Lead Opinion
This is a "termite case” in which Stevens, a homeowner, (hereinafter, "Stevens”) received a jury verdict against Orkin Exterminating Co. Inc. (hereinafter, "Orkin”) and Orkin appeals the overruling of its motions for directed verdict and judgment n. o. v.
The appeal presents the knotty question, not answerable in any fashion save that of case by case analysis, whether as between two private contracting parties a specific act or omission in the nature of a breach of contract may also constitute a tort.
The pleadings and trial evidence showed that on April 3, 1969, Stevens contracted with Orkin for control of subterranean termites in his home, and paid $259 for initial extermination services and the issuance of a "Guaranty.” The contract was said to be extendable by the annual payment of $25 which would entitle Stevens to a re-inspection each December. Subsequent to Orkin’s initial treatment and during the term of the Guaranty, Stevens’ home became severely infested with subterranean termites appearing to originate from untreated portions of the house. From 1969 through 1972 termites swarmed at various times; Stevens made numerous telephone requests to Orkin’s office in Athens, Georgia, for retreatment; and all requested retreatments were given.
Stevens then brought a negligence suit against Orkin to recover for new termite damage to portions of the house not involved in the initial termite infestation. At trial, Orkin presented no evidence. Throughout, Stevens’ suit was declared to be in tort which was wholly consistent with his pleadings (and with his stance on this appeal.) Orkin moved for directed verdict on the ground that no breach was shown, no damages were recoverable under the contract, and notice to Orkin before suit was not given as required by the contract. The trial judge overruled those motions; the case went to the jury on charges of negligence in carrying out the terms of the contract; the jury gave a verdict for plaintiff; Orkin moved on the same grounds for judgment n. o. v.; this motion was denied and the appeal followed.
Turning to the provisions of the operative contract between the parties, the guaranty to be issued later to Stevens was designated on the front of his contract, as the "Lifetime Control” type, which was explained (but not set forth) on the back of the contract as
The actual guaranty document subsequently issued to Stevens provided as follows:
"Your Guarantee
In consideration of sums received and to be received for providing treatment for the above-stated wood destroying insect at the premises specified above, Orkin guarantees, subject to the Terms and Conditions appearing on the reverse side of this Guarantee and on the Service Order bearing the above-stated number:
To inspect the premises treated, as described in said Service Order.
To apply any necessary additional treatment to such premises, At No Extra Cost, if infestation of the above wood destroying insect is found in the premises during the period that this Guaranty remains in force. This Guarantee is limited to re-treatment only and in no way, implied or otherwise, covers damages and repairs to the structure or contents. ” (Emphasis supplied.)
The "General Terms and Conditions” appearing on the back of the contract and on the back of the guaranty included these paragraphs:
"5. Any claim for breach of any Guaranty shall be made forthwith in writing to said Orkin Exterminating Inc., 2170 Piedmont Road, Atlanta, Georgia, 30324.
6. No suit shall lie hereunder unless the provisions of Paragraph 5 have been complied with and unless brought within one (1) year after the making of said written demand.”
