94 Kan. 38 | Kan. | 1915
The opinion of the court was delivered by
This action was brought by F. L. Olson against C. E. 0>rr and 0. Lasley to recover the possession of a two-ton Sternberg truck of the alleged
On the trial of the case in the district court there was testimony tending to show tlíat a verbal contract was entered into between Olson, Orr and Lasley about November 1, 1912, whereby a gasoline engine owned by Orr should be placed in Olson’s truck. ■ The terms of the agreement, it is claimed, were that Olson should pay Lasley $150 when the engine was installed, and pay Orr $150 ninety days after the installation of the engine was completed. There is testimony that the contract was later varied because of Olson furnishing certain material so that he became liable to pay each of the defendants $132.50 at the times previously agreed upon. It appears that the truck was completed about February 5,1913, and it is claimed by Lasley that there was then due to him $132.50, and Orr claimed that the amount of $132.50 became due to her on April 6, 1913. Olson offered testimony tending to show that the work done upon the truck was defective and did not measure up to the terms of the agreement, and that he had been compelled to. expend considerable sums of money to remedy the defects.
It is contended that Lasley was employed by Orr to install the engine, and not by Olson, and that therefore Lasley could not obtain a lien on the truck except by an employment or the consent of Olson, the owner. It appears to be conceded that Orr could not impose a lien on the truck for the debt of Lasley without the express or implied consent "of the owner. There is testimony, however, to support the claim that Olson contracted with Lasley as well as Orr, and also agreed to pay him when the work was completed. The testimony as to the negotiations between the parties indicates that
“Whenever any person shall intrüst to any mechanic, artisan or tradesman materials to so construct, alter Or repair any article of value, or any article of value to be altered or repaired, such mechanic, artisan or tradesman shall have a lien on such article, and, if the same be completed and not taken away, and his fair and reasonable or stipulated charges be not paid, may, after six months from the time such charges become due, sell the same.” (Gen. Stat. 1909, § 4808.)
The jury were told that the claims of Orr and Lasley to a lien must be established by them by a preponderance of the evidence. It appears, therefore, that the issue of whether there was a contract between Olson and each one who claimed a lien was submitted to the jury, and there is competent evidence to support the finding made by the jury.
The contention that the lien was waived by the mere stipulation that one-half of the cost of .the repairs was not to be paid until ninety days after the work was completed can not be upheld. It is argued that because the right to such a lien rests upon the right of possession, any stipulation or special contract for the delivery of possession before payment is made necessarily operates as a waiver of the right to a lien.
“The rule may how be considered as settled, that a lien may exist, although there is a. special contract, unless there is something in that contract inconsistent with such lien, or unless it-is waived expressly, or by fair implication.” (p. 115.)
The lien claimed here, however, is a statutory lien, and while the statute is, to a certain extent, declaratory of the common law, it expressly provides- that a mechanic, artisan or . tradesman may permit the owner to take the property away without the repairs having been paid for and still retain his lien, provided he files a proper statement with the register of deeds within three days. (Gen. Stat. 1909, § 4808.) Nothing in the statute indicates that the mere’ making of a special contract between the owner and artisan will defeat a lien and it can not so operate unless the writing itself expressly or impliedly waives the lien. The statutory lien is an extension of the common-law lien, as it expressly provides that a lien may be retained after the property has been delivered to the owner upon compliance with the prescribed conditions. If the property had been surrendered to the owner without payment and without compliance with the statutory requirements, the lien would, of course, have been lost.
Whether the engine was properly installed and the work completed according to the contract was the principal subject of controversy between the parties, but that dispute has been settled by the verdict of the jury.
The judgment of the district court is affirmed.