133 P. 89 | Or. | 1913
delivered the opinion of the court.
The matters alleged by plaintiff material to an understanding of the controversy are that the plaintiff is the owner of and in possession of a certain irrigation ditch known as the Old Mill Ditch & Irrigation Company’s ditch, having its headgate in the northwest quarter of section 4-, township 36 south, range 4 west of the Willamette meridian, Jackson County, Oregon, at a point on Evans Creek, the main canal of which ditch runs from said point to a point known as Sugar Pine gulch; that the plaintiff is the owner of a water right taken out of Evans Creek at the point aforesaid, where the water is divided and conducted through the ditch to lands of persons holding stock in plaintiff’s corporation; that for a period of 10 years immediately prior to the institution of this suit, plaintiff charges that said property has been in the actual possession of and the beneficial uses
In due time defendant appeared in said court and cause, and made answer to the complaint, and after admitting the corporate existence of plaintiff, and that he claimed an estate and interest in the irrigation ditch and water right described in plaintiff’s complaint, asserted by way of a further and separate answer that he is the owner of a tract of land in Jackson County, irrigated by means of a private ditch lateral to the one in question; that said Old Mill Ditch & Irrigation Company’s ditch has a carrying capacity of (1000) miner’s inches of water under a six-inch pressure, and that he is the absolute owner of the following interest in said' water ditch and water rights: “The perpetual right to (20) miner’s inches of water (being an opening two inches by ten inches under a pressure or head of six inches above the top of said 2x10 inch opening),” said water to be delivered to defendant from said Old Mill Ditch & Irrigation Company’s ditch to the private ditch of defendant. Defendant further alleges that during the irrigating season of each year for the past six years he has required for irrigating purposes the amount of water to which he is entitled; that he has used said water during those years without interruption, save when prevented by plaintiff in 1910, and that during all of the time plaintiff has recognized Ms right to the use of said water; that his title to the water is held by him under deeds of general warranty and mesne conveyance from the original locators and owners of said ditch to the grantors of defendant, and thence to defendant. Lastly, defendant avers that without the use of the quantity of water to which he is entitled his lands would be of little value, but
A reply denp^ig the new matter alleged in plaintiff’s answer concluded the pleadings. After a hearing was had upon the' issues, the trial court entered a decree affirming defendant’s interest in the Old Mill Ditch & Irrigation Company’s ditch and water rights as recited in defendant’s answer, and decreed that plaintiff, its officers, stockholders and successors in interest be perpetually enjoined from diverting any water from said ditch that would prevent the flow to the head of the ditch owned by defendant. Plaintiff, feeling displeased with the decree of the court, effects this appeal, assigning as- error a number of grounds, the significant ones being considered in the opinion which follows.
The facts presented show that during the month of April, 1904, plaintiff corporation was the- owner of a certain irrigation ditch euphoniously denominated the Old Mill Ditch & Irrigation Company’s ditch, having its headgate at a point on Evans Creek in the northwest quarter section 4, township 36 south, range 4 west; of the Willamette meridian in Jackson County, Oregon; that at a time contemporaneous plaintiff, for a valuable consideration to it paid, made, executed and delivered a deed to one of defendant’s predecessors in interest, containing the following description:
“The amount of 10 per cent of all water at present carried or that may hereafter be carried in said Old Mill Ditch & Irrigation Company’s ditch from and including April 15th until and including September 15th of each year, and from and including September 16th until and including April 14th of each year the amount of 16 2/3 per cent of same.”
A brief time prior to the institution of this suit plaintiff corporation attempted a reorganization, and
We do not think the decree of the court is susceptible of the construction that plaintiff is required to deliver water beyond the defendant’s ditch. This the court could not decree, for the instrument conveying the water rights simply contained the measure of defendant’s interest, apart from any legal duty with” respect to the delivery of the water beyond the private ditch of defendant.
We think the decree of the Circuit Court should be modified to conform to this opinion. Modified.