Though Stevens introduced the contract and guaranty into evidence and addresses argument here to the inapplicability or invalidity of the provisions therein concerning the limitation of damages and the requirement of notice before suit, nonetheless he emphasizes that this is a tort suit only. We will, therefore,
It is axiomatic that a single act or course of conduct may constitute not only a breach of contract but an independent tort as well, if in addition to violating a contract obligation it also violates a duty owed to plaintiff independent of contract to avoid harming him. See, e.g., E. & M. Construction Co. v. Bob,
However, not all breaches of contract are also independent torts: '\ . . where defendant’s negligence ends merely in nonperformance of the contract and where defendant is not under any recognized duty to act apart from contract, the courts generally still see no duty to act affirmatively except the duty based on — and limited by — defendant’s consent.” 2 Harper and James, Torts, p. 1050, § 18.6. In those circumstances, an action in tort may not be maintained for what is a mere breach through non-action or through ineffective performance (which is the same thing) of a contract duty — the duty must arise independent of contract to constitute a tort. e. g., Louisville & Nashville R. Co. v. Spinks,
This must be termed nonfeasance for yet another reason as well. As will be discussed below in relation to proof of negligence, the record is devoid of evidence of wrongdoing by Orkin in the sense that Orkin is shown to have done something the reasonable pest control operator would not have done, or to have failed to do that which the reasonable pest control operator would have done. 57 AmJur2d 419, Negligence, § 68. Nothing is shown but the ultimate nonsuccess of the termite treatments, and no theory
Another independently adequate reason for which plaintiff cannot succeed in his claim here is that he has brought a negligence suit and has completely failed to prove negligence. Orkin put on no evidence at trial, and plaintiff, who had the burden, introduced absolutely no evidence of the kind of treatment afforded or not afforded, the chemicals used or not used, the style of application, Orkin’s proper standard of care, and its failure to meet that standard in any particular. The only evidence was that on the first visit to the house Orkin dug a trench or holes around the house and on subsequent visits the treatment was performed indoors. From a proof-of-negligence standpoint this showing is meaningless. Therefore, this record poses a completely unanswered mystery as to why the treatments failed. Nobody knows or guesses, on the record. No viable inference is raised that the treatments failed because of Orkin’s negligence, and, because res ipsa loquitur is not applicable to this action,
Negligence is not to be presumed, but is a matter for affirmative proof. Glynn Plymouth, Inc. v. Davis,
Though Stevens urges that this is strictly a tort suit, and we treat it as such, his brief on appeal taken as a whole is open to another implied construction, and therefore we additionally consider whether he has proved a case for damages for negligent breach of contract. On this analysis he fares no better, however, for the reason that the same contract which raises Orkin’s duty to him limits that duty to retreatment, and Stevens has not contended that Orkin failed to retreat the premises when requested. The description on the original contract of the type guaranty to be issued, and the guaranty itself, make clear that Orkin in no way assumed responsibility under that type guaranty as opposed to other Orkin guaranties for any structural damage caused by termites if its treatments should be unsuccessful. Because Orkin as a private citizen owed plaintiff no duty except that assumed by the contract, there is no impediment to its limiting its contract liability by such a provision, and such limitations are usually valid. 5 Corbin 385, § 1068, supra. Absent a limiting statute or controlling public policy, parties may contract with one another on whatever terms they wish (Anken Const. Co. v. Artistic Ornamental Iron Co.,
Stevens argues that the limitation on liability is void under the reasoning of Screven Oil Co. v. Jarrell,
To Stevens’ insistence that he should not have been allowed to contract away some of his remedies, we must answer that in Georgia there is no generally applicable rule of law forbidding one contracting party from waiving all recourse in the event of breach by the other. See, Monroe v. Martin,
It is unnecessary to discuss the 1970 amendment to Code § 20-504 otherwise than to note that it is entirely inapplicable to this contract which was executed April 3,1969. There is no legislative intent apparent in the statute that it be applied retroactively, and therefore we will not so apply it (see Robert & Co. Assoc. v. Pinkerton & Laws Co.,
An additional bar to Stevens’ right to prevail under the contract is his admitted failure to comply with the notice provisions of paragraphs 5 and 6. Such provisions are entirely valid, Code § 3-106, and Stevens does not even contend that Orkin waived its right to notice, or that his telephoned communications to the Orkin office in Athens satisfied the requirement of a written notice to the office in Atlanta. The failure to give notice as required or to show waiver by Orkin is an independent bar to the maintenance of a successful cause of action on the contract. Cf. Porter-Lite Corp. v. Warren Scott Contracting Co.,
Stevens, in making this contract bargain, was under no disability, and the record contains nothing tending to show that this was a contract of adhesion. If a private party such as Orkin
Orkin was entitled to judgment as a matter of law, and the trial court erred in denying its motion for directed verdict and sending the case to the jury. As we are reversing the trial court, we also deny Stevens’ motion filed in this court for the award of damages against Orkin for taking a frivolous appeal.
Judgment reversed.
Notes
Before the doctrine of res ipsa loquitur is applicable, it must be shown that the accident was of a kind not ordinarily occurring in the absence of someone’s negligence; that it was caused by an instrumentality within the control of Orkin; and that plaintiff did no act contributing to the damage. The doctrine is not applicable where there is an intermediary cause which could produce the injury. Code § 38-123; Hospital Authority of City of St. Mary’s v. Eason,
Not only did Orkin not have exclusive control of the damaging instrumentality (the termites) or of the premises where the damage occurred (plaintiffs home), but more basically this court cannot say on the basis either of the record or the general knowledge of reasonable men that the occurrence or recurrence of subterranean termites is something which in the ordinary course of events would not have occurred if Orkin had used due care. See
Dissenting Opinion
dissenting. Plaintiffs complaint and evidence in this case show that on April 3,1969, plaintiff Stevens entered into
Stevens brought an action in Superior Court of Wilkes County against Orkin, and upon the trial of the case, a jury rendered a verdict for plaintiff, upon which judgment was regularly entered. During the course of the trial, defendant moved for directed verdict, and afterwards filed a motion for judgment n.o.v.
