REQUESTED BY: Dear Senator:
You have asked whether section 24 of LB 795, with committee amendments found on page 840 of the Legislative Journal on February 21, 1978, could be construed to require the following projects to go through the Certificate of Need process: (1) Projects under construction prior to January 1, 1979, (2) Projects which have already undergone section 1122 review but for which construction has not commenced as of January 1, 1979, or (3) Projects which are not under construction prior to January 1, 1979, but which have undergone section 1122 review and are on appeal in the courts on January 1, 1979. We have concluded that it could. If the bill as thus amended were to become law, there are several ambiguities in it which would open it up to statutory construction.
It is a rule of statutory construction that referential and qualifying words in a statute, where no contrary intention appears, refer solely to the last antecedent. SeeHaiar v. Kessler,
It is a rule of statutory construction that where a statute enumerates the things upon which it is to operate, it is to be construed as excluding from its effect all those not expressly mentioned unless the Legislature has plainly indicated a contrary purpose or intention. See Ledwith v.Bankers Life Insurance Company of Nebraska,
It is a rule of statutory construction that a legislative act will not operate retroactively unless the legislative intent that it is to do so is clearly disclosed. SeeState ex rel. City of Grand Island v. Union Pacific RailroadCompany,
In conclusion, all the projects you have mentioned are not clearly exempted from the Certificate of Need process. Neither are all projects on which the bill may have a retroactive effect. Such exemptions as well as the first requirement for exemption under section 24(1) could be clarified by additional amendments.
