81 P. 575 | Or. | 1905
Lead Opinion
delivered the opinion of the court.
The position of the plaintiffs is that the proceeding in question was invalid and void for the reason that neither the resolution for the improvement, nor the ordinance therefor, provided for a continuous improvement of the street, but, on the contrary, expressly omits that part
Proceedings for the improvement of streets in a municipality at the cost of abutting property must be conducted in substantial, if not literal, compliance with the requirements of the charter; and, when the mode for its exercise is provided, it becomes the measure of the power: Bank of Columbia v. Portland, 41 Or. 5 (67 Pac. 1112). If, therefore, the charter requires the improvement of separate portions of a single street to be made under separate proceedings, the proceeding in question is void, for it shows on its face that the improvement of two portions of the street was included therein. For the city it is argued that the charter does not mean that the improvement of separate parts of the same street shall be made under separate proceedings, but that it was designed to prevent the contemplated improvement of two separate streets, or parts thereof, from being joined in one proceeding. This is a strained and unreasonable construction of the language of the charter. Section 375 provides that when the council shall deem it expedient to improve any street, or any portion thereof, it shall require from the city engineer plans, specifications, etc., and that “the improvement of each street, or part thereof, shall be made under a separate proceeding.” The charter is here dealing with but one street, and, when it provides in that connection that the improvement of each part of a street shall be made under a separate proceeding, it must refer to the improvement of a single street, and not to the joining of improvements of separate portions of different streets. This is a natural and reasonable provision, and was, no doubt, inserted for the benefit of property owners affected by a proposed improvement, and who are given the right of remonstrance
It may be argued that this construction will require each block in a street, where the intersections have been improved, to be treated as a separate part, and provided for by a separate proceeding. But the intersections may with propriety be included in or omitted from a contemplated street improvement without destroying its continuity. If the intersections have been improved, they may be considered and treated as a part of the cross-street, and not qf the street intended to be improved. But where, as in this case, the city has, by resolution, ordinance, and contract, expressly divided the street into two separate parts or portions, with entirely different classes of improvements, the proceeding must be regarded as one for the improvement of distinct portions of the street, and should be conducted as such.
The decree of the court below is reversed.
Reversed.
Decided 28 August, 1905.
Rehearing
On Motion for. Rehearing.
delivered the opinion of the court.