137 N.Y.S. 627 | N.Y. App. Div. | 1912
The complaint in this action attempts to set forth eight causes of action growing out of two contracts for the elimination of grade crossings in the State of Connecticut, and the action, being tried before á referee, has resulted in a judgment for the plaintiffs based upon first, third, fourth and eighth causes set forth. The first cause of action is based on the allegations that the plaintiffs are copartners, doing business at Warwick, N. Y.; that the defendant is a corporation organized under the laws of the State of New York, and that on the 17th day of September, 1906, the plaintiffs and defendant entered into a contract in writing for the elimination of a certain grade cross
The second cause of action realleges the formal matters of copartnership and incorporation and alleges that “between the twenty-first day of August, 1907, and the eleventh day of November, 1907, plaintiffs performed work, labor and services for and furnished materials to the defendant at West Norfolk, Connecticut, at its request of the value of ,$1,669.96,” and that no part thereof has been paid.
This second cause of action is entirely ignored by the learned referee, who treats all of the work and materials as having been furnished under the contract above alleged, although it is apparent from the pleadings and the proofs that the work at West Norfolk was not completed at the time the creditors of the plaintiffs placed attachments upon the plant, tools and work on the 26th day of October, 1907, at which time the plaintiffs
The third cause of action realleges the ■ formal parts of the first cause of action, and avers that on the 17th day of September, 1906, the parties entered into a written contract for the elimination of a grade crossing at Winsted, Conn., under substantially the same terms and conditions of the contract here-, inbefore referred to, and that “ said contract further provided that on or about the first day of each month during the progress of the work an estimate should be made by the engineer of the defendant of the value of the part of the work done up to such time and upon his certificate of the amount being presented to the proper official of the defendant the amount of said estimate, less a retained ten per cent and less previous payments should be paid to the plaintiffs on the 20th of each month for the work done the previous month; * * * that
There is no dispute that the plaintiffs’ creditors placed attachments upon their plant, tools, etc., on the 26th day of October, 1907, and that the plaintiffs discontinued work immediately, and that subsequently the plaintiffs in a written memorandum consented that the defendant should relet the contract to other contractors, and that these contractors, using the plaintiffs’ plant and materials, under an agreement with the defendant, subsequently completed the work. The defendant has counterclaimed for the ámount which it cost to complete the work,
The evidence indicates that the defendant’s engineer had from time to time given estimates as the work progressed, and that the plaintiffs had accepted these estimates and had drawn the money upon them as provided in the contract. On or about the 11th day of November, 1907, it appears that an assistant engineer, in the absence of the engineer in charge, made up an estimate of the amount of work performed up to the time, and this estimate indicated that the amount which would be due to the plaintiffs on the 20th day of November, 1907, was $4,447,22, and it is by accepting this estimate without questioning, although there is much evidence to indicate that it is most inaccurate, that the alleged fraud is spelled out. No other fact, so far as we are able to find, is established which would in any manner tend to show that the defendant has been guilty of any fraud in the premises. The contract, it will be remembered, provided for payment upon the basis of the unit of square yards of excavation and construction of concrete work, with some other units of lesser importance, and it was provided that the defendant’s engineer should, on or about the first of each month, make an estimate of “ the value of the part of the work done up to such time,” which should form the basis of the payment to be made on the twentieth' of the month. The contract did not undertake to guarantee that the defendant’s engineer would make an absolutely accurate calculation as to the amount of work done at the time of making up the statement; the parties mutually agreed that the engineer would make up an estimate of the value of the work performed, and, in the absence of bad faith upon the part of the engineer, such estimate furnished the only basis of partial payments during the progress of the work. It is not questioned that the engineer did make these monthly estimates. It is conceded
Assuming, however, that the proper basis is the units agreed upon as the basis for the ultimate price to be paid for the work, the mere fact of an error in the estimate would not constitute any part of a fraud. The error must have been the result of design, not a mere error in judgment, and the case is absolutely barren of such evidence. So far as the evidence discloses, the defendant acted in good faith throughout the transaction, and if the engineer made a mistake in his estimate of the value of the work done at particular times, it was one of the risks which
The whole judgment appears to be based largely upon the erroneous theory that the defendant has been guilty of fraud, and as there is no, evidence from which fraud can properly be found, the judgment does not rest upon a secure foundation and should not be permitted to stand.
The judgment and order appealed from should be reversed and a new trial granted, costs to abide the final award of costs.
Jenks, P. J., Thomas, Oarr and Rich, JJ., concurred.
Judgment and order reversed and new trial granted, costs to abide the final award of costs.