An electric utility sued two regional public transportation authorities, which are governmental entities, to condemn an easement across their land for use in constructing a transmission line approved by the Public Utility Commission (“PUC”). A divided court of appeals upheld the authorities’ assertion of governmental immunity and dismissed the case.
I
Oncor Electric Delivery Company LLC owns and operates the largest electric distribution and transmission system in Texas, delivering power over some 117,000 miles of lines to about three million homes and businesses. Oncor applied to the PUC for approval to construct a new transmission line serving Dallas County.
Oncor attempted to negotiate with the Authorities for an aerial easement and right-of-way over approximately 0.37 acres of their rail line. Although Oncor and its predecessor had successfully negotiated similar rights-of-way with DART hundreds of times before, this time the parties could not reach an agreement,
A gas or electric corporation has the right and power to enter on, condemn, and appropriate the land, right-of-way, easement, or other property of any person or corporation.7
The Authorities are governmental entities
Oncor petitioned this Court for review, and we requested briefing on the merits. But before Oncor filed its brief, the Legislature enacted House Bill 971, adding Section 37.053(d) of the Utilities Code, which provides in part:
For transmission facilities ordered or approved by the [PUC] ..., the rights extended to an electric corporation under Section 181.004 include all public land, except land owned by the state, on which the commission has approved the construction of the line.13
In its brief, Oncor argued that the court of appeals’ opinion and judgment should be vacated and the case remanded to the trial
II
We have long held,
And it is one we need not answer here because our focus instead is on Section 87.053(d). That statute provides that “the rights extended to an electric corporation under Section 181.004” — which by the latter’s terms are the rights “to enter on, condemn, and appropriate ... land, [a] right-of-way, [an] easement, or other property” — “include” certain “public land” in certain circumstances. Section 37.058(d) applies only to electric corporations, not gas corporations also covered by Section 181.004. The rights conferred do not extend to all public land but only to public land not owned by the State. And those rights exist only when construction of transmission facilities on the land is PUC-approved.
Had Section 37.053(d) gone on to state “immunity is waived”, its effect would be perfectly clear. But as we have observed, not all statutes are so explicit, and “[t]he rule requiring a waiver of governmental immunity to be clear and unambiguous cannot be applied so rigidly that the almost certain intent of the Legislature is disregarded.”
In applying the clear-and-unambiguous standard, “we must look at whether a statute makes any sense if immunity is not waived.”
Ill
The Authorities argue that the Legislature did not intend for Section 37.053(d) to apply in a case filed before it took effect and that such application would violate the constitutional prohibition against retroactive laws.
The Legislature has directed that in construing its codes, “[a] statute is presumed to be prospective in its operation unless expressly made retrospective.”
Applying the statute in this proceeding does not violate the Constitution. “The prohibition against retroactive application of laws does not apply to procedural, remedial, or jurisdictional statutes, because such statutes typically do not affect a vested right.”
Accordingly, we conclude that Section 87.053(d) applies in this ease.
IY
Finally, the Authorities argue that their property falls within Section 37.053(d)’s exception for “land owned by the state”. They concede, as they must, that they are not the State,
[[Image here]]
For these reasons, we vacate the opinion and judgment of the court of appeals and remand the case to the trial court for further proceedings.
Notes
.
. Act of May 27, 2011, 82nd Leg., R.S., ch. 949, § 1, 2011 Tex. Gen. Laws 2400, 2400 [hereinafter "House Bill 971”], codified as Tex. Util. Code § 37.053(d).
. See Tex. Util.Code §§ 37.051-37.061 (detailing the requirements for applying for a certificate of convenience and necessity from the PUC).
.A regional transportation authority "is a public political entity and corporate body [that] has perpetual succession[ ] and ... exercises public and essential governmental functions.” Tex. Transp. Code § 452.052(a).
. See Tex. Util.Code § 37.054("(a) When an application for a certificate is filed, the commission shall: (1) give notice of the application to interested parties and to the office; and (2) if requested: (A) set a time and place for a hearing; and (B) give notice of the hearing, (b) A person or electric cooperative interested in the application may intervene at the hearing.”).
. The Authorities tell us that they "do not seek to change Oncor's route ... as established by the [PUC]” and that "DART and Oncor (or its predecessor, TXU Electric Company) have entered into over 800 agreements for Oncor's lines to cross DART property without the use of eminent domain.” Respondents’ Brief on the Merits 2.
. Tex Util.Code § 181.004; see id. § 181.001 (defining "corporation” and "electric corporation” for purposes of chapter 181); id. § 181.001(2) (" ‘Electric corporation' means an electric current and power corporation.”).
. Tex. Transp. Code § 452.052(c) ("An authority is a governmental unit under [the Texas Tort Claims Act], and the operations of the authority are not proprietary functions for any purpose including the application of [the Act].”); Dallas Area Rapid Transit v. Amalgamated Transit Union Local No. 1338,
. Tex. Civ. Prac. & Rem.Code § 51.014(a)(8) (authorizing an interlocutory appeal from an order that “grants or denies a plea to the jurisdiction by a governmental unit as that term is defined in [the Texas Tort Claims Act]”).
.
. Id. at 100-106.
. Id. at 106-107.
. Tex. Util.Code § 37.053(d).
. 55 Tex.Sup.Ct.J. 2 (Sept. 30, 2011).
. Welch v. State,
. Tex. Gov’t Code § 311.034 ("In order to preserve the legislature’s interest in managing state fiscal matters through the appropriations process, a statute shall not be construed as a waiver of sovereign immunity unless the waiver is effected by clear and unambiguous language.”).
. Act of May 24, 1967, 60th Leg., R.S., ch. 455. § 1, 1967 Tex. Gen. Laws 1036, 1036, codified formerly as Tex.Rev.Civ. Stat. Ann. art. 5429b-2 and now as Tex. Gov’t Code § 311.005(2); see also Tex. Util.Code § 1.002 (providing that the Code Construction Act “applies to the construction of each provision in [the Utilities Code] except as otherwise expressly provided by [the Utilities Code]").
. Act of May 26, 2001, 77th Leg., R.S., ch. 1158, § 8, 2001 Tex. Gen. Laws 2570, 2572, codified as Tex. Gov’t Code § 311.034.
. Act approved March 25, 1911, 32d Leg., R.S., ch. 111, § 4, 1911 Tex. Gen. Laws 228, 229.
.
. Tex. Transp. Code § 452.052(a).
. We note that condemnation of public properly generally involves a number of other considerations, such as the nature of the condemnor, the scope of its authority, and an assessment of competing public uses. See generally 1 A Julius L. Sackman, Nichols on Eminent Domain § 2.17 (3d ed. 2011).
. City of LaPorte v. Barfield,
. Tooke v. City of Mexia,
. Barfield,
. Kerrville State Hosp. v. Fernandez,
. Tex. Const, art. I, § 16 (“No ... retroactive law ... shall be made.”).
. Tex. Gov’t Code § 311.022.
. House Bill 971 §§ 2(b) & 4.
. Id. § 5.
. Univ. of Tex. Sw. Med. Ctr. at Dallas v. Estate of Arancibia,
. Robinson v. Crown Cork & Seal Co.,
. Tooke v. City of Mexia,
. Cf. Monsanto Co. v. Cornerstones Mun. Util. Dist.,
. Tex. Gov’t Code § 311.021(2) (providing that, when a statute is enacted, it is presumed that “the entire statute is intended to be effective”).
. See Tex.R.App. P. 60.2(f).
