168 Ind. 593 | Ind. | 1907
Action by appellant to recover damages from appellee on account of an alleged breach of a written contract. The complaint on which the cause was finally tried alleges that the plaintiff and defendant are both incorporated companies; that on September 24, 1900, these parties entered into a written contract, a copy of which was filed with the pleading, whereby the defendant company agreed to sell and deliver to plaintiff company certain described goods, wares and merchandise, enumerated and specified in .the contract; that the amount and kind of instalment goods and wares ordered at various dates by the plaintiff and shipped to it by the defendant under the contract are all alleged and shown in the complaint; that plaintiff paid for all of these goods, and that said payments were accepted by the defendant; that the defendant, on February 22 and 28, 1901, reaffirmed the original contract, and waived any and all rights to renounce and rescind the contract upon any previous failure to pay for the goods within the time provided therein, and that the defendant recognized and affirmed the obligations of said contract on its part by accepting an order from plaintiff for the goods described in said contract.
The complaint alleges, as a breach of the contract in suit, that the plaintiff, on August 30, 1901, sent an order to the defendant for certain described goods, wares and merchandise, but the defendant, as it appears, refused to furnish these goods and wares, and by reason of its said failure the plaintiff was compelled to go into the open market to obtain the goods, and was compelled to pay for the same
The defendant answered in two paragraphs, the first being the general denial. The second alleges that the plaintiff first broke and violated the contract in suit by repeatedly failing and refusing to make payments for the goods furnished and delivered to it by the defendant under said contract, in this, to wit, by the terms and provisions thereof all goods and merchandise therein embraced were to be paid for within sixty days from the date of shipment; that plaintiff repeatedly and persistently failed and neglected to pay for the goods and wares sold and shipped within the time provided, and continued openly to violate the contract in this respect (here follow numerous specifications of the shipments of goods and wares by the defendant to the plaintiff upon the order of the latter under the contract, which, as shown, it failed and neglected to pay for until long after the expiration of the sixty days, the time within which the payments were to be made) ; that, by reason of plaintiff’s repeated violations of the contract in this respect, the defendant rescinded and repudiated said contract, and not otherwise.
The plaintiff replied to this answer in two paragraphs. The first the general denial. The second set up affirmative matter to show that after the rescission or repudiation of the contract by the defendant it waived all breaches or violations thereof by the plaintiff, and approved, ratified, and confirmed the contract in suit. Upon these pleadings the issues were joined. There was a trial by the court and a general finding in favor of the defendant, and over plaintiff’s motion for a new trial, assigning only the statutory
“The Anderson Forging Company agrees to sell and cause to be delivered, and the Ohio Valley Buggy Company agrees to buy and pay for, the following goods at the prices and terms and conditions herein named, as follows:-
4 Bow Japanned Steel Bow Sockets, per set. . .38%c 3 Bow Japanned Steel Bow Sockets, per set.. . 32%c 2% Bow Japanned Steel Rams Horn Bow Sockets,, per set.............................40c
Extension Steel Bow Sockets, Japanned, per set.45c 3 y% Bow Rams Horn 10 c per set over price of 4 Bow. Terms sixty days net, or two per cent for cash if paid between the 10th and 15th of- the following month for previous months; all goods f. o. b. Cincinnati, Ohio. The Anderson Forging Company guarantee prices against a general decline. All goods guaranteed to be up to standard in quality. Quantity of bow sockets not to exceed 2,500 sets. This contract is void after September .1, 1901.”
There are other stipulations and provisions in the contract which are not material to the question here involved, hence they are not set out.
The damages claimed by appellant, under the evidence, are based upon the breach of contract which, as alleged in the complaint and shown by the evidence, occurred on August 30, 1901, and is attributed to appellee’s failing and
The evidence in the case shows that after the execution of the contract in question the first shipment of goods thereunder was made by appellee to appellant on September 29, 1900. These goods appear to have been paid for on November 13, 1900, within the sixty days. The evidence discloses, however, that after this first shipment some six other separate and successive shipments were made, and in each and all of which appellant was in default in making payments within the time prescribed in the contract. To particularize in this respect, the' evidence shows that a shipment of goods made on October 3, 1900, was not paid until. February 15, 1901, or 135 days beyond the date of shipment. Goods that were shipped November 1, 1900, remained unpaid until February 15, 1901, 107 days beyond the date of shipment. For goods shipped November 13, 1900, appellant failed to pay until about February 15, 1901, or 94 days after the date of shipment. Goods shipped on November 30, 1900, were not paid for until March 2, 1901, 92 days beyond the date of shipment. Shipments made December 4, 1900, remained unpaid until March 2, 1901, 88 days after the date of shipment. Goods shipped December 18, 1900, were not paid for until March 2, 1901, or 73 days after shipment.
