Action to foreclose a mechanic’s lién. After the notice of lien had lieen filed the owner of the' real estate upon which it was sought to impress the same paid into court a sum of money sufficient to discharge the lien — there being that amount, at least, due the defendant, the general contractor. This action was subsequently brought by the assignee of the sub-contractor to recover the sum of $1,029.14, with interest from a specified -time, for extra work alleged to have been performed for, and materials furnished to, the general contractor. The plaintiff had a recovery of $562.51, with interest from April 1, 1905, from which the general contractor appeals.
We are satisfied with the correctness of the recovery, except in su far as it includes an allowance for the omission to build the bridge on Yan Dam street. In the contract which- the plaintiff’s assignor had with , the general contractor,, a bridge had to be built in front of the proposed building on Yan Dam street. After work had
Hor do we think plaintiff was entitled to interest on the amount' recovered. The claim made by her Was unliquidated and subject to a reduction—if our conclusion be correct-—of upwards-of sixty per cent. Where a party claims upwards of sixty per cent more than lie is entitled to, and the claim is unliquidated, he is not entitled " to interest upon the amount recovered. (Excelsior Terra Cotta Co. v. Harde, 90 App. Div. 4; affd., 181 N. Y. 11.)
The judgment appealed from, therefore, must be modified by . striking therefrom the difference between the amount- as above, found due. the plaintiff and the amount which the trial court found,
Patterson, P. J., Houghton, Scott and Lambert, JJ., concurred.
Judgment modified as directed in opinion, and as modified affirmed, with costs to appellant. Settle order on notice.
See Lien. Law (Laws of 1897, chap. 418), §§ 3, 9, subd. 4.— [Rep.