Opera House & Art Bldg. Ass'n v. Bert

52 Cal. 471 | Cal. | 1877

By the Court :

The action is forcible detainer, brought upon the third subdivision of sec. 1161 of the Code of Civil Procedure, which reads as follows : “ A tenant of real property for a term less than life is guilty of an unlawful detainer: * * * 8. When he continues in possession, in person or by sub-tenants, after a neglect or failure to perform other conditions or covenants of the lease or agreement under which the property is held than the one for the payment of rent; and three days’ notice, in writing, requiring the performance of such conditions or covenants, or the possession of the property, shall have been served upon him, and if there be a sub-tenant in actual occupation of the premises, also upon such sub-tenant. Within three days after the service of the notice the tenant, or any sub-tenant in actual occupation of the premises, or any mortgagee of the term, or other person interested in the continuance, may perform the conditions or covenants of the lease, or pay' the stipulated rent, as the case may be, and thereby save the lease from forfeiture. A tenant may take proceedings similar to those prescribed in this chapter to obtain possession of the premises let to an under-tenant, in case of his unlawful detention of the premises underlet to him.”

The alleged breach of contract is the assignment of the lease without the written consent of the lessor, as required by the terms of the instrument.

One who seeks the summary remedy allowed by the statute must bring himself clearly within its terms.

No notice in the alternative requiring the lessee to perform^ within three days any condition or covenant, or to surrender the possession of the property, was. alleged or proven. The only notice was one declaring the lease forfeited because of non*473performance of covenants other than the non-payment of rent,, and demanding possession of the demised premises forthwith.. The notice given is not as the statute prescribes, and cannot be. held to be sufficient to authorize the commencement of this action.

It is claimed, however, by plaintiff, that inasmuch as the covenant not to assign was one which could not have been performed after breach thereof, he was released from giving the notice required by the Code as a prerequisite to the commencement of the present suit. But whether the breach did or did not operate a forfeiture, which would justify ejectment, an action in the present form in the County Court can be maintained only upon a refusal to perform a covenant which can be performed after breach, and the notice contemplated by the statute.

Judgment and order reversed, and cause remanded for a new trial.