is brought to recover the stipulated sum of $50,000 foi work performed by the plaintiff’s assignors, the Metropolitan and People’s Surety Companies, in the performance of a contract entered into between them and the defendant, the city of New York. There is no question but that the work was performed in exact accordance with the contract. Although it was made and all the preliminary steps were taken, pursuant to the advice and direction of the corporation counsel, the city is now defending on the ground of want of power to make the contract.
To understand the question presented it is necessary to state in chronological order the different 'transactions involved. On tlie 12th of December, 1905, the defendant, through the commissioner of public charities, entered into a contract with the Church Construction Company for the erection of the new municipal lodging
The city contends (1) that the resolution of March twenty-fifth only authorized the commissioner to execute a contract with the Church Construction Company, and that he, therefore, had no power to enter into a contract with the sureties of that company ; (2) that, having declared the contract abandoned, the contractor and its sureties were in default and the commissioner was precluded by section 419 of the charter from entering into a contract with them < (3) that the contract was void because, when it was executed by the plaintiff’s assignors, there was no appropriation out of which the cost of the work could have been paid ; and (4) that the contract was void because, at the time of the commencement of the work the comptroller had not indorsed thereon the certificate required by section 149 of the charter.
It was obviously the purpose of section 419 of the charter (Laws of 1901, chap. 466, as amd. by Laws of 1906, chap. 598)
It is too late now for the city, after receiving the benefit of a full compliance with its demands, to change its position and assert not only that the commissioner was wrong in making the demand, but tliat he did not even have the power to allow the sureties either to finish the original contract or to perform the supplemental contract. That conclusion disposes of the first and second points of the city. The notice of the commissioner declaring the original contract abandoned must be read in connection with the subsequent notice to the sureties requiring them to perform both contracts. Having procured the sureties to step into the shoes of their principal with respect to both, the city is in no position to assert that they were in default, and that the commissioner was precluded by section 419 of the charter from even allowing them to do that, even if otherwise he would have been so precluded, which we are far from deciding.
The last two points may likewise be disposed of together for they 'relate to the same thing, namely, the existence of an unapplied and unexpended appropriation, and the certificate of the comptroller to that effect. All of the requirements of the charter under that head were complied with long before the work was completed, and indeed before the fully executed contract was delivered to the plaintiff’s assignors. They executed the contract on the twenty-seventh day of June, and in good faith began the work almost immediately, without waiting for the city officials to perform the ministerial acts necessary to give validity to it. Fortunately for them, the present attitude of the city was not conceived until after all of those acts had been performed. Although the work on the original contract could hot proceed until additional work, not contemplated by it, was done, the
The judgment should be reversed and a new trial granted, with costs to appellant to abide the event.
Ingraham, P. J., Laughlin, Clarke and Scott, JJ., concurred.
Judgment reversed and new trial ordered, with costs to appellant to abide event.
Since amd. by Laws of 1910, chap. 545.— [Rep.
Since amd. by Laws of 1910, chap. 554.— [Rep.