The only question argued in this case relates to the subject of damages. The defendant, as a contractor, had agreed to erect on land of another a large building in Northampton. The plaintiffs, as sub-contractors, had agreed with the defendant to furnish and set up all the marble work in the building for $3,000. A controversy afterwards arose between the defendant and the owner of the building, on account of which the defendant ordered the plaintiffs to discontinue the work and do nothing further under the contract. The defendant, having broken the contract, immediately became liable to the plaintiffs for damages, the measure of which was the difference between the sum which it would cost to complete the work in accordance with the contract and the sum which the plaintiffs were to receive. Fox v. Harding, 7 Cush. 516, 523. Amos v. Oakley, 131 Mass. 413. Cutter v. Grillette, 163 Mass. 95. Tufts v. Bennett, 163 Mass. 398. United States v. Behan, 110 U. S. 338. Masterson v. Brooklyn, 7 Hill, 61. Groodman v. Pocock, 15 Q. B. 576.
This breach which fixed the liability occurred on November 9, 1896, and two days afterwards, on November 11, this suit was brought. On the same day, whether before or after the commencement of the suit does not appear and is not material, the plaintiffs made a new contract with the owner of the building to complete the work called for by their contract with the defendant, and also to do certain other work, for a round sum agreed upon between them. The profits on this last contract, as found by the auditor, were $335.23, and the only question before us is whether the plaintiffs are to allow the amount of these profits in diminution of the damages to which they would otherwise be entitled.
The rule which is applicable to one who is under a contract to render personal services, and who, being discharged without cause before the end of his term, sues for damages, requires him, in estimating the damages, to allow for his services during the unexpired term whatever he is able to obtain for them, or if damages are assessed before the end of the term, whatever he reasonably can be expected to obtain for them during the time
We are of opinion that the ruling at the trial was erroneous, and that the plaintiffs’ damages should have been assessed without reference to their profits obtained under the new contract with the landowner. Exceptions sustained.