Appellant, as it appears, made and prolonged its default of payments in the face of the fact that appellee was requesting and urging payment for the goods which it had shipped and furnished. Other shipments appear to have been made as follows: January 4,1901; January 29, 1901;
performance, at the time fixed or prescribed, of the conditions or stipulations therein by the contracting party upon whom such duty rests is indispensable unless waived by said party. The party in default of the performance within the time fixed may, by reason of his default, open the way, or, in other words, give the other party the right, at his election, to rescind the contract or to refuse further to perform the conditions or stipulations therein on his part. It is certainly manifest that the contract in suit imposed upon appellee the obligation to furnish the goods at the prices specified, etc., and likewise imposed upon appellant the obligation to pay for them at the prices fixed within the time stipulated by the contract. These were mutual conditions, a compliance with which the law would exact of each party. It is, under the contract, as much of essence or substance thereof for appellant to pay for the goods within the time stipulated as it is for the appellee to furnish them as therein provided. In support of the above propositions see Cromwell v. Wilkinson (1862), 18 Ind. 365, 371; Phillips, etc., Const. Co. v. Seymour (1875), 91 U. S. 646, 23 L. Ed. 341; Norrington v. Wright (1885), 115 U. S. 188, 203, 6 Sup. Ct. 12, 29 L.
In Skehan v. Rummel, supra, this court said: “It is familiar law that where one of the parties to a contract asks its enforcement against the other party thereto, he must he able to show performance on his part, or to offer a legal excuse for his failure to perform.”
In Frankel v. Michigan, etc., Ins. Co., supra, we said: “If the appellant had himself violated the contract without legal excuse, he could not maintain an action upon it.”
In Hammond, Contracts, §463, the author, speaking in respect to a contract whereby goods are sold to he furnished or delivered and paid for in instalments, asserts that according to the weight of authority-in America the failure of the seller to deliver any one instalment, or a substantial part thereof, according to the contract, entitles the buyer to rescind and refuse to accept further instalments, and that the seller has the right to rescind in case the buyer fails to accept and pay for each instalment. In support of the right of appellee to rescind the contract and decline to furnish to appellant the goods in question, see, in addition to the authorities hereinbefore cited, McGrath v. Gegner (1893), 77 Md. 331, 26 Atl. 502, 39 Am. St. 415; Robson v. Bohn (1880), 27 Minn. 333, 7 N. W. 357; Pope v. Porter (1886), 102 N. Y. 366, 7 N. E. 304; Hill v. Blake (1884), 97 N. Y. 216 ; Rugg & Bryan v. Moore (1885), 110 Pa. St. 236, 1 Atl. 320; Bennett v. Shaughnessy (1889), 6 Utah 273, 22 Pac. 156; Reybold v. Voorhees (1858), 30 Pa. St. 116; King Philip Mills v. Slater (1880), 12 R. I. 82, 34 Am. Rep. 603; Gardner v. Clark (1860), 21 H. Y. 399; Bradley v. King (1867), 44 Ill. 339.
Mr. Bishop,- in his work on contracts, on the question of waiver,'states the rule as follows: “Waiver is where one
in possession of any right, whether conferred by law or by contract, and of full knowledge of the material facts, does or forbears the doing of something inconsistent with the existence of the right or of his intention to rely upon it; thereupon he is said to have waived it, and he is precluded from claiming anything by reason of it afterward.” Bishop, Contracts (2d ed.), §792.
It follows, under the evidence in this case and the law applicable thereto, that the finding of the court in favor of appellee was a right conclusion, and the judgment is accordingly affirmed.