The majority opinion holds that Orkin’s motions for directed verdict and for judgment n.o.v. should have been granted and that Stevens should not have been allowed a recovery.
I disagree, and respectfully dissent for the reasons hereafter set forth.
The majority opinion, at page 365, seemingly recognizes the following correct legal principles, to wit:
1. One of two contracting parties may sue the other in tort because of the violation of a duty owed, because of the contract, as a matter of law, though not necessarily a duty arising under the contract.
2. One of two contracting parties may sue the other in tort for misfeasance (negligently, or failing to properly perform an obligation arising under the law, because of the contract) but may not sue for nonfeasance (mere failure to perform the contract, or to do that which he ought to have done).
These are correct legal principles, and I repeat, the majority seems to have recognized them as such at page 365 of the majority opinion.
But then, at page 366, the majority opinion falls into its first serious error, wherein it asserts that plaintiff, Stevens’, contentions: ". . . may be regarded as a case of nonperformance of a contract obligation, as such falls within the ambit of the above stated rule
Plaintiff did not contend or rely upon nonfeasance; to the contrary he alleged, relied upon, and proved misfeasance.
Black’s Law Dictionary defines misfeasance as "not doing a lawful act in a proper manner; omitting to do it as it should be done, ” while nonfeasance is "neglect or failure of a person to do some act which he ought to do.”
If plaintiff had alleged and proved that Orkin took his money and then failed to treat his house against termites, that would have been nonfeasance. But, to the contrary, he alleged that Orkin did treat his house against termites, but failed to do it as it should have been done, that is, did it improperly, negligently and carelessly.
Let us examine paragraph 3 of plaintiff’s complaint, which is as follows: "3. That the agents, servants and employees of defendant failed to properly treat plaintiffs house, and as a result of the carelessness and negligence of said agents, servants and employees of defendant, plaintiffs house was damaged by termites.” (Emphasis supplied.) This leaves it beyond peradventure that plaintiff contended there had been misfeasance, (not nonfeasance) and the majority simply erred in construing his action as one brought for nonfeasance.
While perhaps unnecessary to this discussion, the cases of Harper v. DeFrietas,
A case that is directly in point, and singularly enough, is against the same defendant, Orkin, is that of Orkin Termite Co. v. Duffell,
The above case is as explicit as can be. Every detail that was absent in that case was present in the Stevens case. Stevens did not contend that there was a failure to apply and inspect, etc., but contended it was not properly done, but was done carelessly and negligently. Judges Nichols, Felton and Quillian concurred.
Following this case, this court considered another action against Orkin in the case of Orkin Exterminating Co. v. Callaway,
The following authorities should help to clarify any problems of law arising in this case and clearly support Stevens’ position, to wit: In A. A. A. Parking, Inc. v. Bigger,
In E. & M. Construction Co. v. Bob,
In Rawls Brothers Co. v. Paul,
A pertinent authority on the duties that arise by law (and not merely by contract) is Frank Graham Co. v. Graham,
The following statutes are helpful on this question. Code § 105-103: "When the law requires one to do an act for the benefit of another, or to forbear the doing of that which may injure another, though no action be given in express terms, upon the accrual of damage the injured party may recover.” Code § 105-104: "Private duties may arise from statute or flow from relations created by contract, express or implied. The violation of any such specific duty, accompanied with damage, shall give a right of action.” Code Ann. § 105-106: "No privity is necessary to support an action for a tort; but if the tort results from the violation of a duty, itself the consequence of a contract, the right of action is confined to the parties and privies to that contract, except in cases where the party would have had a right of action for the injury done, independently of the contract, and except as provided in Code section 109A-2 — 318.”
The present case against Orkin was brought by Stevens because of Orkin’s misfeasance, and his recovery and the judgment of the lower court should be upheld. I therefore respectfully dissent from the majority opinion.
