Dear Ms. Shirley:
You have requested the opinion of this office on the following issues relating to the existing contract by the Concordia Parish Police Jury with George D. Eames for collection of solid waste in the parish. The specific questions raised are:
1. Is the contract void because of its failure to contain general change order provisions under La. R.S.
38:2212 (A)(4)?2. If not, would the extension of door-to-door service to those areas of the parish not now receiving such service under the contract require the rebidding of the contract or could this change be effected by a change order, even if such change order would result in charges in excess of $30,000?
In response to your first question I would point out that the provisions of La. R.S.
As a consequence of the above response to your first inquiry, it follows that it is not now permissible to substantially alter the provisions of the existing contract. On numerous occasions our courts have held that it is contrary to the letter and spirit of the Public Bid Law to alter the requirements of the specifications once the bids are received. HTW Transportation Co., Inc. v. New Orleans Aviation Board,
Under the circumstances, it appears that the Police Jury can either live with the current terms of the existing contract and services until the end of the contract term on November 12, 1994 or may seek to obtain the voluntary termination of the existing contract by the contractor and then proceed to solicit new bids for solid waste collection, as required by La. R.S.
I trust that this answers your inquiries. Please advise if we may be of further assistance to you.
Sincerely,
RICHARD P. IEYOUB Attorney General
BY: GLENN R. DUCOTE Assistant Attorney General
GRD:0324z