Orchard Hotel, LLC v. D.A.B. Group, LLCOrchard Hotel, LLC v. D.A.B. Group, LLC
Orders, Supreme Court, New York County (Bernard J. Fried, J.), entered March 30, 2012, which granted plaintiff‘s and defendants-respondents’ (additional counterclaim defendants) motions to dismiss defendant D.A.B. Group, LLC‘s counterclaims, unanimously affirmed, with costs.
D.A.B.‘s counterclaim for breach of contract alleges that Brooklyn Federal failed to fund the construction project during certain periods in 2008 and 2009. This claim is barred by an estoppel certificate executed August 26, 2010 in which D.A.B. represented and warranted that it had no claims against Brooklyn Federal and no defenses to any of its obligations under any of the loan documents.
D.A.B. also alleges two post-estoppel certificate breaches by Brooklyn Federal. The first is a breach of the building loan agreement by the failure to fund the general contractor‘s requisitions numbered 8 and 9. This claim is also refuted by documentary evidence. The subject requisitions were certified after March 1, 2011, the maturity date of the building loan. As a consequence of D.A.B.‘s default under the note at maturity, Brooklyn Federal was not obligated to make any more advances under the building loan agreement. Indeed, it was entitled to cease making any advances, without advising D.A.B. that D.A.B. was in default.
The second is a breach of a purported agreement to satisfy the mechanic‘s lien for $960,000 filed against the property by the general contractor in February 2010. Although D.A.B. did not refer to any particular written agreement, the motion court found a provision in the estoppel certificate that addresses this issue, and, on appeal, D.A.B. argues that this provision supports its claim. The provision states,
“The sum of $12,040,000 is available
to Contractor which sum may be increased by the amount, if any, by which the Cava Construction mechanic‘s lien is resolved, to the satisfaction of Lender, for a sum less than $960,000, provided that no assurances are made as to the availability of any such additional funds.”
However, as the court concluded, nothing in the provision suggests that Brooklyn Federal agreed to pay the lien.
In its third counterclaim, D.A.B. alleges that Brooklyn Federal “grossly exaggerated the amount necessary to fully satisfy the loan by miscalculating interest and purported late charges due,” as a result of which D.A.B. was unable to satisfy or obtain financing to refinance the loan. As the motion court found, even if these allegations are true, they do not fit into any cognizable legal theory. “[A] dispute as to the exact amount owed by the mortgagor to the mortgagee . . . does not preclude the issuance of summary judgment directing the sale of the mortgaged property” (Long Is. Sav. Bank of Centereach, F.S.B. v Denkensohn, 222 AD2d 659, 660 [2d Dept 1995]). Concur—Mazzarelli, J.P., Andrias, DeGrasse, Freedman and Manzanet-Daniels, JJ. [Prior Case History: 35 Misc 3d 1206(A), 2012 NY Slip Op 50576(U).]